Attachment_1_Statement_of_Work_FOVA_Dual_Gate_Motor_Replacement.pdf

PDF 117 KB Posted

Attached to
REPLACE DUAL GATE MOTORS Federal contract opportunity
Solicitation number
140P8326Q0051
Issued by
Department of the Interior National Park Service Pacific West Region

About this file

This is a Request for Quote (RFQ) for the replacement of dual swing gate operator motors at Fort Vancouver National Historic Site (FOVA) in Vancouver, Washington.

The contractor shall remove existing damaged gate operator motors and install two new commercial-grade dual swing gate operators, along with specified components: a ½ HP high cycle gate opener operating on standard 125V electric circuit, 4 gate edge contact sensors with wireless remotes (UL325 compliant), 2 magnetic gate locks with relay modules (one high and one low), and 1 safety edge contact sensor. The contractor must provide all labor, materials, wiring, conduit, and required hardware. Work includes integration with the existing access control system located in Building 404, programming the gate to automatically remain open during business hours (5:45 AM–5:45 PM Monday–Friday) and closed during Federal holidays, coordination with three existing LincPass card readers and punch code keypads, testing and commissioning of full open/close cycles, verification of safety systems, cleanup, and delivery of submittals, safety plans, warranty documents, operations and maintenance manuals, and a completion report. A preliminary site visit is scheduled for Wednesday, July 15, 2026 at 11:00 AM Pacific. Work hours are 7:00 AM–5:30 PM Monday through Friday, beginning after Notice to Proceed. The contractor must comply with OSHA regulations, NPS safety policy (DO#50B), and provide a minimum one-year manufacturer warranty and one-year workmanship warranty.

View the file

Other files for this federal contract opportunity

Other files attached to REPLACE DUAL GATE MOTORS, newest first.
File Type Posted
Sol_140P8326Q0051_Amd_0001.pdf PDF
Attachment_B_Forms_to_Return_with_Quote.pdf PDF
Attachment_A_Quote_Instructions.pdf PDF
Attachment_2_501_GATE_SECURITY_PLANS_04152026.pdf PDF
Attachment_3_Wage_Determination.pdf PDF
Sol_140P8326Q0051.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFQ 140P8326Q0051 Fort Vancouver NHS

Replace Dual Gate Motors

SCOPE OF WORK

Project Title: Replacement of Dual Swing Gate Operator Motors

Park Unit: Fort Vancouver National Historic Site (FOVA)

1. PURPOSE

The Scope of Work includes upgrading security by removing and installing two dual swing gate operator motors at Fort Vancouver National Historic Site. All work will adhere to NPS standards, manufacturer specifications, and applicable codes.

2. BACKGROUND

The existing gate operator motors have been damaged beyond repair and require replacement to ensure safe and reliable operation of access-controlled areas within the park.

3. LOCATION

The gate requiring motor replacement is located at 501 E 5th Street, Vancouver, WA 98661. The associated control panel is located in Building 404, which is adjacent to the gate.

4. CONTRACTOR RESPONSIBILITIES

The contractor shall furnish all labor, materials, and equipment required to remove existing units and install new dual swing motors.

4.1 Pre-Work

Attend planning meeting before beginning work to verify site conditions, submit product data sheets, provide a Job Hazard Analysis, and coordinate scheduling.

*A site visit is scheduled for Wednesday July 15, 2026 at 11:00 AM Pacific for preliminary inspection.

4.2 Removal of Existing Motors

Implement Lockout/Tagout procedures, disconnect wiring, remove motors, and inspect gate hardware for deficiencies.

4.3 Installation of New Dual Swing Motors

Provide and install two new Dual swing motors following manufacturer guidelines, integrate access control systems, and replace incompatible components. Furnish and install dual swing gate operator to open both sides of existing dual swing gate. Select commercial grade vehicular gate operators intended for high traffic and other commercial applications and designed for efficiency and consistency in both installation and function. The following specifications and components shall be considered the minimum for installation:

• ½ HP high cycle gate opener that can run on standard 125V electric circuit

• 4 gate edge contact sensors with wireless remotes along bottom of gate (UL325)

• 2 magnetic gate locks with relay module, one high and one low

• 1 Safety edge contact sensor where swing gates come together and meet

4.4 Programing New Dual Swing Motors

Connect gate operating system to existing access control system located in Building 404. It is expected that this will require coordination with the proprietary company that the access control comes from.

Three existing access control points are installed and connected to the power and data point located at the site and as shown on the plans.

Each access control point includes a LincPass card reader that is connected to the existing access control system in 404 and a punch code keypad system that shall allow us as the user to manage and change multiple passwords that will work at the three access points installed.

• Setup operation so that gate will automatically stay open during the following business hours; 5:45 am – 5:45pm Monday through Friday.

• Gate shall be setup so that it remains closed during Federal holidays.

4.5 Testing & Commissioning

Test full open/close cycles, verify safety systems, adjust limits, provide manuals, and demonstrate operation to NPS & USFS staff.

4.6 Cleanup and Final Acceptance

Remove debris, restore areas, and provide a completion report detailing work performed.

5. MATERIALS SUPPLIED BY CONTRACTOR

Contractor supplies motors, wiring, conduit, and required hardware or tools.

6. SAFETY REQUIREMENTS

Contractor must follow OSHA, NPS safety policy (DO#50B), and park safety rules; PPE and barricades required.

7. SCHEDULE

Work begins after Notice to Proceed and must be completed within the approved timeframe.

Work hours will be from 7:00 am to 5:30 pm, Monday through Friday. Site Access: Contractor shall have unlimited access to 501 E 5th Street gate area during the regular work week but will be prohibited from working on holidays and weekends. If necessary, coordinate access with the

National Park Service (NPS) and the USDA Forest Service (USDAFS) between the hours of 7

P.M. and 6 A.M., Monday through Friday.

8. WARRANTY

Minimum one-year manufacturer warranty and one-year contractor workmanship warranty.

9. DELIVERABLES

Submittals, safety plan, warranty documents, O&M manuals, and completion report.