This document is an amendment to Solicitation 140P8624R0012, which is a requirement by the National Park Service (Pacific West Region) to install 19 electric vehicle chargers at Fort Cronkhite in Marin County, California.
The amendment provides responses to several questions received from interested parties, including details on required utility data, soil testing, construction schedule assumptions, availability of utility plans, use of past performance questionnaires, and clarification on trench depth requirements. It also notes that all other terms and conditions of the solicitation remain unchanged.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140P8624R0012 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
PPG
San Francisco CA 94123 Building 201, Fort Mason
NPS, PWR - GOGA MABO
06/21/20240002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
05/30/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
This amendment is being issued to provide answers to the following questions received by interested parties.
Question 1: Please provide the PG&E peak demand data for the new meters to be released.
Answer 1: See attachment 15.
Question 2: Will analytical soil testing be required for any soil reused on site?
Answer 2: No. Soil may be used for backfilling.
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Liset Gomez
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140P8624R0012/0002
Question 3: For the required Construction
Schedule to be submitted with the proposal, are we to assume lead times?
Answer 3: Yes, include realistic lead times for material procurement.
Question 4: Is an existing utility plan available?
Answer 4: No.
Question 5: Are we able to use existing Past
Performance Questionnaires completed by clients for other solicitations?
Answer 5: The Past Performance Questionnaire must come from the reference, so no, previously used questionnaires cannot be used.
Please note the instructions at the top of the past performance questionnaire.
Offeror to complete Sections I and II and transmit questionnaire to reference.
Reference to complete Sections III and IV and transmit back to Contracting Specialist at robert_j_barnes@nps.gov.
Question 6: As the prime contractor, our experience and expertise are in earthwork. We will be teaming with an electrical subcontractor.
Since we are teaming, do we need to submit our past performance showing our earthwork experience in addition to having our subcontractor submit past performance showing their electrical experience? Or can we simply just include our electrical subcontractor¿s relevant experience?
Answer 6: Submit past performance for the prime contractor. Relevant experience for subcontractors is acceptable.
Question 7: The scope of work mentions that all trenching is to be 18-inches deep, but our understanding is that any locations receiving vehicle traffic should be 30-inches deep. The current alignment for trenching shows portions going through the parking lot at several different angles, so we just wanted to confirm.
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
3 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140P8624R0012/0002
Answer 7: Conduit under parking areas/driveways shall have a minimum 24 inches of cover. Conduit not under parking areas shall have a minimum 18 inches of cover. Contractor does not need to follow the exact trenching alignments shown in the solicitation and may follow a reasonable trenching alignment of their choice.
All other terms and conditions remain the same.