This document is a Section 01 27 00 defining contract line items for a project at Lehman Cave, likely for the National Park Service. The section outlines two primary contract line items: (1) Lehman Cave Lighting, Electrical, and Telecommunications Upgrades, which includes site preparation, improvements, utilities, and telecommunications infrastructure upgrades, and (2) an optional alternate ground plate electrode installation for grounding. The first line item will be paid at a lump sum contract price with no separate measurement, while the second line item will be paid per ground plate electrode instance, potentially replacing ground rods in areas where they are not feasible due to cave conditions.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GRBA PMIS 349463 (Former GRBA PMIS 311595) 01 27 00 - 1

082525 DEFINITION OF CONTRACT LINE ITEMS

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS

PART 1 - GENERAL

1.1 SUMMARY

A. Section explains in general, what is and is not included in a contract line item, and limits or cut-off points where one item ends and another begins.

B. If no contract line item exists for a portion of work, include costs in a related item.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS

A. Contract Line Item Number 1 Lehman Cave Lighting , Electrical, and

Telecommunications Upgrades

1. This item consists of Site Preparation, Site Improvements, and Site , Utilities, Site

Telecommunications, included upgraded lighting and electrical infrastructure at Lehman

Cave.

2. No separate measurement will be made on lump sum items.

3. Payment will be made at the contract lump sum price.

3.2 LIST OF CONRACT LINE ITEMS - OPTIONS

A. Contract Line Item Number 2 Alternate Ground Plate Electrodes for Grounding

1. This item consists of installing with a ground plate electrode instead of the ground rods as described on Sheet E0.2 Grounding Electrode Systems Notes. The conditions in the cave may require plate electrodes in areas where ground rods are not feasible, to be based per location.

2. Measurement for payment will be a single instance and include the credit of the costs for the ground rod in addition to the costs for installing a ground plate electrode.

3. Payment will be made at price per ground plate electrode instance.

END OF SECTION 01 27 00