BIG HOLE NATIONAL BATTLEFIELD
REPLACE SEWER COLLECTION PIPES
BIHO PMIS No. 186113
FINAL
CONSTRUCTION DOCUMENTS
NATIONAL PARK SERVICE
PACIFIC WEST REGION
APRIL 2019
04/30/2019
BIHO - 186113 TABLE OF CONTENTS - 1
TABLE OF CONTENTS
DIVISION 01 – GENERAL REQUIREMENTS NO. OF PAGES
01 11 00 Summary of Work 01 26 01 Contract Modification Procedures 01 27 00 Definition of Contract Price Items 01 31 00 Project Management & Coordination 01 32 16 Construction Schedule 01 33 23 Submittal Procedures 01 35 13.22 Archeological Protection 01 35 23 Safety Requirements 01 40 00 Quality Requirements 01 42 00 References 01 50 00 Temporary Facilities & Controls 01 56 00 Temporary Barriers 01 57 23 Temporary Storm Water Pollution Prevention 01 67 00 Product Requirements 01 73 40 Execution 01 74 19 Construction Waste Management & Disposal 01 77 00 Closeout Procedures Appendix A Submittal List Appendix B List of Closeout Requirements
DIVISION 02 – EXISTING CONDITIONS
02 05 10 General Site Construction Requirements 02 41 00 Demolition & Abandonment
DIVISION 03 – CONCRETE
03 30 00 Cast-In-Place Concrete 03 31 00 Normal Weight Structural Concrete
DIVISION 04 – MASONRY (Section not used)
DIVISION 05 – METALS (Section not used)
DIVISION 06 – WOOD, PLASTICS & COMPONENTS (Section not used)
BIHO - 186113 TABLE OF CONTENTS - 2
DIVISION 07 – THERMAL & MOISTURE PROTECTION (Section not used)
DIVISION 08 – OPENINGS (Section not used)
DIVISION 09 – FINISHES (Section not used)
DIVISION 10 – SPECIALTIES (Section not used)
DIVISION 11 – EQUIPMENT (Section not used)
DIVISION 12 – FURNISHINGS (Section not used)
DIVISION 13 – SPECIAL CONSTRUCTION (Section not used)
DIVISION 14 – CONVEYING EQUIPMENT (Section not used)
DIVISION 21 – FIRE SUPPRESSION (Section not used)
DIVISION 22 – PLUMBING (Section not used)
DIVISION 23 – HEATING, VENTILATING & AIR CONDITIONING (Section not used)
DIVISION 25 – INTEGRATED AUTOMATION (Section not used)
DIVISION 26 – ELECTRICAL (Section not used)
DIVISION 27 – COMMUNICATIONS (Section not used)
DIVISION 28 – ELECTRONIC SAFETY & SECURITY (Section not used)
DIVISION 31 – EARTHWORK
31 05 16 Aggregates for Earthwork 31 10 00 Site Clearing 31 23 33 Utility Excavation & Backfill 31 23 33.10 Restoration of Surfaces 31 25 00 Soil Erosion & Sedimentation Control 31 25 00.10 Watering
BIHO - 186113 TABLE OF CONTENTS - 3
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 13 13 Concrete Paving
DIVISION 33 – UTILITIES
33 00 00 Pipe & Pipe Fittings: General Statement 33 01 30 Cured-In-Place Pipe 33 05 26 Utility Line Identification Marking 33 31 13 Sanitary Sewer Pipe
DIVISION 34 – TRANSPORTATION (Section not used)
DIVISION 35 – WATERWAY & MARINE CONSTRUCTION (Section not used)
DIVISION 40 – PROCESS INTEGRATION (Section not used)
DIVISION 41 – MATERIAL PROCESSING & HANDLING EQUIPMENT (Section not used)
DIVISION 42 – PROCESS HEATING, COOLING & DRYING EQUIPMENT (Section not used)
DIVISION 43 – PROCESS GAS & LIQUID HANDLING, PURIFICATION & STORAGE
EQUIPMENT (Section not used)
DIVISION 44 – POLLUTION CONTROL EQUIPMENT (Section not used)
DIVISION 45 – INDUSTRY-SPECIFIC MANUFACTURING EQUIPMENT (Section not used)
DIVISION 46 – EQUIPMENT (Section not used)
DIVISION 48 – ELECTRICAL POWER GENERATION (Section not used)
END OF SECTION
DIVISION 01
GENERAL REQUIREMENTS
BIHO - 186113 01 11 00 - 1
SUMMARY OF WORK
SECTION 01 11 00
SUMMARY OF WORK
PART 1 – GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Work phases.
3. Work under other contracts.
4. Government Furnished Materials.
5. Contractor use of premises.
6. Public use of site.
7. Occupancy requirements for buildings.
8. Work Restrictions.
9. Special Construction Requirements.
10. Soils Investigation Report.
11. Additional Reports.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: Big Hole National Battlefield - Wisdom, Montana. Project area is adjacent to the existing Visitor Center and Staff Housing/Maintenance Facility areas.
B. The Work includes the following:
1. The Work includes replacement of approximately 500 lineal feet of existing 4” and 6” gravity sanitary sewer main with new 4”, 6” and 8” PVC piping and appurtenances by open trench method. The Work also include rehabilitation of approximately 730 lineal feet of existing 6” gravity sewer main using a Cast-In-Place-Pipe (CIPP) repair method.
Work includes completion of all necessary connections to existing sanitary sewer mains and manholes and completion of concrete surfacing repairs. Additionally, work will include the construction of all necessary wastewater bypass systems needed to maintain full wastewater service to the site throughout the construction process.
C. Project will be constructed under a single prime contract.
D. Project Contacts:
1. Contracting Officer will provide project contacts at the Contractor’s request.
BIHO - 186113 01 11 00 - 2
1.3 CONTRACTOR USE OF SITE
A. General: Contractor shall have full use of the site for construction operations during the construction period. Contractor's use of the site is limited only by the Government's right to perform work or to retain other contractors on portions of Project.
B. Construction Time Period: The project time period shall be ninety (90) calendar days following notice to proceed.
C. Storage of Materials: Confine storage of materials to within construction limits.
D. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
E. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
F. Construction Camp: Establishment of a camp within the park will not be permitted unless authorized by Contracting Officer.
G. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
1.4 PUBLIC USE OF SITE
A. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public. Closures of the project area will be permitted, when required, upon specific approval of Contracting Officer.
01 11 00 - 3
1.5 CONDUCT OF OPERATIONS
A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer. Submit requests 48 hours in advance of the work to the Contracting Officer for approval.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
1.6 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during the hours of 7:00 AM to 5:00 PM or during daylight hours between 6:00 AM to 5:30 PM defined as one half hour after sunrise to one half hour before sunset, Monday through Friday, except when otherwise indicated.
1. Weekend Hours: May be performed only with prior written consent of the contracting officer.
2. Early Morning Hours: May be performed only with prior written consent of the contracting officer.
B. Existing Utilities
1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
2. Contractor shall be responsible for locating and preventing damage to known utilities.
If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than five (5) days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer’s written permission.
3. Hours for Utility Shutdowns: Notify Contracting Officer not less than five (5) days in advance of proposed utility interruptions. Contracting Officer will coordinate specific hours acceptable for utility shutdowns.
4. Contractor will provide wastewater services in compliance with 01 50 00.
1.7 SOILS INVESTIGATION REPORT
No specific soils investigation report has been completed for the project area.
BIHO - 186113
BIHO - 186113 01 11 00 - 4
PART 2 – PRODUCTS (not used)
PART 3 – EXECUTION (not used)
BIHO - 186113 01 26 01 - 1
CONTRACT MODIFICATION PROCEDURES
SECTION 01 26 01
CONTRACT MODIFICATION PROCEDURES
PART 1 – GENERAL
1.1 SUMMARY
A. The work of this section includes administrative and procedural requirements for contract bids.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with Bids
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of bids will not be allowed. The costs for these items are to be included only in the general conditions of the bid estimate. Only in the case of a contract time extension are additional general conditions included in bids. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager, Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
6. Scheduling
BIHO - 186113 01 26 01 - 2
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the bid. These costs shall be shown as direct costs in the estimate.
The following items, if applicable, are considered allowable costs for calculating General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the bid must only be for General Conditions staff and workers actually present and working on the project site. Bid costs for salaried workers are only allowed within the structure of a forty (40) hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: This is the hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums , such as:
1) Social Security
2) Medicare
3) Workers Compensation– Policy and company calculation to be made available.
4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.
5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.
6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.
BIHO - 186113 01 26 01 - 3
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all bid proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in bid proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in bid proposals.
1.3 BID PROPOSAL PRICING REQUIREMENTS
A. General:
1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
PART 2 – PRODUCTS (not used)
BIHO – 186113 01 27 00 - 1
DEFINITION OF CONTRACT PRICE ITEMS
SECTION 01 27 00
DEFINITION OF CONTRACT LINE ITEMS
PART 1 – GENERAL
1.1 SUMMARY
A. The intent of this section is to set a schedule of values and to explain, in general, what is and what is not included in the contract and for determining whether the price set forth is fair and reasonable.
PART 2 – PRODUCTS (not used)
PART 3 – EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Price Item No.1 – Project Preliminaries.
1. This item includes Schedule of Values, Progress Schedule, Product Submittals, Safety Plan, Quality Control Plan, Designation of Onsite Supervisor & Onsite Safety Officer and any other submittals related to preparatory contract work including but not limited to items under Section 01 31 00 “Project Management & Coordination,” Section 1.3.A., Items 1 through 13.
2. No separate measurement will be made.
3. Payment will be made at the contract lump sum price.
B. Contract Price Item No. 2 – Mobilization and Demobilization
1. This price item consists of mobilization, demobilization. The government shall consider that mobilization is sixty (60) percent and demobilization is forty (40) percent of the total cost and effort for Mobilization and Demobilization.
2. No separate measurement will be made.
3. Payment will be made at the contract lump sum price.
C. Contract Price Item No. 3 – Temporary Traffic Control
1. This price item consists of providing all labor, materials and equipment to provide and maintain traffic control during the construction of the sewer force main and leachfield including flaggers, construction signage, barricades, cones, flashers, and associated labor and equipment in accordance with Government Requirements and the Manual on Uniform Traffic Control Devices complete in place.
2. No separate measurement will be made.
3. Payment will be made at the contract lump sum price.
BIHO – 186113 01 27 00 - 2
D. Contract Price Item No. 4 – Temporary Erosion and Sediment Control
1. This price item consists of providing a Under-an-Acre Pollution Prevention Plan for review and approval. Upon approval this price item includes providing all labor, materials and equipment necessary to implement the approved plan and to meet the requirements of Section 31 25 00.
2. No separate measurement will be made.
3. Payment will be made at the contract lump sum price.
DI. Contract Price Item No. 5 – 4” PVC Sanitary Sewer Collection Piping (Buried)
1. This price item consists of providing all labor, materials and equipment required to install the specified 4” PVC Sanitary Sewer Pipe to a fully functional condition as detailed in the project plans. This includes, but is not limited to, completing all required temporary bypass system construction and maintenance, completing all required excavation, removing and disposing of all pertinent existing piping and appurtenances, providing and installing all required bedding material, providing and installing the specified pipe and all required fittings, connection of the new piping to all existing structures and lateral pipes, installation and compaction of trench backfill, providing and installing the specified locate tape, completion of all required testing and completion of surface restoration in accordance with the project plans, specifications and to the satisfaction of the project CO.
2. No separate measurement will be made.
3. Payment will be made at the contract lump sum price.
DII. Contract Price Item No. 6 – 6” PVC Sanitary Sewer Collection Piping (Buried)
1. This price item consists of providing all labor, materials and equipment required to install the specified 6” PVC Sanitary Sewer Pipe to a fully functional condition as detailed in the project plans. This includes, but is not limited to, completing all required temporary bypass system construction and maintenance, completing all required excavation, removing and disposing of all pertinent existing piping and appurtenances, providing and installing all required bedding material, providing and installing the specified pipe and all required fittings, connection of the new piping to all existing structures and lateral pipes, installation and compaction of trench backfill, providing and installing the specified locate tape, completion of all required testing and completion of surface restoration in accordance with the project plans, specifications and to the satisfaction of the project CO.
2. No separate measurement will be made.
3. Payment will be made at the contract lump sum price.
DIII. Contract Price Item No. 7 – 8” PVC Sanitary Sewer Collection Piping (Buried)
1. This price item consists of providing all labor, materials and equipment required to install the specified 8” PVC Sanitary Sewer Pipe to a fully functional condition as detailed in the project plans. This includes, but is not limited to, completing all required temporary bypass system construction and maintenance, completing all required excavation, removing and disposing of all pertinent existing piping and appurtenances, providing and installing all required bedding material, providing and installing the specified pipe and all required fittings, connection of the new piping to all existing
BIHO – 186113 01 27 00 - 3
structures and lateral pipes, installation and compaction of trench backfill, providing and installing the specified locate tape, completion of all required testing and completion of surface restoration in accordance with the project plans, specifications and to the satisfaction of the project CO.
2. No separate measurement will be made.
3. Payment will be made at the contract lump sum price.
H. Contract Price Item No. 8 – 6” Cast-In-Place Pipe
1. This price item consists of providing all labor, materials and equipment required to install the specified Cast-In-Place Pipe liner to a fully functional condition. This includes, but is not limited to, completing all required temporary bypass system construction and maintenance, completing all required pipe inspection and cleaning, completing the required video inspection, completing any necessary joint grouting, completing the CIPP installation and completion of all post installation testing in accordance with the project plans, specifications and to the satisfaction of the project
CO.
2. No separate measurement will be made.
3. Payment will be made at the contract lump sum price.
I. Contract Price Item No. 9 – Concrete Paving
1. This price item consists of providing all labor, materials and equipment required to repair existing concrete paving that is damaged and/or removed during the project. This includes, but is not limited to, preparing the sub-base/base in preparation for paving, providing and placing all required form work, providing, placing and finishing the concrete and associated joint material to match existing concrete paving to provide a complete and uniform surface to the satisfaction of the project CO.
2. No separate measurement will be made.
3. Payment will be made at the contract lump sum price.
J. Contract Price Item No. 10 – Project Closeout
1. This price item includes general Division 01 administrative costs including closeout submittals and final cleanup. The contractor shall submit any and all product specifications, manufacturer’s contact information, warranties, and special maintenance instructions necessary for the successful function and operation of newly installed force main system including, but not limited to, design documents.
2. Division 01, Appendix A, Submittal List and Division 01, Appendix B, Close-out List shall be followed. The Contracting Officer shall have authority to request additional closeout submittal items in addition to the items contained in Division 01, Appendix A and Appendix B as is determined necessary to close out the project with a complete set of closeout submittal items.
3. No separate measurement will be made.
4. Payment will be made at the contract lump sum price.
BIHO – 186113 01 31 00 - 1
PROJECT MANAGEMENT & COORDINATION
SECTION 01 31 00
PROJECT MANAGEMENT & COORDINATION
PART 1 – GENERAL
1.1 SUMMARY
A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Construction Coordination.
2. Coordination Drawings.
3. Requests for Information (RFIs).
4. Project meetings.
5. Environmental Coordination.
6. Permits
B. Related Requirements:
1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.
1.2 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
BIHO – 186113
01 31 00 - 2
PROJECT MANAGEMENT & COORDINATION
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Permit requirements.
7. Pre-installation conferences.
8. Project closeout activities.
1.3 SUBMITTALS
A. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.
1. Letter designating Project Superintendent, Environmental Manager, Schedule Representative, and Pollution Prevention and Erosion Control Manager.
2. Construction Schedule.
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention Plan.
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.
7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.
8. Waste Management Plan.
9. Quality Control Plan.
10. Under-an-Acre Pollution Prevention Plan (UPPP).
11. Erosion and Sedimentation Plan
12. Temporary wastewater services plan
13. Aggregate source and weed-free certifications
B. All items listed must be provided to the Contracting Officer before the Pre-Construction Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.
1.4 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI utilizing the form as directed by the Contracting Officer.
1. Contracting Officer will not respond to RFIs submitted by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
BIHO – 186113 01 31 00 - 3
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially.
2. Date.
3. RFI subject.
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution. If Contractor's suggested resolution impacts the
Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
8. Contractor's signature.
9. Requested date for response.
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Form: Complete the RFI Form as directed by the Contracting Officer.
D. Contracting Officer’s Action: Contracting Officer will review each RFI, determine action required, and respond. Contracting Officer will determine the critical nature of each RFI and issue a response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in the Contract
Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. Contracting Officer's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.
3. Contracting Officer's action on RFIs may result in the need for a change to the Contract Time or the Contract Sum. All contract changes will be processed following the terms and conditions of the contract.
1.5 PROJECT MEETINGS
A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. The meeting agenda will include the following as a minimum:
1. Roles & Responsibilities/ Lines of Authority.
2. Park rules and regulations.
3. Jobsite Safety.
BIHO – 186113 01 31 00 - 4
4. Resolution of comments on required Division 01 documents.
5. Coordination of Subcontractors.
6. Labor law application.
7. Modifications.
8. Payments to Contractor.
9. Payroll reports.
10. Contract time.
11. Contractor Performance Evaluation.
12. Display of Hotline posters.
13. Notice to proceed.
14. Correspondence procedures.
15. Acceptance/rejection of work.
16. Progress meetings.
17. Submittal procedures.
18. NPS Final Accessibility Inspection.
19. Environmental requirements.
20. Permit requirements.
21. As-constructed drawings.
22. Saturday, Sunday, and holiday.
23. Reference materials.
24. Value engineering.
B. Progress Meetings: The Contracting Officer Representative (COR) will schedule weekly meetings with the Contractor.
1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings.
All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. The meeting agenda will include the following:
a. Approval of minutes of previous meetings.
b. Submittal status.
c. Review of off-site fabrication and delivery schedules.
d. Requests for information (RFI) and other issues.
e. Modifications.
f. Work in progress and projected.
1) Status of required inspections (Special Inspections, Accessibility, etc.)
g. Inspections of work in progress and projected (Special inspections,
h. Construction Schedule update (provide updated CPM).
i. Status of Project Record Drawings.
j. Other business relating to work.
k. Permit requirements.
BIHO – 186113 01 31 00 - 5
C. Pre-installation Conferences: Conduct a pre-installation conference at Project site before each construction activity that requires coordination with other construction.
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise Contracting Officer of scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:
a. Contract Documents.
b. Options.
c. Related RFIs.
d. Related Change Orders.
e. Purchases.
f. Deliveries.
g. Submittals.
h. Possible conflicts.
i. Compatibility requirements.
j. Time schedules.
k. Weather limitations.
l. Manufacturer's written instructions.
m. Warranty requirements.
n. Compatibility of materials.
o. Acceptability of substrates.
p. Temporary facilities and controls.
q. Space and access limitations.
r. Regulations of authorities having jurisdiction.
s. Testing and inspecting requirements.
t. Installation procedures.
u. Coordination with other work.
v. Required performance results.
w. Protection of adjacent work.
x. Protection of construction and personnel.
3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.
5. Do not proceed with installation if the conference cannot be successfully concluded.
Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.
1.6 ENVIRONMENTAL COORDINATION
A. Contractor’s Environmental Manager: Designate an on-site party responsible for overseeing the Contractor’s conformance to environmental goals for the project and implementing procedures for environmental protection.
BIHO – 186113 01 31 00 - 6
1. Qualifications: Minimum three (3) years Construction experience on projects of similar size and scope; with environmental procedures similar to those of this project; must be familiar with environmental regulations applicable to construction operations.
2. Responsibilities: Responsibilities shall include:
a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.
b. Implementation of the Waste Management Plan (WMP.)
c. Implementation of the Under-an-acre Pollution Prevention Plan.
d. Present an overview of environmental issues and summarize site specific procedures relating to management plans at the Preconstruction conference.
e. Training for Contractor personnel in accordance with their position requirements.
f. Monitoring and documentation of environmental procedures.
B. Perform project quality control in accordance with requirements specified in Related Sections, including:
1. Quality Requirements.
2. Regulatory Requirements.
3. Temporary Storm Water Pollution Prevention Environmental Management.
4. Construction Waste Management.
C. Contractor’s Environmental Training Program: Contractor shall provide environmental training for workers performing work on the project site. Training shall include the following:
1. Overview of environmental issues related to the Project.
2. Review of site specific procedures and management plans:
a. Construction Waste Management.
b. Temporary Storm Water Pollution Prevention.
D. Provide documentation for environmental procedures as specified herein and in accordance with approved Waste Management Plan and Under-an-acre Prevention Plan.
PART 2 – PRODUCTS (not used)
BIHO – 186113 01 32 16 - 1
CONSTRUCTION SCHEDULE
SECTION 01 32 16
CONSTRUCTION SCHEDULE
PART 1 – GENERAL
1.1 SUMMARY
A. This Section includes Construction Schedule requirements including but not limited to the following:
1. Schedule of Values
2. Construction Schedule Requirements.
3. Construction Schedule Updates.
4. Time Extensions.
B. Purpose: The purpose of the Construction Schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. The Construction Schedule will assist the Contractor and Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the Contractor's monthly progress payment.
1.2 DEFINITIONS
A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.
1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
B. Cost Loading: The allocation of the Schedule of Values for the completion of an activity as scheduled. The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.
C. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.
D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.
E. Float: The measure of leeway in starting and completing an activity.
1. Float: Float is not for the exclusive use or benefit of either the Government or the Contractor but is jointly owned.
BIHO – 186113 01 32 16 - 2
2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.
3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.
F. Resource Loading: The allocation of manpower and equipment necessary for the completion of an activity as scheduled.
G. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.
1.3 SUBMITTALS
A. All schedules and reports shall be submitted to the Contracting Officer Representative (COR) in either electronic and/or printed format at the discretion of the COR. It is the intent of the Government to limit the number of printed reports to only those reports determined by the project team to be essential.
B. Schedule of Values: After contract award and before the Pre-Construction conference submit a schedule of dollar values based on the Contract Price Schedule.
C. Construction Baseline Schedule: After contract award and before the Pre-Construction conference, submit two (2) paper copies of baseline schedule, large enough to show entire schedule for entire construction period.
D. CPM Reports: Concurrent with CPM schedule, submit three (3) paper copies of each of the following computer-generated reports. Format for each activity in reports shall contain activity number, activity description, resource loading, original duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float in calendar days.
1. Activity Report: List of all activities sorted by activity number and then early start date, or actual start date if known.
2. Logic Report: List of predecessor and successor tasks for all activities, sorted in ascending order by activity number and then early start date, or actual start date if known.
3. Total Float Report: List of all activities sorted in ascending order of total float.
E. Construction Schedule Updates: On or before the seventh (7th) day preceding the progress payment request date, submit estimates of the percent completion of each schedule activity and necessary supporting data. Provide two (2) paper copies.
1.4 QUALITY ASSURANCE
A. The Contractor shall meet with the Contracting Officer on the day of the preconstruction conference to go over the following:
1. Review software limitations, content and format for reports.
2. Verify availability of qualified personnel needed to develop and update schedule.
3. Discuss constraints, including phasing work stages area separations and interim milestones.
BIHO – 186113 01 32 16 - 3
4. Review time required for review of submittals and re-submittals.
5. Review requirements for tests and inspections by independent testing and inspecting agencies.
6. Review time required for completion and startup procedures.
7. Review and finalize list of construction activities to be included in schedule.
8. Review baseline schedule comments, resolve issues and progress on incorporating them
9. Review procedures for updating schedule.
10. Discuss reporting requirements and establish a protocol for naming and transmitting electronic schedules.
B. Contractor's Schedule Representative: Before or at the preconstruction conference, designate an authorized representative to be responsible for the preparation and maintenance of the Construction Schedule. A resume outlining the qualifications of the Scheduler shall be submitted to the Contracting Officer for acceptance. The Scheduler shall have prepared and maintained at least five (5) previous schedules of similar size and complexity similar to this Contract, demonstrating proficiency in the use of scheduling software. The authorized representative will be responsible for preparing the Baseline Schedule, all required updates, revisions, Time Impact Analyses, and preparation of reports.
1.5 COORDINATION
A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate Contractors.
B. Coordinate Construction Baseline Schedule with the Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.
1. In developing the Construction Baseline Schedule, ensure that the Subcontractor’s work at all tiers, as well as the prime Contractor’s work, is included and coordinated.
2. Secure time commitments for performing critical elements of the Work from parties involved.
3. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.
PART 2 – PRODUCTS
2.1 SCHEDULE OF VALUES
A. Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. Include mobilization, general condition costs, overhead and profit in the total dollar value of unit price items and in the component work activities for each lump-sum item. Do not include mobilization, general condition costs, overhead or profit as a separate item.
B. Do not break down unit price items. Use only the contract price for unit price items.
BIHO – 186113 01 32 16 - 4
C. The total cost of all items shall equal the contract price. The Schedule of Values will form the basis for progress payments.
D. An acceptable Schedule of Values shall be agreed upon by the Contractor and Contracting Officer before the first progress payment is processed.
2.2 CONSTRUCTION SCHEDULE REQUIREMENTS
A. Construction Baseline Schedule: Prepare Construction Baseline Schedule using a computerized, resource-loaded, time-scaled CPM network analysis diagram for the Work.
1. Develop and finalize Construction Baseline Schedule so it can be accepted for use no later than ninety (90) days after date established for the Notice of Award.
a. Failure to include any work item required for performance of this Contract shall not excuse Contractor from completing all work within applicable completion dates, regardless of Governments acceptance of the schedule.
2. Establish procedures for monitoring and updating Construction Baseline Schedule and for reporting progress. Coordinate procedures with progress meeting and payment request dates.
B. Construction Baseline Schedule Preparation: Prepare a list of all activities required to complete the Work. Using the preliminary CPM network diagram, prepare a skeleton network to identify probable critical paths.
1. Activities: Indicate the estimated duration, sequence requirements, and relationship of each activity in relation to other activities.
2. Critical Path Activities: Identify critical path activities, including those for interim completion dates. Scheduled start and completion dates shall be consistent with Contract milestone dates.
3. Processing: Process data to produce output data on a computer-drawn, time-scaled network. Revise data, reorganize activity sequences, and reproduce as often as necessary to produce the CPM schedule within the limitations of the Contract Time.
4. The Construction Baseline Schedule as developed shall show the sequence and interdependence of activities required for complete performance of the work. Ensure all work sequences are logical and the Construction Baseline Schedule shows a coordinated plan of the work.
5. Resource loading of each activity shall include all personnel by labor category and equipment type and capacity proposed to complete the activity in the duration shown.
6. Consider seasonal weather conditions in planning and scheduling all work influenced by high and low ambient temperatures, wind, or precipitation to ensure completion of all work within the contract time.
7. Time Frame: Proposed duration assigned to each activity shall be the Contractor's best estimate of time required to complete the activity considering the scope and resources planned for the activity.
a. An early finish date may be shown but the late finish date must be the same date as the last day of the contract period. An early completion schedule must contain the following:
1) Insert an activity titled “Project Float” as a successor to the last activity in the early project completion schedule network.
BIHO – 186113 01 32 16 - 5
2) Add a milestone titled “Contract End Date” as a successor to the activity “Project Float”.
3) Add duration to the activity “Project Float” as required so the milestone “Contract End Date” equals the last day of the Contract Period.
b. Contract completion date shall not be changed by submission of a schedule that shows an early completion date.
c. The Contractor shall limit use of lead or lag duration’s between schedule activities.
d. Project Calendars: Develop and incorporate the following calendars:
1) Administrative Calendar: Include a calendar that is based on a seven (7) day week to be used on any activities that are based on calendar days. Apply this calendar to administrative tasks or any other tasks that are not affected by non-working days (Federal Holidays, weather, etc.).
2) Project Calendar: Include a calendar that is based on the planned work week for the project. Include Federal Holidays, weekends, and any other non-work days indicated in the contract documents. Apply this calendar to activities which are not anticipated to be affected by weather.
3) Weather Calendar: Utilize the Project Calendar and show anticipated normal downtime related to weather as non-working time. Weather days shall be based on data for the local area from a reliable source like the National Oceanic and Atmospheric Administration (NOAA), National Park Service records, or source acceptable to the Contracting Officer. Apply this calendar to activities that are anticipated to be affected by weather.
e. Activity Duration: Define activities so no activity is longer than fifteen (15) days, except for non-construction activities including mobilization, shop drawings and submittals, fabrication and delivery of materials and equipment.
f. Submittal Review Time: Include review and re-submittal times indicated.
Coordinate submittal review times in Construction Baseline Schedule.
g. Substantial Completion: Allow time for Government administrative procedures necessary for certification of Substantial Completion. (For more information, refer to Division 01 Specification 01 77 00 “Closeout Procedures.”)
8. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule, and show how the sequence of the Work is affected.
a. Phasing: Arrange list of activities on schedule by phase.
b. Work under More Than One Contract: Include a separate activity for each contract.
c. Work Restrictions: Show the effect of the following items on the schedule:
1) Coordination with existing construction.
2) Uninterruptible services.
3) Use of premises restrictions.
4) Provisions for future construction.
5) Seasonal variations.
6) Environmental control.
d. Work Stages: Indicate important stages of construction for each major portion of the Work.
1) Subcontract awards.
2) Submittals.
3) Purchases.
4) Mockups.
5) Fabrication.
6) Sample testing.
BIHO – 186113 01 32 16 - 6
7) Deliveries.
8) Installation.
9) Tests and inspections.
10) Adjusting.
11) Curing.
e. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to, the Notice to Proceed, Substantial Completion.
C. Joint Review, Revision, and Acceptance:
1. Within seven (7) calendar days of…