Questions_and_Answers_-_Amend_2_0002.pdf
PDF 122 KB Posted
- Attached to
- Brandywine Culvert Replacement Federal contract opportunity
- Solicitation number
- 140P6424B0001
About this file
This document contains Questions and Answers related to Amendment 2 of Solicitation #P6424B0001 for the Brandywine Culvert Project in Cuyahoga Valley National Park.
The key details are:
- The National Park Service has not yet obtained the USACE Nationwide Permit (NWP) approval and has not provided the proposed USACE NWP to bidders. The Park Service is still processing the NWP application and will share it once issued.
- The contractor must follow the final permit conditions and restrictions related to in-water work in Brandywine Creek, including any ODNR or USACE restrictions.
- The Park Service has attached the Stormwater Pollution Prevention Plan (SWPPP) that was submitted to the Ohio EPA.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B09_Solicitation_Amendments_-_Application_0002.pdf | ||
| B09_Solicitation_Amendments_-_SWPPP_0002.pdf | ||
| Sol_140P6424B0001_Amd_0002.pdf | ||
| Sol_140P6424B0001_Amd_0001.pdf | ||
| Structural_Test_and_Inspection_0001.pdf | ||
| OEPA-_Stormwater_Permit_Approval_through_2028_0001.pdf | ||
| Questions_and_Answers_0001.pdf | ||
| Geotechnical_Report_0001.pdf | ||
| Sol_140P6424B0001.pdf | ||
| B08_Solicitation_-_Limitations_on_Subcontracting_Report.xlsx | XLSX spreadsheet | |
| Drawings_-_Brandywine_Culvert.pdf | ||
| DOL_Wage_Determination.pdf | ||
| B08_Solicitation_-_Submittal_List.pdf | ||
| Specifications_-_Brandywine_Culvert.pdf | ||
| B08_Solicitation_-_Notice_to_Contractors_-_BWC.pdf | ||
| Construction_Contract_Administration.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation #: P6424B0001
Amendment #: 2
Brandywine Culvert Project – CUVA
Questions and Answers listed below:
QUESTIONS:
Question # Question Answer/Response
1. Amendment 1 provided the Ohio Environmental
Protection Agency’s Approved Construction Site
Stormwater General Permit. However, the National
Park Service has not obtained the USACE NWP approval or provided bidders a copy of their proposed submitted USAC NWP outlining all requirements and procedures necessary for installation of the proposed Box Culvert and
Brandywine Creek Stream Modifications. Current solicitation, specifications, and plans do not stipulate if construction equipment will be permitted in the waterways of Brandywine Creek.
We request that the National Park Service provide the proposed USACE NWP and confirm to the bidding contractors that necessary construction equipment shall be permitted in the Brandywine
Creek.
March 15 – June 30th is the typical ODNR in‐ water work restriction.
USACE in‐water work restrictions are not known at this time, we will share the NWP when it is issued. The contractor must follow the final permit conditions and restrictions. Here is our application.
We are also attaching the Stormwater Pollution Prevention Plan (SWPPP) that was submitted to the OEPA
2.
File details come from the government source that posted it. Updated .