This is a Questions and Answers document for Amendment P0001 to federal solicitation 140P6426B0004 for the Munising Falls Trail Project at Pictured Rocks National Lakeshore (PIRO).

The document addresses 15 contractor inquiries regarding project execution. Key clarifications include: no trees require contractor removal except one 4-inch tree to be removed by NPS prior to mobilization; a Stormwater Pollution Prevention Plan (SWPPP) and erosion/sediment control measures are required per construction drawings sheets 6-7; the Superintendent, Site Safety and Health Officer, and Quality Control Manager roles may be filled by fewer than three individuals if properly qualified; the period of performance includes all lead times and cannot be extended post-award; third-party testing is required as contractor-procured sources; no building/construction permit is needed as NPS is the Authority Having Jurisdiction, but regulatory permitting and an Erosion and Sediment Control permit are required by the contractor; and landscaping restoration including topsoil, seeding, and fertilizer is required per construction drawings. Additional responses confirm no phasing is required, materials are generally state tax-exempt with an exemption letter to be provided by the contracting officer, work cannot occur during winter months pending notice to proceed, asbestos and lead are not known to be present, geotechnical investigations are available in the project manual, no on-site hydrant exists but contractors may coordinate with the city for water access, and a site visit sign-in sheet is attached documenting four attendees from various organizations including Munising Construction, WE Construction LLC, NK Environmental, and Pictured Rocks National Lakeshore staff.

View the file

Other files for this federal contract opportunity

Other files attached to Munising Falls Trail Rehabilitation, newest first.
File Type Posted
Sol_140P6426B0004_Amd_0001.pdf PDF
B08_Solicitation_-__ADDENDUM_1.pdf PDF
B08_Solicitation_-_Statement_of_Structural_Tests_and_Special_Inspections.pdf PDF
B08_Solicitation_-__Specifications_-_PIRO_226930.pdf PDF
B08_Solicitation_-_DOL_Wage_Determination.pdf PDF
B08_Solicitation_-_Bid_Schedule.xlsx XLSX spreadsheet
B08_Solicitation_-_Drawings_-_Bid_Option_1.pdf PDF
Sol_140P6426B0004.pdf PDF
B08_Solicitation_-_Drawings_PIRO_226930.pdf PDF
B08_Solicitation_-_Limitations_on_Subcontracting_Report.xlsx XLSX spreadsheet

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation #: 140P6426B0004

Amendment #: P0001

Munising Falls Trail Project – PIRO

Questions and Answers listed below:

QUESTIONS:

Question # Question Answer/Response

1. Please provide the number of trees and sizes to remove for bidding purposes.

The new work follows the alignment of the existing trail.

There are no trees identified to be removed by the Contractor. Per Bid Option 1, the overlook platform includes a single 4” tree which states on the drawings will be removed by NPS prior to Contractor mobilization.

2. Is an SWPPP required?

Yes. See sheet 7 of 35 in the Construction Drawings, Erosion and Sediment Control Notes which state the requirement. The project is also permitted by Michigan EGLE and NPS has obtained and will provide to the awarded contractor copy of the permit to adhere to its conditions.

3. Should contractor account for any silt fencing or erosion control measures? If so, to what extent?

Absolutely yes. See Construction Drawings, sheets 6 and 7 of 35 for the minimum provision of sediment and erosion controls as defined.

Additional measures may be required should construction activity or maintenance of installed measures not provide required control as condition of the permitting.

4. Do the Superintendent, SSHO and QC Manager need to be 3 separate individuals?

They do not. If fewer individuals have the proper qualifications and experience, they may fill more than one role.

5. Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project?

The period of performance is inclusive of lead times

6. Please provide the site visit attendee sign in sheet.

Sheet attached

7. Please confirm whether asbestos or lead is present on this project, and if so, provide the relevant documentation.

Lead nor asbestos are known to be present within the project.

8. Does this project require phasing?

No

9. Is this project tax exempt?

Materials purchased for this project are generally exempt from state taxes. An exemption letter will be supplied by the contracting officer to the awardee,

10. When do you anticipate on site work starting?

Work will begin once all necessary post award documentation is completed and a notice to proceed has been issued. No work will be able to be completed during the winter months and will be accounted for.

11. Are third party inspections required?

There is testing required as defined in the specifications as third party, Contractor procured sources.

12. Is permitting required?

No building/construction permit as NPS is the Authority Having Jurisdiction. Regulatory permitting addressing natural resource impacts is required. Erosion and Sediment Control permit is required to be obtained by the Contractor. The project is also permitted by Michigan EGLE and NPS has obtained and will provide to the awarded contractor copy of the permit to adhere to its conditions.

13. Are soil boring reports available? If not, it will be assumed that excavation will be clear of rocks and obstructions.

Geotechnical investigations which informed the structural design is provided as a appendix of the project manual.

14. Is there a bulk water fill i.e. a hydrant or water source we can pump from for grading operations in close proximity?

There is no hydrant on site;

contractor could work with city to access nearby hydrants or water sources.

15. Is any landscaping restoration required for this project?

For example; topsoil, seeding, and fertilizer.

Yes. Extent is identified in the Construction Drawings pertaining to tree, soil, and vegetation protection, topsoil conservation and salvage, and seeding.