SAFR - 214907 01 27 00 - 1
030819 DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.01 SUMMARY
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends, and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.01 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item No. 0001 – Eppleton Hall Mooring System (Complete)
1. This item consists of all work shown in the plans and specifications, including all design/build items shown. Bid includes design/build of the Eppleton Hall Mooring System shown on the plans and described in these specifications.
2. Measurement for payment will be as a percent of work completed based on the Contractor’s submitted and approved schedule of values.
3. Payment will be made at the contract lump sum price.
B. Contract Line Item No. 0002 - Mobilization and Demobilization
1. This item consists of all work shown in the plans and specifications, including all design/build items shown. Bid includes the work identified in section 01 73 40 of the specification.
2. Measurement for payment will be as a percent of work completed based on the Contractor’s submitted and approved schedule of values.
3. Payment will be made at the contract lump sum price.
C. Contract Line Item No. 0003 – Salvage Existing Mooring System (Complete)
1. This item consists of all work shown in the plans and specifications, including all design/build items shown. Bid includes salvage of all items shown on the plans and described in these specifications.
2. Measurement for payment will be as a percent of work completed based on the Contractor’s submitted and approved schedule of values.
3. Payment will be made at the contract lump sum price.
END OF SECTION 01 27 00
| PART 1 - GENERAL |
| 1.01 SUMMARY |
| A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends, and another begins. |
| B. If no contract line item exists for a portion of the work, include the costs in a related item. |
| PART 2 - PRODUCTS (Not Used) |
| PART 3 - EXECUTION |
| 3.01 LIST OF CONTRACT LINE ITEMS |
| A. Contract Line Item No. 0001 – Eppleton Hall Mooring System (Complete) |
| 1. This item consists of all work shown in the plans and specifications, including all design/build items shown. Bid includes design/build of the Eppleton Hall Mooring System shown on the plans and described in these specifications. |
| 2. Measurement for payment will be as a percent of work completed based on the Contractor’s submitted and approved schedule of values. |
| 3. Payment will be made at the contract lump sum price. |
| B. Contract Line Item No. 0002 - Mobilization and Demobilization |
| 1. This item consists of all work shown in the plans and specifications, including all design/build items shown. Bid includes the work identified in section 01 73 40 of the specification. |
| 2. Measurement for payment will be as a percent of work completed based on the Contractor’s submitted and approved schedule of values. |
| 3. Payment will be made at the contract lump sum price. |
| C. Contract Line Item No. 0003 – Salvage Existing Mooring System (Complete) |
| 1. This item consists of all work shown in the plans and specifications, including all design/build items shown. Bid includes salvage of all items shown on the plans and described in these specifications. |
| 2. Measurement for payment will be as a percent of work completed based on the Contractor’s submitted and approved schedule of values. |
| 3. Payment will be made at the contract lump sum price. |