This document outlines closeout submittal requirements for a federal contract to remove and install a new HVAC system. The contractor must provide final project record drawings, train facility staff to operate building controls and mechanical equipment, and submit operation and maintenance manuals and warranty documentation for various building systems. Closeout submittals include as-built drawings, demonstration of DDC controls and mechanical equipment operation, spare parts lists, keys, acoustical panel information, and warranty guarantees. Closeout requirements cover record documents, system training, tools, parts, and warranty information for the replacement of an existing geothermal HVAC system with a new fluid cooler, natural gas boiler, heat pumps, energy recovery ventilators, and associated ductwork and controls at a National Park Service facility. All closeout submittals are due by specified dates between September 2023 and June 2024 following completion of the HVAC installation work.
View the file
Other files for this federal contract opportunity
Show all 37
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Topic Specification
Section Requirement
Submittal
Date Completed
Received by Park
017700 Final Project Record Drawings
230923 Train owner to operate DDC controls
235216 Train owner to adjust, operate, and maintain boiler
236423 Train owner to adjust, operate, and maintain cooling tower
238126 Train owner to adjust, operate, and maintain heat pumps
238113 Train owner to adjust, operate, and maintain ERV
262923 Train owner to adjust, operate, and maintain VFD's
230593 Final HVAC Testing and Balancing Report
75323 Maintenance Data for EPDM Roof
87100 Maintenance Data for Door Hardware
98433 Maintenance Data for Acoustical Panels
104416 O&M data for Fire Extinguishers
221119 O&M data for backflow preventer
221119 O&M data for PRV
230923 O&M Manual for DDC System
231126 O&M data for gas PRV
232116 O&M data for strainers and air separators
232123 O&M data for pump
235216 O&M data for boiler
235216 Warranty documentation for boiler
236514 O&M data for cooling tower
236514 Warranty documentation for cooling tower
237223 O&M data for ERV
237223 Warranty documentation for ERV
238146 O&M data for Water Source Heat Pump
238146 Warranty documentation for Water Source Heat Pump
262416 O&M Data for Panelboard
262416 Warranty for Panelboard
262816 O&M Data for Enclosed Switches and Circuit Breakers
262816 Warranty for Enclosed Switches and Circuit Breakers
262923 O&M Data for Variable Frequency Drives
262923 Warranty for Variable Frequency Drives
265119 O&M Data for LED Lighting
265119 Warranty for LED Lighting
O&M Data
Warranties
Guarantees
Environmental
Record
Documents
Extra Stock
Reports
Keys and keying schedule
CLOSEOUT AND OPERATION & MAINTENANCE REQUIREMENTS
Project Record
Drawings
System
Demonstration and Training
Tools
Spare Parts
Equipment