This document is a solicitation for a construction contract to rehabilitate restrooms at Hawaii Volcanoes National Park. The solicitation includes a base requirement to rehabilitate restrooms at the Nahuku, Historic Thurston Lava Tube location, and an option to rehabilitate restrooms at the Chain of Craters Road location. The government will evaluate offers based on determining the best value, and may award the base requirement, the option, or a combination of the two. Pricing will be evaluated on a firm-fixed-price basis. The work is subject to Davis-Bacon wage rates. The solicitation has a closing date of February 5, 2024, and the contract completion period is 330 calendar days from the notice to proceed. This is a small business set-aside contract.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation 5 Feb 2024 Document No.
140P8224R0002 Document Title Hawaii Volcanoes National Park Rehabilitate Restrooms, PMIS #334178 and 236497
TABLE OF CONTENTS
| PART I – THE SCHEDULE | 8 |
| SECTION A – SOLICITATION / CONTRACT FORM | 8 |
| SECTION B – BID SCHEDULE | 9 |
| SECTION C – SPECIFICATIONS / DRAWINGS | 10 |
| SECTION D – PACKAGING AND MARKING | 10 |
| SECTION E – INSPECTION AND ACCEPTANCE | 10 |
| 52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996) | 10 |
| SECTION F – DELIVERIES OR PERFORMANCE | 11 |
| CLAUSES INCORPORATED BY REFERENCE | 11 |
| 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) | 11 |
| 52.242-14 SUSPENSION OF WORK (APR 1984) | 12 |
| SECTION G – CONTRACT ADMINISTRATION DATA | 12 |
| CONTRACT ADMINISTRATION | 12 |
| CORRESPONDENCE | 12 |
| APPOINTMENT OF CONTRACTOR REPRESENTATIVE/SUPERINTENDENT | 13 |
| 1452.201-70 AUTHORITIES AND DELEGATIONS (SEP 2011) | 13 |
| 1452.204-70 RELEASE OF CLAIMS—DEPARTMENT OF THE INTERIOR (Jul 1996) | 14 |
| CONSTRUCTION CONTRACT ADMINISTRATION | 14 |
| NOTICE TO CONTRACTORS – CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM (DEC 2015) | 14 |
| ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS – INVOICE PROCESSING PLATFORM (APR 2013) | 15 |
| SECTION H – SPECIAL CONTRACT REQUIREMENTS | 16 |
| WAGE RATES | 16 |
| WORKERS COMPENSATION | 16 |
| SITE SPECIFIC SAFETY AND HEALTH PLAN | 16 |
| PART II – CONTRACT CLAUSES | 18 |
| SECTION I – CONTRACT CLAUSES | 18 |
| CLAUSES INCORPORATED BY REFERENCE | 18 |
| 1452.203-70 RESTRICTIONS ON ENDORSEMENTS (JUL 1996) | 20 |
| 52.219-14 LIMITATIONS ON SUBCONTRACTING. LIMITATIONS ON SUBCONTRACTING DEVIATION OCT 2022) | 21 |
| 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN 2020) | 23 |
| 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022) | 23 |
| 1452.228-70 LIABILITY INSURANCE (JUL 1996) | 27 |
| 1452.236-70 PROHIBITION AGAINST USE OF LEAD-BASED PAINT (JUL 1996) | 28 |
| 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 28 |
| PART III – LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS | 28 |
| SECTION J – LIST OF ATTACHMENTS | 28 |
| PART IV – REPRESENTATIONS AND INSTRUCTIONS | 28 |
| SECTION K – REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS OF OFFERORS | 28 |
| 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2023) | 28 |
| 52.204-24 REPRESENTATIONS REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES AND EQUIPMENT (NOV 2021) | 32 |
| 52.204-26 COVERED TELECOMMUNICATIONS EQUIPMENT OR SERVICES-REPRESENTATION (OCT 2020) | 34 |
| 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018) | 35 |
| 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS-CERTIFICATION (NOV 2021) | 36 |
| SECTION L – INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS | 38 |
| PROVISIONS INCORPORATED BY REFERENCE | 38 |
| 1452.215-71 USE AND DISCLOSURE OF PROPOSAL INFORMATION—DEPARTMENT OF THE INTERIOR (APR 1984) | 38 |
| 52.216-1 TYPE OF CONTRACT (APR 1984) | 39 |
| 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999) | 39 |
| 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT – CONSTRUCTION MATERIALS (MAY 2014) | 40 |
| 52.228-1 BID GUARANTEE (SEP 1996) | 41 |
| 52.233-2 SERVICE OF PROTEST DEPARTMENT OF THE INTERIOR (JUL 1996) (DEVIATION) | 41 |
| 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)–ALTERNATE I (FEB 1995) | 42 |
| 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 42 |
| 52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (NOV 2020) | 43 |
| INSTRUCTIONS FOR THE SUBMISSION OF OFFERS AND OTHER INFORMATION – COMPETITIVE SOURCE SELECTION | 44 |
| RESPONSIBILITY DETERMINATION | 49 |
| SECTION M – EVALUATION FACTORS FOR AWARD | 50 |
PART I – THE SCHEDULE
SECTION A – SOLICITATION / CONTRACT FORM
Solicitation, Offer, and Award (SF 1442) - pages 1- 4 of this package.
SECTION B – BID SCHEDULE
SOLICITATION NUMBER: 140P8224R0002
PARK - PMIS: Hawaii Volcanoes National Park, PMIS 334178 and 236497
POJECT TITLE: Rehabilitate Restrooms
Offerors are required to submit, at a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all option line items. Failure to do so may render the proposal unacceptable. For any lump-sum line items, provide the total price only. For any unit-priced line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of summation error, the total corrected amounts govern. Round totals & extended prices to whole dollars.)
Evaluation of Options. The Government reserves the right to award any or no options at or after the time of award. At the option of the Government, the period for exercise of options at the proposed prices shall extend throughout the entire period of performance. Pricing will be evaluated based on what is determined to be the best value to the Government. Options may be exercised in any combination, order, or grouping deemed in the judgment of the Contracting Officer to offer the best value to the Government.
| CONTRACT LINE ITEM NUMBER (CLIN) |
| CONTRACT LINE ITEM (CLI) TITLE |
| QUANTITY |
| UNIT OF MEASURE |
| UNIT PRICE |
| TOTAL PRICE |
| 10 |
| Rehabilitate the Restrooms at Nahuku, Historic Thurston Lava Tube. PMIS 236497 |
| 1 |
| LS |
| 20 |
| Option-Rehabilitate the Restrooms at Chain of Craters Rd. PMIS 334178 |
| 1 |
| LS |
TOTAL BASE PRICE (Contract Line Item Number 10 through 20) ------------------------------------
All measurement and payment information is included in Division 01 Specifications Section 01 27 00 Definition of Contract Line Items.
SECTION C – SPECIFICATIONS / DRAWINGS
Specifications and site maps are attached and incorporated herein by reference. Refer to section J.
SECTION D – PACKAGING AND MARKING
No clauses included.
SECTION E – INSPECTION AND ACCEPTANCE
52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)
(a) Definition. “Work” includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not—
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.
(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may—
(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or
(2) Terminate for default the Contractor’s right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.
(End of clause)
SECTION F – DELIVERIES OR PERFORMANCE
CLAUSES INCORPORATED BY REFERENCE
The following contract clauses pertinent to this section are incorporated by reference (by Citation Number, Title, and Date) per the clause at FAR “52.252-2 CLAUSES INCORPORATED BY REFERENCE” in Section I of this contract. See FAR 52.252-2 for an internet address (if specified) for electronic access to a clause’s full text.
52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS (APR 1984)
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within ____7____ calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than ______330______ calendar days after the date the Contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.
(End of clause)
52.242-14 SUSPENSION OF WORK (APR 1984)
(a) The Contracting Officer may order the Contractor, in writing, to suspend, delay, or interrupt all or any part of the work of this contract for the period of time that the Contracting Officer determines appropriate for the convenience of the Government.
(b) If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted (1) by an act of the Contracting Officer in the administration of this contract, or (2) by the Contracting Officer’s failure to act within the time specified in this contract (or within a reasonable time if not specified), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by the unreasonable suspension, delay, or interruption, and the contract modified in writing accordingly. However, no adjustment shall be made under this clause for any suspension, delay, or interruption to the extent that performance would have been so suspended, delayed, or interrupted by any other cause, including the fault or negligence of the Contractor, or for which an equitable adjustment is provided for or excluded under any other term or condition of this contract.
(c) A claim under this clause shall not be allowed—
(1) For any costs incurred more than 20 days before the Contractor shall have notified the Contracting Officer in writing of the act or failure to act involved (but this requirement shall not apply as to a claim resulting from a suspension order); and
(2) Unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of the suspension, delay, or interruption, but not later than the date of final payment under the contract.
(End of clause)
SECTION G – CONTRACT ADMINISTRATION DATA
CONTRACT ADMINISTRATION
The Contracting Officer's Representative (COR) for this contract will be:
James Sutton Facilities Manager Hawaii Volcanoes National Park
| 808-985-6055 |
| James_Sutton@nps.gov |
The Contracting Officer (CO) with overall responsibility for this contract will be:
| Michael Davidson |
| Contracting Officer |
| 808-285-1885 |
| Michael_Davidson@nps.gov |
(End of Clause)
CORRESPONDENCE
Copies of all correspondence and written notices between the Contracting Officer’s Representative and the Contractor shall be sent to the cognizant Contracting Officer at the email address below. All correspondence shall state the contract number in the subject line of the email.
| Michael Davidson |
| Contracting Officer |
| 808-285-1885 |
| Michael_Davidson@nps.gov |
(End of Clause)
APPOINTMENT OF CONTRACTOR REPRESENTATIVE/SUPERINTENDENT
Prior to commencement of work on this contract, the contractor shall provide to the Contracting Officer, the name and telephone number of at least one responsible individual who will serve to respond to operational problems and/or emergencies on a daily basis. The contractor agrees that notice to the designated representative shall constitute notice to the contractor and agrees to be bound by any commitments or representations made by the representative.
(End of Clause)
1452.201-70 AUTHORITIES AND DELEGATIONS (SEP 2011)
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer’s Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor’s performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
€ The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the Contractor’s right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR’s appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph € prior to receipt of the Contracting Officer’s response issued under paragraph € of this clause.
€ The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor’s risk.
(End of clause) 1452.204-70 RELEASE OF CLAIMS—DEPARTMENT OF THE INTERIOR (Jul 1996) After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (DI–137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.
(End of clause)
CONSTRUCTION CONTRACT ADMINISTRATION
Federal Acquisition Regulation (FAR) 36.211(b) requires agencies provide description of policies and procedures that apply to definitization of equitable adjustments for change orders under construction contracts and data on the time required to definitize equitable adjustments for change orders under construction contracts. This information can be found at: https://www.doi.gov/pam/acquisition/policy/constructioncontract.
(End of clause) NOTICE TO CONTRACTORS – CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM (DEC 2015)
1. FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.
2. The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action.
3. We request that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official (AO). Information in the report must be protected as source selection sensitive information not releasable to the public.
4. When your Contractor Representative(s) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.gov/.
5. Within 60 days after the end of a performance period, the AO will complete an interim or final past performance evaluation, and the report will be accessible at https://www.cpars.gov/.
a. Contractor Representatives may then provide comments in response to the evaluation, or return the evaluation without comment.
b. Your comments should focus on objective facts in the AO's narrative and should provide your views on the causes and ramifications of the assessed performance.
c. All information provided should be reviewed for accuracy prior to submission.
d. If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating "No comment" in the space provided, and then selecting “Accept the Ratings and Close the Evaluation”.
e. Your response is due within 60 calendar days after receipt of the CPAR. On day 15, the evaluation will become available in PPIRS-RC marked as “Pending” with or without comments and whether or not it has been closed.
f. If you do not sign and submit the CPAR within 60 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment."
6. The following guidelines apply concerning your use of the past performance evaluation:
a. Protect the evaluation as source selection information. After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the CO for instructions.
b. Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.
c. Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determinations, production readiness reviews, or other similar purposes.
7. If you wish to discuss a past performance evaluation, you should request a meeting in writing to the CO no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 60-day review period.
8. A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.
(End of Notice) ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS – INVOICE PROCESSING PLATFORM (APR 2013) Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP).
"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract. The IPP website address is: https://www.ipp.gov.
The Contractor shall submit a draft Invoice Package, including copies of the following documents, to the National Park Service’s (NPS) Contracting Officer’s Representative (COR), with a copy to the Contracting Officer, a minimum of 5 working days prior to submittal of the formal Invoice through IPP. Within 5 working days of receipt, the COR shall provide an acceptability recommendation to both the NPS Contracting Officer (CO) and the Contractor. If the COR recommends acceptance, the Contractor shall submit a copy of the final version of the COR’s checklist and the Invoice Package to the NPS through IPP.
1. Completed copy of the COR’s final Construction Payment Request Checklist (Submit only with the formal submittal to IPP)
2. Completed copy of the Pay Estimate Form (including signed certification of subcontractor payments as required by contract clause 52.232-5)
3. Completed copy of the Limitations on Subcontracting Report
4. Certified copies of Payroll Reports per Contract clause 52.222-8 Payrolls and Basic Records.
5. Completed copy of the Payroll Report PII Certification sheet
6. Information required by contract clause 52.232-27, Prompt Payment for Construction Contracts
7. A copy of the current construction schedule
8. A copy of the current Schedule of Values
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal.
(End of Clause)
SECTION H – SPECIAL CONTRACT REQUIREMENTS
(End of Clause)
WAGE RATES
Davis-Bacon Wage Rates apply for this project and are attached to this solicitation (See Section J). The project is located in Hawaii Volcanoes National Park, Hawaii.
(End of Clause)
WORKERS COMPENSATION
The Contractor is required to be insured against liability for workmen's compensation or to undertake self-insurance in accordance with the provisions of the Section 3700 of the Labor Code of the State of Hawaii. Evidence of coverage is required before commencement of project work.
(End of Clause)
SITE SPECIFIC SAFETY AND HEALTH PLAN
A site specific safety and health plan shall be prepared covering on-site work to be performed by the contractor and all subcontractors. The prime contractor shall be responsible for development, implementation, and oversight of the site specific plan. The site specific safety and health plan shall establish in detail, the protocols necessary for recognition, evaluation, and control of hazards associated with each task performed. The plan shall address site specific safety and health requirements and procedures based upon site specific conditions. The level of detail provided in the site specific safety and health plan shall be tailored to the type of work, complexity of operations to be performed, and hazards anticipated. The site specific safety and health plan shall address, in as much detail as possible, anticipated tasks, their related hazards, and anticipated control measures.
As work proceeds, the site specific safety and health plan shall be adapted to new situations and new conditions. Changes and modifications to the accepted site specific safety and health plan shall be made with the knowledge and concurrence of the safety office, site superintendent, and contracting office. Should any unforeseen hazard become evident during the performance of work, the contractor shall bring such hazard to the attention of the safety office and COR, both verbally and in writing for resolution as soon as possible. In the interim, necessary action shall be taken to re-establish and maintain safe working conditions in order to safeguard on-site personnel, visitors, the public, and the environment.
Prior to submittal to the COR, the site specific safety and health plan shall be signed and dated by the prime contractor's safety and health manager and site superintendent. The site specific safety and health plan shall be part of the contractor's safety and Health program. The contractor shall submit to the COR the contractor's site specific safety and health plan for review and approval by the safety office.
Work performed under this contract shall comply with applicable federal, state, and local safety and occupational health laws and regulations. This includes, but is not limited to, Occupational Safety and Health Administration (OSHA) standards, 29 CFR, Part 1910 and Part 1926. Where the requirements of applicable laws, criteria, ordinances, regulations, and referenced documents vary the most stringent requirements shall apply.
(End of Clause)
EVALUATION OF OPTIONS
The Government reserves the right to award any or no options at or after the time of award. At the option of the Government, the period for exercise of options at the proposed prices shall extend 365 calendar days from the date of award. Pricing will be evaluated based on what is determined to be the best value to the Government. Options may be exercised in any combination, order, or grouping deemed in the judgment of the Contracting Officer to offer the best value to the Government.
(End of clause)
PART II – CONTRACT CLAUSES
SECTION I – CONTRACT CLAUSES
CLAUSES INCORPORATED BY REFERENCE
The following contract clauses pertinent to this section are incorporated by reference (by Citation Number, Title, and Date) per the clause at FAR “52.252-2 CLAUSES INCORPORATED BY REFERENCE” in Section I of this contract. See FAR 52.252-2 for an internet address (if specified) for electronic access to a clause’s full text.
| 52.202-1 | DEFINITIONS (JUN 2020) |
| 52.203-3 | GRATUITIES (APR 1984) |
| 52.203-5 | COVENANT AGAINST CONTINGENT FEES (MAY 2014) |
| 52.203-6 | RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT (JUN 2020) |
| 52.203-7 | ANTI-KICKBACK PROCEDURES (JUN 2020) |
| 52.203-8 | CANCELLATION, RECESSION, AND RECOVERY OF FUNDS FOR ILLEGAL OR IMPROPER ACTIVITY (MAY 2014) |
| 52.203-10 | PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY (MAY 2014) |
| 52.203-12 | LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS (JUN 2020) |
| 52.203-17 | CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS AND REQUIREMENT TO INFORM EMPLOYEES OF WHISTLEBLOWER RIGHTS (JUN 2020) |
| 52.203-19 | PROHIBITION ON REQUIRING CERTAIN INTERNAL CONFIDENTIALITY AGREEMENTS OR STATEMENTS (JAN 2017) |
| 52.204-4 | PRINTED OR COPIED DOUBLE SIDED ON POSTCONSUMER FIBER CONTENT PAPER (MAY 2011) |
| 52.204-10 | REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT AWARDS (JUN 2020) |
| 52.204-13 | SYSTEM FOR AWARD MANAGEMENT MAINTENANCE (OCT 2018) |
| 52.204-14 | SERVICE CONTRACT REPORTING REQUIREMENTS (OCT 2016) |
| 52.204-18 | COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE (AUG 2020) |
| 52.204-19 | INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) |
| 52.204-23 | PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES (NOV 2021) |
| 52.204-25 | PROHIBITION ON CONTRACTING FOR CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021) |
| 52.209-6 | PROTECTING THE GOVERNMENT’S INTEREST WHEN SUBCONTRACTING WITH CONTRACTOR’S DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT (NOV 2021) |
| 52.209-9 | UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018) |
| 52.209-10 | PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC CORPORATIONS (NOV 2015) |
| 52.215-2 | AUDIT AND RECORDS-NEGOTIATIONS (JUN 2020) |
| 52.215-8 | ORDER OF PRECEDENCE - UNIFORM CONTRACT FORMAT (OCT 1997) |
| 52.219-6 | NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (NOV 2021) |
| 52.219-8 | UTILIZATION OF SMALL BUSINESS CONCERNS (OCT 2018) |
| 52.219-28 | POST AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (SEP 2021) |
| 52.222-3 | CONVICT LABOR (JUN 2003) |
| 52.222-4 | CONTRACT WORK HOURS AND SAFETY STANDARDS-OVERTIME COMPENSATION (MAY 2018) |
| 52.222-6 | CONSTRUCTION WAGE RATE REQUIREMENTS (AUG 2018) |
| 52.222-7 | WITHHOLDING OF FUNDS (MAY 2014) |
| 52.222-8 | PAYROLLS AND BASIC RECORDS (JUL 2021) |
| 52.222-9 | APPRENTICES AND TRAINEES (JUL 2005) |
| 52.222-10 | COMPLIANCE WITH COPELAND ACT REQUIREMENTS (FEB 1988) |
| 52.222-11 | SUBCONTRACTS (LABOR STANDARDS) (MAY 2014) |
| 52.222-12 | CONTRACT TERMINATION - DEBARMENT (MAY 2014) |
| 52.222-13 | COMPLIANCE WITH CONSTRUCTION WAGE RATE REQUIRMENTS AND RELATED REGULATIONS (MAY 2014) |
| 52.222-14 | DISPUTES CONCERNING LABOR STANDARDS (FEB 1988) |
| 52.222-15 | CERTIFICATION OF ELIGIBILITY (MAY 2014) |
| 52.222-21 | PROHIBITION OF SEGREGATED FACILITIES (APR 2015) |
| 52.222-26 | EQUAL OPPORTUNITY (SEP 2016) |
| 52.222-27 | AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR CONSTRUCTION (APR 2015) |
| 52.222-35 | EQUAL OPPORTUNITY FOR VETERANS (JUN 2020) |
| 52.222-37 | EMPLOYMENT REPORTS ON VETERANS (JUN 2020) |
| 52.222-40 | NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT (DEC 2010) |
| 52.222-50 | COMBATING TRAFFICKING IN PERSONS (NOV 2021) |
| 52.222-54 | EMPLOYMENT ELIGIBILITY VERIFICATION (MAY 2022) |
| 52.222-55 | MINIMUM WAGES FOR CONTRACTOR WORKERS UNDER EXECUTIVE ORDER 14026 (JAN 2022) |
| 52.222-62 | PAID SICK LEAVE UNDER EXECUTIVE ORDER 13706 (JAN 2022) |
| 52.223-2 | AFFIRMATIVE PROCUREMENT OF BIOBASED PRODUCTS UNDER SERVICE AND CONSTRUCTION (SEP 2013) |
| 52.223-5 | POLLUTION PREVENTION AND RIGHT-TO-KNOW INFORMATION (MAY 2011) |
| 52.223-6 | DRUG-FREE WORKPLACE (MAY 2001) |
| 52.223-15 | ENERGY EFFICIENCY IN ENERGY-CONSUMING PRODUCTS (MAY 2020) |
| 52.223-17 | AFFIRMATIVE PROCUREMENT OF EPA-DESIGNATED ITEMS IN SERVICE AND CONSTRUCTION CONTRACTS (AUG 2018) |
| 52.223-18 | ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE DRIVING (JUN 2020) |
| 52.223-21 | FOAMS (JUN 2016) |
| 52.225-13 | RESTRICTIONS ON CERTAIN FOREIGN PURCHASES (FEB 2021) |
| 52.227-1 | AUTHORIZATION AND CONSENT (JUN 2020) |
| 52.227-2 | NOTICE AND ASSISTANCE REGARDING PATENT AND COPYRIGHT INFRINGEMENT (JUN 2020) |
| 52.227-4 | PATENT INDEMNITY—CONSTRUCTION CONTRACTS (DEC 2007) |
| 52.227-17 | RIGHTS IN DATA – SPECIAL WORKS (DEC 2007) |
| 52.228-2 | ADDITIONAL BOND SECURITY (OCT 1997) |
| 52.228-5 | INSURANCE - WORK ON A GOVERNMENT INSTALLATION (JAN 1997) |
| 52.228-11 | INDIVIDUAL SURETY—PLEDGES OF ASSETS (FEB 2021) |
| 52.228-12 | PROSPECTIVE SUBCONTRACTOR REQUESTS FOR BONDS (DEC 2022) |
| 52.228-14 | IRREVOCABLE LETTER OF CREDIT (NOV 2014) |
| 52.228-15 | PERFORMANCE AND PAYMENT BONDS-CONSTRUCTION (JUN 2020) |
| 52.229-3 | FEDERAL, STATE, AND LOCAL TAXES (FEB 2013) |
| 52.232-5 | PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (MAY 2014) |
| 52.232-17 | INTEREST (MAY 2014) |
| 52.232-23 | ASSIGNMENT OF CLAIMS (MAY 2014) |
| 52.232-27 | PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS (JAN 2017) |
| 52.232-33 | PAYMENT BY ELECTRONIC FUNDS TRANSFER – SYSTEM FOR AWARD MANAGEMENT (OCT 2018) |
| 52.232-39 | UNENFORCEABILITY OF UNAUTHORIZED OBLIGATIONS (JUN 2013) |
| 52.232-40 | PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS SUBCONTRACTORS (MAR 2023) |
| 52.233-1 | DISPUTES (MAY 2014)–ALTERNATE I (DEC 1991) |
| 52.233-3 | PROTEST AFTER AWARD (AUG 1996) |
| 52.233-4 | APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM (OCT 2004) |
| 52.236-1 | PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984) |
| 52.236-2 | DIFFERING SITE CONDITIONS (APR 1984) |
| 52.236-3 | SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (APR 1984) |
| 52.236-5 | MATERIAL AND WORKMANSHIP (APR 1984) |
| 52.236-6 | SUPERINTENDENCE BY THE CONTRACTOR (APR 1984) |
| 52.236-7 | PERMITS AND RESPONSIBILITIES (NOV 1991) |
| 52.236-8 | OTHER CONTRACTS (APR 1984) |
| 52.236-9 | PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS (APR 1984) |
| 52.236-10 | OPERATIONS AND STORAGE AREAS (APR 1984) |
| 52.236-11 | USE AND POSSESSION PRIOR TO COMPLETION (APR 1984) |
| 52.236-12 | CLEANING UP (APR 1984) |
| 52.236-13 | ACCIDENT PREVENTION (NOV 1991) |
| 52.236-17 | LAYOUT OF WORK (APR 1984) |
| 52.236-21 | SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997) |
| 52.236-26 | PRECONSTRUCTION CONFERENCE (FEB 1995) |
| 52.242-5 | PAYMENTS TO SMALL BUSINESS SUBCONTRACTORS (JAN 2017) |
| 52.242-13 | BANKRUPTCY (JUL 1995) |
| 52.243-4 | CHANGES (JUN 2007) |
| 52.244-6 | SUBCONTRACTS FOR COMMERCIAL ITEMS AND COMMERCIAL SERVICES (JUN 2023) |
| 52.246-21 | WARRANTY OF CONSTRUCTION (MAR 1994) |
| 52.248-3 | VALUE ENGINEERING – CONSTRUCTION (OCT 2020) |
| 52.249-2 | TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (APR 2012)-ALTERNATE I (SEP 1996) |
| 52.249-10 | DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984) |
| 52.253-1 | COMPUTER GENERATED FORMS (JAN 1991) |
(End of clause)
1452.203-70 RESTRICTIONS ON ENDORSEMENTS (JUL 1996)
The Contractor shall not refer to contracts awarded by the Department of the Interior in commercial advertising, as defined in FAR 31.205–1, in a manner which states or implies that the product or service provided is approved or endorsed by the Government, or is considered by the Government to be superior to other products or services. This restriction is intended to avoid the appearance of preference by the Government toward any product or service. The Contractor may request the Contracting Officer to make a determination as to the propriety of promotional material.
(End of clause)
(8) The intelligence elements of the Army, the Navy, the Air Force, the Marine Corps, the Coast Guard, the Federal Bureau of Investigation, the Drug Enforcement Administration, and the Department of Energy;
1452.215-70 EXAMINATION OF RECORDS BY THE DEPARTMENT OF THE INTERIOR (APR 1984)
For purposes of the Examination of Records by the Comptroller General clause of this contract (FAR 52.215–2(d)), the Secretary of the Interior, the Inspector General, and their duly authorized representative(s) from the Department of the Interior shall have the same access and examination rights as the Comptroller General of the United States.
(End of clause) 52.219-14 LIMITATIONS ON SUBCONTRACTING. LIMITATIONS ON SUBCONTRACTING DEVIATION OCT 2022)
(a) This clause does not apply to the unrestricted portion of a partial set-aside.
(b) Definition. Similarly situated entity, as used in this clause, means a first-tier subcontractor, including an independent contractor, that—
(1) Has the same small business program status as that which qualified the prime contractor for the award (e.g., for a small business set-aside contract, any small business concern, without regard to its socioeconomic status); and
(2) Is considered small for the size standard under the North American Industry Classification System (NAICS) code the prime contractor assigned to the subcontract.
(c) Applicability. This clause applies only to—
(1) Contracts that have been set aside for any of the small business concerns identified in 19.000(a)(3);
(2) Part or parts of a multiple-award contract that have been set aside for any of the small business concerns identified in 19.000(a)(3);
(3) Contracts that have been awarded on a sole-source basis in accordance with subparts 19.8, 19.13, 19.14, and 19.15;
(4) Orders expected to exceed the simplified acquisition threshold and that are—
(i) Set aside for small business concerns under multiple-award contracts, as described in 8.405-5 and 16.505(b)(2)(i)(F); or
(ii) Issued directly to small business concerns under multiple-award contracts as described in 19.504(c)(1)(ii);
(5) Orders, regardless of dollar value, that are—
(i) Set aside in accordance with subparts 19.8, 19.13, 19.14, or 19.15 under multiple-award contracts, as described in 8.405-5 and 16.505(b)(2)(i)(F); or
(ii) Issued directly to concerns that qualify for the programs described in subparts 19.8, 19.13, 19.14, or 19.15 under multiple-award contracts, as described in 19.504(c)(1)(ii); and
(6) Contracts using the HUBZone price evaluation preference to award to a HUBZone small business concern unless the concern waived the evaluation preference.
(d) Independent contractors. An independent contractor shall be considered a subcontractor.
(e) Limitations on subcontracting. By submission of an offer and execution of a contract, the Contractor agrees to the following requirements in the performance of a contract assigned a North American Industry Classification System (NAICS) code applicable to this contract:
(1) Services (except construction). It will not pay more than 50 percent of the amount paid by the Government for contract performance, excluding certain other direct costs and certain work performed outside the United States (see paragraph (e)(1)(i)), to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor’s 50 percent subcontract amount that cannot be exceeded. When a contract includes both services and supplies, the 50 percent limitation shall apply only to the service portion of the contract.
(i) The following services may be excluded from the 50 percent limitation:
(A) Other direct costs, to the extent they are not the principal purpose of the acquisition and small business concerns do not provide the service. Examples include airline travel, work performed by a transportation or disposal entity under a contract assigned the environmental remediation NAICS code (562910), cloud computing services, or mass media purchases.
(B) Work performed outside the United States on awards made pursuant to the Foreign Assistance Act of 1961, or work performed outside the United States required to be performed by a local contractor.
(2) Supplies (other than procurement from a nonmanufacturer of such supplies). It will not pay more than 50 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor’s 50 percent subcontract amount that cannot be exceeded. When a contract includes both supplies and services, the 50 percent limitation shall apply only to the supply portion of the contract.
(3) General construction. It will not pay more than 85 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor’s 85 percent subcontract amount that cannot be exceeded.
(4) Construction by special trade contractors. It will not pay more than 75 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor’s 75 percent subcontract amount that cannot be exceeded.
(f) The Contractor shall comply with the limitations on subcontracting as follows:
(1) For contracts, in accordance with paragraphs (c)(1), (2), (3) and (6) of this clause – [Contracting Officer check as appropriate.] __ By the end of the base term of the contract and then by the end of each subsequent option period; or __ By the end of the performance period for each order issued under the contract.
(2) For orders, in accordance with paragraphs (c)(4) and (5) of this clause, by the end of the performance period for the order.
(g) A joint venture agrees that, in the performance of the contract, the applicable percentage specified in paragraph (e) of this clause will be performed by the aggregate of the joint venture participants.
(1) In a joint venture comprised of a small business protégé and its mentor approved by the Small Business Administration, the small business protégé shall perform at least 40 percent of the work performed by the joint venture. Work performed by the small business protégé in the joint venture must be more than administrative functions.
(2) In an 8(a) joint venture, the 8(a) participant(s) shall perform at least 40 percent of the work performed by the joint venture. Work performed by the 8(a) participants in the joint venture must be more than administrative functions.
(End of clause)
52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN 2020)
(a) Equal opportunity clause. The Contractor shall abide by the requirements of the equal opportunity clause at 41 CFR 60-741.5(a), as of March 24, 2014. This clause prohibits discrimination against qualified individuals on the basis of disability, and requires affirmative action by the Contractor to employ and advance in employment qualified individuals with disabilities.
(b) Subcontracts. The Contractor shall include the terms of this clause in every subcontract or purchase order in excess of the threshold specified in Federal Acquisition Regulation (FAR) 22.1408(a) on the date of subcontract award, unless exempted by rules, regulations, or orders of the Secretary, so that such provisions will be binding upon each subcontractor or vendor. The Contractor shall act as specified by the Director, Office of Federal Contract Compliance Programs of the U.S. Department of Labor, to enforce the terms, including action for noncompliance. Such necessary changes in language may be made as shall be appropriate to identify properly the parties and their undertakings.
(End of clause)
52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (OCT 2022)
(a) Definitions. As used in this clause— Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is–
(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means—
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.
Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.
Domestic construction material means—
(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-
(i) An unmanufactured construction material mined or produced in the United States; or
(ii) A construction material manufactured in the United States, if– (A)The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or
(B) The construction material is a COTS item; or
(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".
Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.
Foreign construction material means a construction material other than a domestic construction material.
Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.
Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.
Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.
"United States" means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:
“none”
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that- (i)The cost of domestic construction material would be unreasonable.
(A) For domestic construction material that is not a critical item or does not contain critical components.
(1)The cost of a particular domestic construction material subject to the requirements…