Brandywine Culvert Replacement Federal contract opportunity
Solicitation number
140P6424B0001
Issued by
Department of the Interior National Park Service Midwest Region

About this file

This is a solicitation notice for a construction contract. The National Park Service is seeking bids for the Brandywine Culvert Replacement project in Cuyahoga Valley National Park, Ohio. The work includes renovating an existing historic culvert and installing a new culvert to accommodate 150% of creek flows. The contract is a firm-fixed price construction contract subject to prevailing wage rates in Summit County, Ohio. The NAICS code is 238910 and it is reserved as a 100% small business set-aside. The solicitation number is 140P6424B0001 and the project value is between $1 million and $5 million. Interested offerors must register in SAM.gov and complete online representations and certifications by the solicitation closing date once posted. Christopher Bauer is the point of contact for any questions. A site visit is also available; see the solicitation for details.

View the file

Other files for this federal contract opportunity

Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CUYAHOGA VALLEY

NATIONAL PARK

Ohio

Brandywine Historic Culvert Rehab

CUVA

PMIS NO. 247361

PROJECT SPECIFICATIONS

NATIONAL PARK SERVICE

MIDWEST REGION

March 3, 2023

THIS PAGE INTENTIONALLY LEFT BLANK

CUVA - 247361 00 01 10 - 1

TABLE OF CONTENTS

TABLE OF CONTENTS

DIVISION 01 — GENERAL REQUIREMENTS

01 10 00 - DIVISION 01 SHORT FORM GENERAL REQUIREMENTS

01 22 00 - MEASUREMENT AND PAYMENT

01 32 33 - PHOTO DOCUMENTATION

01 35 91 - HISTORIC PRESERVATION TREATMENT

01 57 23 - TEMPORARY STORM WATER POLLUTION PREVENTION

DIVISION 02 — EXISTING CONDITIONS

02 41 00 - DEMOLITION

DIVISION 03 — CONCRETE

03 00 05 - CONCRETE

DIVISION 04 — MASONRY

04 01 40.91 - STONE RESTORATION

04 34 00 - STONE MASONRY

DIVISION 31 — EARTHWORK

31 10 00 - SITE CLEARING

31 22 00 - SITE GRADING

31 23 10 - EXCAVATION AND BACKFILL

31 23 16 - TOPSOIL

31 23 19 - DEWATERING

31 32 19 - GEOTEXTILES

31 37 00 - RIPRAP

DIVISION 32 — EXTERIOR IMPROVEMENTS

32 15 40 - CRUSHED STONE SURFACING

32 91 13 - SOIL PREPARATION

32 92 19 - SEEDING

32 93 00 - PLANTS

DIVISION 40 — PROCESS INTERCONNECTIONS

40 05 39 - PIPE - REINFORCED CONCRETE

D I V I S I O N 0 1

GENERAL REQUIREMENTS

CUVA - 247361 01 10 00 - 1

DIVISION 01 SHORT FORM GENERAL REQUIREMENTS

PMIS NUMBER: 247361

Project Title: Brandywine Creek Historic Culvert Rehabilitation

Project Location: Cuyahoga Valley National Park, 1175 W Highland Road, Sagamore, OH 44067

SECTION 01 10 00

DIVISION 1 SHORT FORM GENERAL REQUIREMENTS

PART 1 – GENERAL

ITEM 1 - DESCRIPTION OF WORK

1.1 Background: The historic stone arch culvert under the Ohio & Erie Canal Towpath trail is hydraulically undersized and stream flows frequently overtop the trail embankment damaging the surfacing and increasing maintenance. Scour erosion is occurring at each end of the upstream headwall of the historic culvert causing instability and displacing stones.

1.2 Work Covered by the Contract Documents:

A. Project Location: Cuyahoga Valley National Park, 1175 W Highland Road Sagamore, OH

44067, Summit County, OH. Supplemental Box Culvert adjacent to existing historic stone arch culvert for the Ohio & Erie Canal Towpath Trail over Brandywine Creek, approximately 1,320

FT south of Vaughn/West Highland Road (Highway 111).

1. Work consists of: Renovation of the Brandywine Creek Historic Culvert including the installation of a new culvert constructed adjacent to the existing historic culvert and of sufficient size and length to accommodate approximately 150% of Brandywine Creek’s flows. The creek channel will be regraded upstream and downstream to a very limited extent so that most of the Creek’s flow passes through the new culvert to the extent possible within limited channel design and construction (and hydraulic analysis) and limited construction grading.

B. All work will be performed under a single contract.

Period of performance: Work shall be completed within 270 days of the start date provided on the

Notice to Proceed. The period of performance is inclusive of 10 weather days.

ITEM 2 - EXISTING UTILITIES

2.1 Existing Utilities: Notify Contracting Officer (CO), Contracting Officer’s Representative (COR) and utility companies to coordinate proposed locations, times for excavation and request location services prior to any digging operation.

CUVA - 247361 01 10 00 - 2

2.2 Contractor shall be responsible for locating and preventing damage to known utilities. If contractor damage occurs, alert CO and COR as soon as safely possible, and repair utility at no additional expense to the Government. If damage occurs to an unknown utility, contact CO and COR as soon as safely possible.

2.3 Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated below:

2.3.1 Notify CO and COR not less than two business days in advance of proposed utility interruptions.

2.3.2 Hours for Utility Shutdowns: Shutdowns shall not exceed 2 to 3 hours. Temporary provisions will be needed by the Contractor for periods longer than stated allowance or if required for critical systems as determined by COR.

ITEM 3 - CONTRACTOR’S USE OF PREMISES

3.1 Conduct of Operations: At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent. Laws & Policies - Cuyahoga

Valley National Park (U.S. National Park Service) (nps.gov).

A. No signs or advertisements (except those specified herein and as required for safety) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

B. Smoking is not permitted within any Federal building or within 25 feet of entrances, operable windows, or outdoor air intakes.

C. Public Use of Site: Contractor shall at all times conduct operations to ensure the least inconvenience to the public. Provide appropriate signage on the Ohio & Erie Canal Towpath Trail at nearest public access sites.

3.2 On-site work hours: Work shall be generally performed during normal business working hours of 7 a.m. to 5 p.m., Monday through Friday, except when otherwise indicated.

A. Work on Saturdays, Sundays, Federal holidays, early morning, or at night may not be performed without prior consent from the CO and COR. Submit requests for work outside of the stated normal business hours to the CO and COR for approval at least 48 hours in advance of the work.

The following Federal holidays are observed by the National Park Service:

New Year Day

Martin Luther King, Jr’s Birthday

Washington’s Birthday

Memorial Day

Juneteenth National Independence Day

Independence Day

Labor Day

Columbus Day

Veterans Day

Thanksgiving Day

Christmas Day https://www.nps.gov/cuva/learn/management/lawsandpolicies.htm https://www.nps.gov/cuva/learn/management/lawsandpolicies.htm

CUVA - 247361 01 10 00 - 3

B. Note: Any of the above holidays falling on a Saturday will be observed on the preceding Friday;

holidays falling on Sunday will be observed on the following Monday. The specific day that each holiday is recognized for each year can be found at the following site: Federal Holidays

(opm.gov).

3.3 Contractor Use of Site:

A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to construction area as shown on site plan and described below. Do not disturb portions of Project site beyond areas in which the Work is indicated.

B. Limits: The maintenance access road, construction area, and staging area shown on the site plan.

C. Driveways and Entrances: Keep driveways, access roads, and entrances not identified for contractor use as shown on site plan clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize use of driveways and entrances.

D. Limit site disturbance, including earthwork and clearing of vegetation, to:

a. limits of construction areas shown on plans

b. 3 feet beyond edge of surfacing on portions of maintenance access road outside construction boundaries.

c. Removal of overhanging branches and limbs along maintenance access road that would be damaged by vehicular activities associated with construction activities.

B. Utilities

a. General: Cost or use charges for temporary facilities shall be included in the Contract

Sum as required.

b. Water Service: Water from existing water system is not available.

c. Electric Power Service: Electric power from existing system is not available.

d. Toilets: Contractor provided for contracting personnel, sufficiently lighted and ventilated toilet facilities in weatherproof, sight proof, handicap accessible (if required), sturdy enclosures with privacy locks. Coordinate with COR for approved location if not shown on attached site plan.

C. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with state and federal environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

D. Cleaning of Equipment: The Contractor shall ensure that prior to moving on to the Project Area, all equipment, is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Ensure that all equipment has been pressure washed and is free of exotic species prior to start-up of operations and moving of equipment to Project Area. Equipment shall be considered free of soil, seeds, and other debris when a visual inspection does not disclose such material.

Disassembly of equipment components or specialized inspection tools are not required.

E. Tree and Plant Protection: Provide Tree Protection fence at drip line of trees not marked for removal in construction area. Coordinate with COR.

https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2022 https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2022

CUVA - 247361 01 10 00 - 4

F. Restore damaged areas to original condition, repairing or replacing damaged trees and plants not marked for removal, at no additional expense to the Government.

G. Provide temporary barriers to protect existing trees and plants and root zones not marked for removal.

H. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with

Contracting Officer Representative and remove agreed-on roots and branches that interfere with construction.

I. Do not fasten ropes, cables, or guys to trees.

J. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

K. Pest Control: Follow best practices to minimize attraction and harboring of rodents, roaches, and other pests and to perform extermination and control procedures at regular intervals so

Project will be free of pests and their residues at project completion. Perform control operations lawfully, using environmentally safe materials.

L. Safety Barrier Fence: Orange plastic fence, minimum height, 4 feet.

M. Barrier Tape: Yellow tape Imprinted with "CAUTION: CONSTRUCTION AREA," manufactured by Reef Industries, Inc., Houston, Texas, or approved equal.

3.4 Storage - Staging Areas:

N. Confine Storage of materials and equipment to the project staging area noted on the Overall Site

Key Plan Sheet. No cost-specific storage and staging area’s may be discussed at the preconstruction briefing.

O. Limits of use and control shall be subject to Contracting Officer’s approval. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

3.5 Preservation of Natural Features: N/A.

3.6 Hauling Restrictions: Contractor to verify path to site and meet state and county road requirements and height restrictions for all park work/access.

P. Access Road, Towpath and Historic Culvert

1. During the planned activities including site preparation and construction, heavy trucks and equipment are expected to use the access road, Towpath and the historic culvert over

Brandywine Creek to access the Site and staging area. The following measures will be taken to minimize any potential damage:

a. reduced vehicle speeds,

b. weight limits, and

c. frequent inspections by the NPS PC/On-Site Representative.

CUVA - 247361 01 10 00 - 5

Q. Damage to Towpath, Historic Culvert, and Access Road: The execution of the Project will involve travel of large heavy equipment along the Site access road, the Towpath and across the historic culvert above Brandywine Creek. In the course of the project, damage or suspected damage may occur to the access road, the Towpath, or the historic culvert. Contingency planning for damage to the access road, Towpath, or historic culvert includes the following.

1. The NPS On-Site Representative shall be notified immediately if damage to the access road, Towpath, or historic culvert is observed or suspected. The NPS On-Site

Representative will conduct a walk along the access road, Towpath and historic culvert looking for signs of damage on a weekly basis during the construction activities or after heavy traffic days.

2. NPS will be responsible for assessing and documenting the situation. If the NPS On-Site

Representative determines that additional technical support is required to assess the damage, the technical resource will be obtained (e.g., damage to the culvert would likely require engineering support). Documentation will include interviews with those involved and photo documentation of the suspected damage. The event will be documented in the daily report, at a minimum.

3. Depending on the scope of the damage, repairs will be made in a timeframe commensurate with the degree of damage and planning required for mitigation.

4. A root cause analysis review will be performed to determine the cause of the damage.

E.g., was the equipment or truck too heavy for the road, culvert, or path? If so, can a different piece of equipment be used that is lighter or do the trucks need to carry less weight? Were traffic controls ineffective or not followed? Were Site conditions, such as weather, a factor?

5. Once the root cause is understood, corrective measures will be employed to avoid similar incidents.

3.7 Housekeeping:

A. Keep project neat, orderly, and in a safe condition at all times.

a. Dispose of waste materials and recycling legally outside the park. The contractor shall not use park dumpsters

1) Address Recycling: Government goal is to salvage and recycle as much nonhazardous construction waste as possible. Use sustainable methods to extent possible during this project, recycling material as is probable with local means.

Maintain accurate documentary records for submittal of all recycled materials used including fly ash and slag cement.

3.8 Temporary Storm Water Pollution Prevention:

Prepare Temporary Storm Water Pollution Prevention Plan, Section 01 57 23.

3.9 Photo Documentation:

Contractor must provide existing condition, progress and completion photos. All photos shall be in focus, show maximum range of depth of field general photo and then close-up detail photo as needed. Shall be in JPEG digital form and submitted electronically by email or via CD-R Archival Gold or DVD-R

Archival Gold media with printed labels and 8 mega pixels minimum within 7 days from time of taken or as approved by COR.

CUVA - 247361 01 10 00 - 6

A. Existing Condition Images:

Before starting construction, take color, dated, digital images of project site, maintenance access road, towpath trail near construction area, historic stone arch culvert barrel and upstream and downstream headwalls, and adjacent property/roads/etc. that may be impacted by construction activity/traffic. Include existing items to remain or be salvaged from different vantage points and with context for location identification.

B. Construction Progress Images:

1. Document all sub-surface work/ trenches etc. prior to backfill with photos covering enough overall field view to show location and then zoom in for details. (Locations and dimensions shall also be noted on as built drawing set.)

2. Maintain organized index for photos with date, description, etc.

3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.

C. Completion Images:

1. Document all completed work within scope of work.

2. Maintain organized index for photos with date, description, etc.

3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.

3.10 Fire and Life Safety:

R. As a minimum, conduct one weekly 15 minute "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the following week. Document and submit meeting minutes to the CO and COR within one day after the meeting and document the meetings on the daily reports.

S. Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations). Take all necessary precautions to prevent fire during construction. Provide adequate ventilation during use of volatile or noxious substances.

T. Store and handle hazardous materials in accordance with manufacturer’s and OSHA

29CFR1926 Subpart D requirements 1926 | Occupational Safety and Health Administration

(osha.gov). Maintain readily available, on site, MSDS/Safety Data Sheets (SDS) for each chemical.

1. Immediately report all spills of hazardous materials to the CO, COR and park.

2. Maintain a spill emergency response kit.

3. Train employees how to respond to a spill and use the emergency response kit.

U. Repetitive and/or intermittent, high-level noise: Permitted only during Daytime.

1. Do not exceed the following dB(A) limitations at 50 feet:

https://www.osha.gov/laws-regs/regulations/standardnumber/1926 https://www.osha.gov/laws-regs/regulations/standardnumber/1926

CUVA - 247361 01 10 00 - 1

Sound Level in dB(A)

Time Duration of Impact Noise

More than 12 minutes in any hour

More than 3 minutes in any hour

1. Maximum permissible construction equipment noise levels at 50 feet:

EARTHMOVING dB(A)

Compressors 75

Pumps 75

Generators 75

MATERIALS HANDLING dB(A)

Pneumatic Tools 80

Saws 75

Vibrators 75

A. Ambient Noise:

1. Maximum noise levels (dB) for receiving noise area at property line shall be as follows:

Residential receiving area, dB:

Daytime: 65 dB

Commercial/Industrial receiving area:

Daytime: 67 dB

Nighttime: 45 dB

Nighttime: 65 dB

ITEM 4 - COMMENCEMENT, PROSECUTION, AND COMPLETION

4.1 The Contractor shall commence work in accordance with the terms and conditions of the contract.

Contractor shall coordinate and incorporate long lead and delivery time items within the schedule.

ITEM 5 - EXAMINATION OF THE SITE

5.1 All bidders are urged to visit the job site and examine existing conditions before submitting bids.

Contractors will be accountable for understanding existing conditions. No cost changes for items viewable during site visit will be allowed.

ITEM 6 - ABBREVIATIONS

6.1 The list of abbreviations, standards and organizations which may be used in/referred within the

Construction Specifications or Special Provisions, may be found linked from the listed page below. On the home page, follow the link under “Contracting and Procurement” labeled “NPS Reference

Standards.”

https://www.nps.gov/orgs/1671/do-business-with-us.htm

ITEM 7 - ACCIDENT PREVENTION

7.1 Description: The work of this section consists of establishing and implementing an effective accident prevention program (APP) and providing a safe environment for all personnel and visitors.

7.2 Submittals:

A. Accident Prevention (Safety) Plan (APP): Submit a site-specific accident prevention (safety) plan. The Plan shall be written to comply with OSHA and project requirements (a generic plan is not acceptable) including but not limited to the following:

1. Name and qualifications of responsible supervisor to carry out the program.

https://www.nps.gov/orgs/1671/do-business-with-us.htm

CUVA - 247361 01 10 00 - 2

2. First aid and rescue procedures.

3. Training, both initial and continuing.

4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to provide for property protection and safety of the public, National Park

Service personnel, and Contractor's employees. Identify the work included under each phase, with a Job Hazard Analysis (JHA)/Job Safety Analysis (JSA), etc. A sample JHA template may be provided upon request.

5. Planning for possible emergency situations, such as cave-ins, earthquake, explosions, fires, floods, power outages, slides, and windstorms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.

6. Contractor to identify nearest location of medical facility for emergencies

7. Recognition that work will be performed in remote areas with limited communication or cell phone coverage if applicable.

8. Supplemental hazard specific plans may be required IAW 29 CFR 1926 or 1910.

B. Meeting and Inspection Reports: Safety Meetings: As a minimum, conduct 15 minute

"toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite. Submit a report of safety meetings and inspections to CO and COR within one day after the meeting and document the meetings on the daily reports.

7.3 Qualification of Employees:

A. Ensure that employees are physically qualified to perform their assigned duties in a safe manner to include operators of vehicles and equipment. Provide operating instructions for all equipment.

B. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.

7.4 Accident Reporting: The Contractor shall report all accidents to the CO and COR as soon as safely possible and assist the CO and COR and other officials as required in the investigation of the accident.

7.5 First Aid Facilities: Provide access to facilities for the number of employees and appropriate to the hazards associated with the types of ongoing construction work at the site.

7.6 Emergency Instructions: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.

7.7 Personal Protective Equipment (PPE): It is the Contractor's responsibility to require all those working on or visiting the site to wear necessary protective equipment at all times.

A. PPE must meet requirements of applicable ANSI standards. Selection shall conform to OSHA

29CFR 1926 Subpart E.

B. A hard hat use area shall be designated by the Contractor. The hard hat area shall be posted by the

Contractor in a manner satisfactory to the Contracting Officer.

C. All PPE will be serviceable at all times. At a minimum, maintain four (4) sets of PPE including hard hats and all other Accident Prevention Plan required equipment.

CUVA - 247361 01 10 00 - 3

7.8 Hazardous Materials: It shall be the responsibility of all operators and contractors, functioning within the park to properly cleanup, mitigate and remediate, if necessary, all unauthorized discharges of hazardous materials or non-hazardous chemical and biological products released from fleet and/or other support vehicles or stationary sources. Response shall be consistent with guidelines established by federal, state and local regulations, and as outlined within the operator's Safety or Hazardous Materials

Business Plan.

A. If a spill, leak or other release occurs, the operator shall as soon as possible, without impeding cleanup, notify the National Park Service Emergency Dispatch.

ITEM 8 - PRECONSTRUCTION CONFERENCE: If the Contracting Officer decides to conduct a preconstruction conference, the successful offeror will be notified and will be required to attend. The

Contracting Officer’s notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed. See Item 9.1C below.

ITEM 9 - SUBMITTALS

9.1 General Submittal Procedures:

A. General: Prepare and submit submittals required by individual Technical Specification

Sections. Types of submittals are indicated in individual specific sections.

1. CM-16 Transmittal Form: All submittals shall be transmitted via electronic email using

National Park Service form CM-16 form. The form will be provided by the Contracting

Officer. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form. Submit completed CM-16 forms to the CO and the COR

B. Submittal List: administrative required submittals are listed below in 9.1.C and does not include technical section submittal requirements included in each technical section.

C. Preconstruction Conference Submittal: Satisfactory evidence of liability insurance coverage and workman’s compensation, and any applicable bonds, must be submitted within 10 calendar days of Notice of Award. The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. If all these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed may not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued. Contracting Officer will notify Contractor of tentative date for the Pre-Construction

Conference:

1. Letter designating Project Superintendent.

2. Construction Schedule. (Must include shop drawings, procurement time including long lead time items, mobilization, trade work progression and completion at minimum.)

3. A comprehensive breakdown of the Schedule of Values.

4. Accident Prevention (Safety) Plan (see section 7 of this document).

5. A list of Subcontractors for this project.

6. Written statements from subcontractors certifying compliance with applicable labor standard clauses (SF1413).

7. Quality Control Plan.

8. Waste Management Plan.

CUVA - 247361 01 10 00 - 4

9. Temporary Storm Water Pollution Prevention Plan (SWPP) Submitted to AHJ (Authority

Having Jurisdiction; State of Ohio Environmental Protection Agency, Division of Surface

Water.)

10. Historic Preservation Treatment Plan Submitted to AHJ (Authority Having Jurisdiction) defined as Cuyahoga Valley National Park.

11. List of Required Construction Permits. Include the following information for each permit:

a. Name of Permit.

b. The Agency(ies) with Jurisdiction issuing the permit.

c. Information required from the Government to complete the permit application.

9.2 Shop Drawings, Product Data, and Samples: Contracting Officer will provide sample cover sheet.

A. Shop Drawings: Indicate all coordinating materials and work impacting the installation coordination, connection details, anchorage requirements, hardware locations, and installation details and locations.

1. Submit Shop Drawings according to Part 9.1 of this section to include one digital file

(.PDF or .TIF) and two full size hardcopy documents to COR.

B. Product Data: Provide component construction and specification data sheets, anchorage requirements and any other product specific data.

1. Submit Product Data according to Part 9.1 of this section to include one digital file (.PDF or .TIF) to COR.

C. Samples: Submit 2 color samples on a 16-inch by 16-inch size (or manufacturers standard size with approval, but no smaller than 12-inch by 12-inch) cementitious backer unit or CBU panel

(e.g., tile backer board) for all color selection. Paint/stain samples shall be actual finish drawdown for all project colors.

1. Submit Samples CM-16 Transmittal Form according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and physical samples of actual material to COR.

D. For submittals specified above, forward submittals to Contracting Officer and COR at least 15 days before need for approval (depends on length of project).

E. After approving submittals, Contracting Officer and/or COR will return one copy to the

Contractor. If submittals are not approved, Contracting Officer will return all copies to

Contractor with reasons for rejection. Resubmit, identifying changes. Any work done before approval shall be at Contractor's own risk.

9.3 Approved Equals: If an item in this solicitation is identified as “brand name or equal” or lists more than 1 manufacturer, the description of the proposed item must reflect the characteristics and level of quality that will satisfy the Government’s needs as demonstrated by the salient physical, functional, or performance characteristics that “equal” products must meet and/or exceed that as specified in the solicitation or relevant specification.

A. For each item proposed as an “approved equal,” submit supporting data, including:

1. Drawings and samples as appropriate.

2. Comparison of the characteristics of the proposed item with that specified and with the salient characteristics provided.

3. Changes required in other elements of the work because of the substitution.

4. Name, address, and telephone number of vendor.

CUVA - 247361 01 10 00 - 5

5. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists. Describe availability of maintenance service, and state source of replacement materials.

B. A request for approval constitutes a representation that Contractor:

1. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.

2. Will provide the same warranties for the proposed item as for the item specified.

3. Has determined that the proposed item is compatible with interfacing items.

4. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.

5. Waives all claims for additional expenses that may be incurred as a result of the substitution.

C. Approved Equals will be evaluated and approved/disapproved during the submittal process.

9.4 Progress Reporting: The initial Construction Schedule and Schedule of Values are required a minimum of one week prior to the Preconstruction Conference. After the Notice to Proceed is issued and after on-site work begins, progress will be documented via daily logs and by providing an updated

Construction Schedule and Schedule of Values when requested, but minimally with each pay application.

Submit digital copy electronically (PDF preferred) of all required documents. Construction Schedules are normally in bar chart form and indicate estimated starting and completion dates for each part of the work.

For a pay application to be reviewed and processed in a timely manner, the following information must either be submitted prior to or accompany submission of the pay application:

A. Daily/weekly progress reports during construction as part of the administration process.

B. Updated Schedule of Values: Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The Schedule of Values will form the basis for payment. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. A sample Schedule of Values format may be provided upon request.

ITEM 10 – TEMPORARY SERVICES

10.1 It is the Contractor’s responsibility to provide temporary services, equipment, tools, and skilled labor as required for the chosen means and methods to perform the work in accomplishing this Contract.

ITEM 11 - PROJECT CLOSEOUT

11.1 Description: The work of this section consists of final cleanup, closeout submittals, final inspection procedures working toward Final Acceptance.

11.2 Cleaning: Remove all tools, equipment, surplus materials, and rubbish. Move attic stock to location coordinated with COR. At time of final inspection, project shall be thoroughly clean and ready for intended use. Inspector holds the right to reschedule if project is not ready for inspection.

CUVA - 247361 01 10 00 - 6

11.3 Completion and Final Inspection: Contractor shall submit written certification of project completion and request a final inspection to the Contracting Officer and COR. The Contracting Officer or designee will make an inspection within 10 days of receipt of request or at a mutually agreeable time.

A. If the work is determined to be complete following the final inspection with minor comments, the

COR will prepare and provide the Contractor a Punch List noting outstanding items to be addressed.

B. If the work is not determined to be complete following the final inspection, the Contracting

Officer will notify Contractor in writing, stating reasons. Contractor, after completing the work according to the Contract Documents, shall resubmit completion and request a new final inspection. Re-inspection costs may be charged against the Contractor in accordance with the

Inspection of Construction contract clause.

C. Contractor shall complete the Punch List within 30 calendar days, or a time directed by the CO.

D. Once Contractor completes all items of work on the Punch List and all contractually required items are accepted, Contracting Officer will issue Letter of Final Acceptance of Work and request the final pay application.

E. If the Contractor fails to complete the work within the time frame, the Contracting Officer may correct the work with an appropriate reduction in contract price or charge for re-inspection costs in accordance with the Inspection of Construction contract clause.

F. Disposition of any permits and warranties required by the specifications in this section.

11.4 Final Acceptance of the Work: After all punch list deficiencies have been corrected, a Letter of

Final Acceptance will be issued. A Release of Claims document must be executed and submitted to the

Contracting Officer before final payment can occur.

11.5 Warranties

A. Construction Warranty shall be based on date of final acceptance of the work and remain in effect for one year.

B. Provide all manufacturer warranty information of products installed organized by Division.

All contact information, extent of coverage and conditions shall be clearly noted as well as date of overall final acceptance.

C. Information shall include operation and maintenance manuals for each warranted product.

PART 2 – PRODUCTS (NOT USED)

PART 3 – EXCUTION (NOT USED)

END OF SECTION

CUVA - 247361 01 22 00 - 1

MEASUREMENT AND PAYMENT

PMIS Number: 247361

Project Title: Brandywine Creek Historic Culvert Rehabilitation

PROJECT LOCATION: CUYAHOGA VALLEY NATIONAL PARK, 15610 VAUGHN ROAD,

BRECKSVILLE, OH 44141

SECTION 01 22 00 - MEASUREMENT AND PAYMENT

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. General requirements applicable to all bid/pay items.

2. General provisions on unit prices and quantities.

3. General provisions on lump sums.

4. Listing of the various bid/pay items in the Project, together with criteria for measuring

Unit Price Work for payment.

B. Related Requirements:

1. Include but are not necessarily limited to:

a. Section 01 10 00 – Division 01 Short Form General Requirements.

1.2 REQUIREMENTS APPLICABLE TO ALL BID/PAY ITEMS

A. In this Section and elsewhere in the Contract Documents, the terms “bid item”, “pay item”, “bid/pay item”, “Item” followed by a number designation, “this item”, and the like all have the same meaning, and refer to one or more specific elements of the Contract, established for pricing and payment, as indicated in the Bid Form and in the Agreement (or exhibit to the

Agreement) at the time the Contract was signed by the parties.

B. This Article applies to all bid/pay items in the Contract.

C. Prices – General:

1. The bid/pay items listed starting with Article [1.5] of this Section refer to and are the same bid items listed in the Bid Form and included in the Contract and constitute all bid/pay items for the Work at the time the Contract was signed by the parties.

CUVA - 247361 01 22 00 - 2

2. No direct or separate payment will be made, outside of the bid/pay items in the Contract, for the following: providing miscellaneous temporary or accessory materials or equipment, temporary works, temporary construction facilities, Contractor’s project management, superintendence, and similar costs for Subcontractors or Suppliers; [bonds and] insurance; schedules and schedule updates; coordination with: Owner’s operations

(including, but not limited to, lockout/tag-out procedures), other contractors, utility owners, owners of transportation facilities, adjacent property owners and occupants, authorities having jurisdiction, Subcontractors and Suppliers, and others with whom

Contractor is to coordinate the Work); information technology systems required by the

Contract Documents; Submittals; photographic documentation; Project meetings;

Contractor’s hazard communication program; Contractor’s compliance with environmental procedures for Constituents of Concern (including spill control and countermeasures plans and implementation); professional services (required for

Contractor’s means and methods of construction, and for delegated designs required by the Contract Documents); obtaining and complying with permits and licenses; temporary utilities (including electric power, water supply and disposal, fuel, and communications);

temporary lighting; temporary fire protection; temporary enclosures and HVAC;

temporary sanitary facilities; temporary first-aid facilities and services; ; Contractor’s field offices and sheds, Engineer’s field offices (when required elsewhere in the Contract

Documents); temporary vehicular access and parking (including access to the Site, temporary access roads and parking, onsite traffic controls for construction traffic, and offsite haul routes); traffic control of non-construction vehicular and pedestrian traffic;

temporary controls (including temporary erosion and sediment controls, noise control, control of storm water, surface water, and groundwater, pollution controls (including solid waste control, water pollution control, and control of atmospheric pollution), dust control, pest and rodent controls, odor controls, and other temporary controls required by the Contract Documents); temporary security for the Work; temporary barriers; Project signage (when required elsewhere in the Contract Documents); delivering, handling, and storing materials and equipment to be incorporated into the Work; layouts and surveys for the Work; construction equipment, machinery, tools, and vehicles; safety and protection; Site maintenance during construction; cleaning and removal and disposal of waste and debris; checkout and startup; testing and other quality control activities required by the Contract Documents; record documents, operation and maintenance data;

warranties; spare parts and extra materials required by the Contract Documents;

instruction of facility personnel as required by the Contract Documents; commissioning

(when required elsewhere in the Contract Documents); Contractor’s correction period, Contractor’s general warranty and guarantee; Contractor’s indemnification obligations;

other labor, cost, or effort required by the General Conditions and Supplementary

Conditions, Division 01 Specifications, and other requirements of the Contract

Documents.

3. Price Escalation:

a. Unless expressly indicated otherwise in the Contract Documents, Owner is not obligated to change the stipulated prices (including lump sums, unit prices, and allowances) that are all or part of the Contract Price because of escalation of costs when there is no corresponding change in the Contract Times.

b. Changes in the Contract Times do not necessarily entitle Contractor to a change in

Contract Price due to escalation.

4. Compensation for all services, labor, materials, and equipment shall be included in prices stipulated for the lump sum and unit price bid/pay items in the Contract.

CUVA - 247361 01 22 00 - 3

5. Each lump sum and unit price in the Contract shall include an amount considered by

Contractor as sufficient for all overhead and profit for each separately identified bid/pay item.

D. Contract Price, Payment Procedures, and Related Matters:

1. Contract Price: The Contract Price, as apportioned among bid/pay items in the Contract, is indicated in the Agreement and may be modified by Change Order.

2. Payments to Contractor: Refer to the General Conditions (as may be modified by the

Supplementary Conditions), the Agreement (including provisions on retainage, if any), and Section 01 10 00, among other applicable Contract Documents.

3. Procedures for Changes in Contract Price: Refer to the General Conditions (as may be modified by the Supplementary Conditions) and Section 01 10 00 s.

4. Defective Work is not eligible for payment.

1.3 GENERAL PROVISIONS ON UNIT PRICES AND QUANTITIES

A. Quantities:

1. Quantities of Unit Price Work indicated in the Bid Form and in the Contract (at the time the Agreement was signed by the parties) are estimates for purposes of pricing and comparison of Bids.

2. Owner does not represent, either expressly or by implication, or agree that the nature of materials encountered below ground surface or in concealed areas, or actual quantities of

Unit Price Work required, will correspond with the quantities in the Contract at the time the Agreement was signed by the parties. Owner reserves the right to increase or decrease quantities, and to eliminate quantities, as Owner may deem necessary or as may be necessary due to Site conditions encountered.

3. Adjustment of Unit Prices Due to Variation in Quantities:

a. Provisions, if any, regarding adjustment of unit prices due to variations in actual quantities (eligible for payment) from the estimated quantities in the Contract

(including quantities at the time the Agreement was signed by the parties and as subsequently modified by Change Order) are in the General Conditions, as may be modified by the Supplementary Conditions.

1) Owner’s review for possible unit price adjustment, when provision for such adjustment is expressly indicated in the Contract, will be at a time Owner deems reasonable and proper.

2) When the Supplementary Conditions establish that, to be eligible for an adjustment in the unit price, a pay item of Unit Price Work must have a total computed, extended price (at the time the Agreement was signed by the parties) equal to or greater than a specified percentage (stipulated in the

Supplementary Conditions) of the total Contract Price (at the time the

Agreement was signed by the parties), and the total extended price of such pay item does not exceed the stipulated percentage of the Contract Price, then the associated pay item will be paid at the unit price in the Contract without adjustment for variations in actual quantity.

CUVA - 247361 01 22 00 - 4

4. Quantities eligible for payment will be actual quantities furnished and installed (as applicable) in accordance with the Contract Documents, within the pay limits shown or indicated, as measured by Owner (or other entity so empowered in the Contract

Documents) and recommended for payment by Owner.

5. At Contractor’s expense, Contractor may independently verify quantities measured by

Owner for payment. Should Contractor disagree with quantities measured and recommended for payment by Owner, submit appropriate Change Proposal (appealing

Owner’s measurements) indicating the specific reasons for Contractor’s appeal, with detailed reasons therefor and associated calculations and estimates, in accordance with the Contract Documents.

6. Quantity Overruns:

a. When the quantity of a pay item of Unit Price Work eligible for payment exceeds the pay item’s quantity included in the Contract, Owner will pay for quantities that exceed those in the Contract only while the estimated total payments to Contractor under the Contract will not exceed the Contract Price. Otherwise, a Change Order is required to modify the associated quantity in the Contract, thus changing the

Contract Price.

7. Except as may be established elsewhere in the Contract Documents, make no claim for anticipated profit, loss of profit, damages, or additional compensation arising from difference between quantities of Unit Price Work eligible for payment and the estimated quantities in the Contract.

B. Measuring for Payment:

1. Unless expressly indicated otherwise in the Contract Documents, measurements will be in United States standard measurements.

2. Unless indicated otherwise elsewhere in the Contract Documents, quantities of Unit Price

Work eligible for payment will be rounded to the nearest whole number.

3. In the event of conflict between this Section and the measurement criteria in the

Specifications of Divisions 02-49, the measurement criteria in this Section will govern.

Typical intent when measurement criteria are in both this Section and the associated

Division 02-49 Specifications section, is for the criteria to be interpreted together.

4. Assistance with Measurements:

a. Assist Contracting Officer (CO), by providing measuring equipment, labor, and survey personnel necessary to measure quantities eligible for payment.

5. Quantities eligible for payment can be adjusted by Owner to correct quantities included in Contractor’s prior payment requests, and for incomplete or defective Unit Price Work.

Such corrections are at Owner’s sole discretion.

1.4 GENERAL PROVISIONS ON LUMP SUM ITEMS

A. Progress payments for Work paid on a lump sum basis will based on Owner’s estimate of the

Work (in accordance with the Contract Documents) performed through the end of the associated pay period, based on the Schedule of Values accepted by Owner in accordance with the

Contract Documents.

CUVA - 247361 01 22 00 - 5

B. At its sole discretion, Owner may correct amounts of lump sum Work included in prior payment requests based on improved data or information available to Owner, or Owner’s knowledge or reasonable belief that Work is incomplete or defective.

1.5 BID/PAY ITEMS – GENERAL CONTRACT

A. Item 1 – Mobilization and Demobilization:

1. Measurement: In accordance with the Contract’s provisions and progress payments for lump sum Work.

2. Item Includes:

a. Work and activities indicated in this provision are intended as illustrative for purposes of scope and payment and do not represent a complete list of all preconstruction activities and Submittals, or all Work or activities required by the contract for mobilization and demobilization.

b. Mobilization Work paid under this item will include:

1) Furnishing required performance bond and payment bond.

2) Furnishing required insurance and associated documentation.

3) Obtaining Owner’s acceptance of proposed Subcontractors and Suppliers and entering into subcontracts and purchase orders needed to start the Work.

4) Preparing and obtaining Owner’s approval of Shop Drawings required in

Section 01 10 00 – Division 01 Short Form General Requirements of Site.

5) Preparing and obtaining Owner’s acceptance of schedules, including

Progress Schedule, Schedule of Submittals, and Schedule of Values.

6) Preconstruction conference(s) required by the Contract Documents.

7) Preconstruction photographic documentation.

8) Establishing Contractor’s Site-specific health and safety plan, preconstruction activities needed to start implementing Contractor’s safety programs, and verifying status of training of construction workers and personnel and condition of construction equipment, machinery, and tools.

9) Submitting acceptable emergency contact information.

10) Obtaining required permits needed to start the Work.

11) Implementing and maintaining the SWPPP.

12) Initial establishment of temporary utilities and temporary facilities.

13) Establishing Contractor’s field office and sheds, Contractor’s storage areas, staging and laydown areas, and other areas necessary to perform the Work.

14) Initial establishment of construction vehicular access to the Site, parking needed for construction, and offsite haul routes.

15) Establishing construction equipment, machinery, and tools at the Site.

16) Providing initial temporary controls.

17) Temporary security needed to start Work at the Site.

18) Performing preconstruction assessments and condition surveys required by the Contract Documents.

19) Material testing and quality control.

20) Other mobilization acceptable to Owner.

c. Demobilization Work paid under this item will include:

CUVA - 247361 01 22 00 - 6

1) Performing post-construction assessments and condition surveys required by the Contract Documents and associated remedial Work, if any.

2) Removal from the Site and adjacent areas of excess materials and equipment.

3) Removal of temporary controls, temporary facilities, temporary barriers, and similar materials and equipment.

4) Restore operation and maintenance access road line, grade, and surfacing to pre-construction conditions or better.

5) Removal of temporary access roads and parking areas not part of permanent pavement or otherwise allowed to remain by Owner, including temporary traffic controls established for construction vehicles and equipment.

6) Removal of all field office and sheds, storage areas, staging and laydown areas, and other areas needed to perform the Work and restoration of such areas.

7) Removal from the Site of all construction equipment, machinery, tools, Contractor’s containers, temporary fuel storage tanks, and similar items.

8) Closeout of permits on which Contractor is a permittee or co-permittee.

9) Final cleaning.

10) Furnishing required closeout documents.

11) Other costs and effort by Contractor for demobilization.

d. Other cost and Work are under other bid/pay items in the Contract.

3. Payment: Lump sum price for this item will be full compensation for all mobilization and demobilization required and needed for the Contract, not included under other bid/pay items or contracts.

B. Item 2 – Demolition

1. Measurement: In accordance with the Contract’s provisions and progress payments for lump sum Work.

2. Demolition Work paid under this item will include:

a. Demolition and removal of:

1) Steel pipe handrail.

2) Concrete slab in vicinity of handrail.

3) Operation and maintenance access road and Towpath surfacing.

4) Tree removal, loading and hauling.

5) Tree protection

6) Protecting the historic stone arch culvert and headwall.

7) Other demolition acceptable to Owner.

b. Clearing and Grubbing.

3. Payment: Lump sum price for this item will be full compensation for all demolitions and clearing and grubbing required and needed for the Contract, not included under other bid/pay items or contracts.

CUVA - 247361 01 22 00…