B08_Attachment_15_Building_Load_Sheets_0002.pdf

PDF 4 MB Posted

Attached to
GOGA INSTALL EV CHARGERS AT FORT CRONKHI
Solicitation number
140P8624R0012
Issued by

About this file

The document provided is a set of Connected Load Breakdown Sheets for various buildings at Fort Cronkhite, related to a federal contract opportunity to install 19 electric vehicle (EV) chargers at the site. The sheets detail the electrical load and capacity of the buildings, including existing single-phase and three-phase loads, as well as planned future installations of EV chargers. The federal contract opportunity, solicitation number 140P8624R0012, is for the National Park Service (NPS), Golden Gate National Recreation Area (GOGA), to install the EV chargers at Fort Cronkhite in Marin County, California. The opportunity is for civilian (non-defense) agencies, with no specific set-asides mentioned. The document does not contain a Performance Work Statement, Statement of Objectives, or other high-level details about the contract requirements beyond the EV charger installations.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Connected Load Breakdown Sheet (1 form for each unit/meter)

□ Residential □ Commercial □ House Meter Unit Descriptor/Address: Square Footage:

Individual meter panel size: _______Amps, ________Volts, ______Phase

Switch gear size: _______Amps, ________Volts, ______Phase

Single-Phase Loads

Quantity

Fill out kVA value

HP Each kVA Each

Lighting

Receptacles

Water Heater

Commercial Cooking

Refrigeration

Air Conditioning (Motors must be in HP) Electric Heating:

Miscellaneous Single phase Motors (Motors must be in HP) Resistance Welders

Arc Welders (Largest Unit)

Elevators (Motors must be in HP) Other (Describe):

Other (Describe):

Total Load (single-phase):

kVA =

HP =

Three-Phase Loads

Quantity kVA Each

HP

Each

Motor Start Soft?

(Y or N)

Locked Rotor Amps

Starting Amps

Refrigeration

Air Conditioning (Motors must be in HP) Electric Heating:

Miscellaneous 3 phase Motors (Motors must be in HP) Resistance Welders

Arc Welders * (Largest Unit)

Elevators:

(Motors must be in HP) Other (Describe):

Total Load (three-phase):

kVA =

HP =

ETCM

10/2020

TD-2056P-01-F02

Building 1066-Building Meter

200 240 1

2 1.5 3wall heater

EV Charger 2 1.4 2.8

1 2.3 2.3

1 1.5 1.5

19 0.178 3.4

22 0.18 4

Note: Renovations planned for 2023. Future load calculation on additional sheet.

1,080

EV Chargers will be removed from this service as part of the EV project.

14.2

□ Residential □ Commercial □ House Meter Unit Descriptor/Address: Square Footage:

Individual meter panel size: _______Amps, ________Volts, ______Phase

Switch gear size: _______Amps, ________Volts, ______Phase

Single-Phase Loads

Quantity

Fill out kVA value

HP Each kVA Each

Lighting

Receptacles

Water Heater

Commercial Cooking

Refrigeration

Air Conditioning (Motors must be in HP) Electric Heating:

Miscellaneous Single phase Motors (Motors must be in HP) Resistance Welders

Arc Welders (Largest Unit)

Elevators (Motors must be in HP) Other (Describe):

Other (Describe):

Total Load (single-phase):

kVA =

HP =

Three-Phase Loads

Quantity kVA Each

HP

Each

Motor Start Soft?

(Y or N)

Locked Rotor Amps

Starting Amps

Refrigeration

Air Conditioning (Motors must be in HP) Electric Heating:

Miscellaneous 3 phase Motors (Motors must be in HP) Resistance Welders

Arc Welders * (Largest Unit)

Elevators:

(Motors must be in HP) Other (Describe):

Total Load (three-phase):

kVA =

HP =

ETCM

Building 1066-EV Panel

Single EV Charger

Dual EV Charger

1 7.7

5.8

13.5

Note-EV Chargers will be installed in future project. Projected install is early 2023.

□ Residential □ Commercial □ House Meter Unit Descriptor/Address: Square Footage:

Individual meter panel size: _______Amps, ________Volts, ______Phase

Switch gear size: _______Amps, ________Volts, ______Phase

Single-Phase Loads

Quantity

Fill out kVA value

HP Each kVA Each

Lighting

Receptacles

Water Heater

Commercial Cooking

Refrigeration

Air Conditioning (Motors must be in HP) Electric Heating:

Miscellaneous Single phase Motors (Motors must be in HP) Resistance Welders

Arc Welders (Largest Unit)

Elevators (Motors must be in HP) Other (Describe):

Other (Describe):

Total Load (single-phase):

kVA =

HP =

Three-Phase Loads

Quantity kVA Each

HP

Each

Motor Start Soft?

(Y or N)

Locked Rotor Amps

Starting Amps

Refrigeration

Air Conditioning (Motors must be in HP) Electric Heating:

Miscellaneous 3 phase Motors (Motors must be in HP) Resistance Welders

Arc Welders * (Largest Unit)

Elevators:

(Motors must be in HP) Other (Describe):

Total Load (three-phase):

kVA =

HP =

ETCM

Building 1067 Panel A

.18

20 .15 3

23 4.1

1 3 3 additional lighting6 .028 0.2

10.3

2,444

□ Residential □ Commercial □ House Meter Unit Descriptor/Address: Square Footage:

Individual meter panel size: _______Amps, ________Volts, ______Phase

Switch gear size: _______Amps, ________Volts, ______Phase

Single-Phase Loads

Quantity

Fill out kVA value

HP Each kVA Each

Lighting

Receptacles

Water Heater

Commercial Cooking

Refrigeration

Air Conditioning (Motors must be in HP) Electric Heating:

Miscellaneous Single phase Motors (Motors must be in HP) Resistance Welders

Arc Welders (Largest Unit)

Elevators (Motors must be in HP) Other (Describe):

Other (Describe):

Total Load (single-phase):

kVA =

HP =

Three-Phase Loads

Quantity kVA Each

HP

Each

Motor Start Soft?

(Y or N)

Locked Rotor Amps

Starting Amps

Refrigeration

Air Conditioning (Motors must be in HP) Electric Heating:

Miscellaneous 3 phase Motors (Motors must be in HP) Resistance Welders

Arc Welders * (Largest Unit)

Elevators:

(Motors must be in HP) Other (Describe):

Total Load (three-phase):

kVA =

HP =

ETCM

10/2020

TD-2056P-01-F02

200 240 1

Dual EV Charger 7.7

Note-EV Chargers will be installed in future project. Projected install is early 2023.

Building 1067-EV Panel

15.4

□ Residential □ Commercial □ House Meter Unit Descriptor/Address: Square Footage:

Individual meter panel size: _______Amps, ________Volts, ______Phase

Switch gear size: _______Amps, ________Volts, ______Phase

Single-Phase Loads

Quantity

Fill out kVA value

HP Each kVA Each

Lighting

Receptacles

Water Heater

Commercial Cooking

Refrigeration

Air Conditioning (Motors must be in HP) Electric Heating:

Miscellaneous Single phase Motors (Motors must be in HP) Resistance Welders

Arc Welders (Largest Unit)

Elevators (Motors must be in HP) Other (Describe):

Other (Describe):

Total Load (single-phase):

kVA =

HP =

Three-Phase Loads

Quantity kVA Each

HP

Each

Motor Start Soft?

(Y or N)

Locked Rotor Amps

Starting Amps

Refrigeration

Air Conditioning (Motors must be in HP) Electric Heating:

Miscellaneous 3 phase Motors (Motors must be in HP) Resistance Welders

Arc Welders * (Largest Unit)

Elevators:

(Motors must be in HP) Other (Describe):

Total Load (three-phase):

kVA =

HP =

ETCM

Building 1068 1,300

EV Charger

Note: Unit does not currently have EV chargers. Chargers are scheduled to be installed in 2023.

3 3

0.18 2.2

0.178 3

2 7.7 15.4

23.6

□ Residential □ Commercial □ House Meter Unit Descriptor/Address: Square Footage:

Individual meter panel size: _______Amps, ________Volts, ______Phase

Switch gear size: _______Amps, ________Volts, ______Phase

Single-Phase Loads

Quantity

Fill out kVA value

HP Each kVA Each

Lighting

Receptacles

Water Heater

Commercial Cooking

Refrigeration

Air Conditioning (Motors must be in HP) Electric Heating:

Miscellaneous Single phase Motors (Motors must be in HP) Resistance Welders

Arc Welders (Largest Unit)

Elevators (Motors must be in HP) Other (Describe):

Other (Describe):

Total Load (single-phase):

kVA =

HP =

Three-Phase Loads

Quantity kVA Each

HP

Each

Motor Start Soft?

(Y or N)

Locked Rotor Amps

Starting Amps

Refrigeration

Air Conditioning (Motors must be in HP) Electric Heating:

Miscellaneous 3 phase Motors (Motors must be in HP) Resistance Welders

Arc Welders * (Largest Unit)

Elevators:

(Motors must be in HP) Other (Describe):

Total Load (three-phase):

kVA =

HP =

ETCM

Building 1069 1,275

12 0.178 2.1

13 0.180 2.3

1 2 2

3 5 5

EV Charger

Note: Unit does not currently have EV chargers. Chargers are scheduled to be installed in 2023.

26.8

□ Residential □ Commercial □ House Meter Unit Descriptor/Address: Square Footage:

Individual meter panel size: _______Amps, ________Volts, ______Phase

Switch gear size: _______Amps, ________Volts, ______Phase

Single-Phase Loads

Quantity

Fill out kVA value

HP Each kVA Each

Lighting

Receptacles

Water Heater

Commercial Cooking

Refrigeration

Air Conditioning (Motors must be in HP) Electric Heating:

Miscellaneous Single phase Motors (Motors must be in HP) Resistance Welders

Arc Welders (Largest Unit)

Elevators (Motors must be in HP) Other (Describe):

Other (Describe):

Total Load (single-phase):

kVA =

HP =

Three-Phase Loads

Quantity kVA Each

HP

Each

Motor Start Soft?

(Y or N)

Locked Rotor Amps

Starting Amps

Refrigeration

Air Conditioning (Motors must be in HP) Electric Heating:

Miscellaneous 3 phase Motors (Motors must be in HP) Resistance Welders

Arc Welders * (Largest Unit)

Elevators:

(Motors must be in HP) Other (Describe):

Total Load (three-phase):

kVA =

HP =

ETCM

Fort Cronkhite Building 1070

11 0.178 2

22 0.18 4

1 2 2

EV Charger

Note: Unit does not currently have EV chargers. Chargers are scheduled to be installed in 2023.

2,470

23.4

1066 Load sheet Commercial-Building Side
1066 Load sheet Commercial Panel B_EV Charger
1067 Panel A Load sheet Commercial (2)
1067 Load sheet Commercial Panel B_EV Charger
1068 Load sheet Commercial
1069 Load Calc Sheet
1070 Load Calc Sheet

File details come from the government source that posted it. Updated .