B09 - Amendment4Atch14Section221429_0004.pdf

PDF 652 KB Posted

Attached to
Remove and Install a New HVAC unit. Federal contract opportunity
Solicitation number
140P6220B0002
Issued by
Department of the Interior National Park Service Midwest Region

About this file

This document includes a technical specification for sump pumps and a related federal contract opportunity for replacing an HVAC system. The specification outlines performance, product, and installation requirements for submersible sump pumps and basin components. Pump types include submersible and end-suction centrifugal models. Materials and components are specified for pump casings, shafts, seals, motors, and basins. Installation and testing standards are also provided. The related federal contract opportunity is to disconnect and replace an existing geothermal HVAC system serving a visitor center with a new fluid cooler, natural gas boiler, and replacement of heat pumps and ductless split systems. The work will also include adding energy recovery ventilators. The solicitation is from the Department of the Interior National Park Service Midwest Region.

View the file

Other files for this federal contract opportunity

Other files attached to Remove and Install a New HVAC unit., newest first.
File Type Posted
B09 - Amendment5Attachment28_A301_0005.pdf PDF
B09 - Amendment5Attachment26_087100_0005.pdf PDF
B09 - Amendment5Attachment30_S201_0005.pdf PDF
Sol_140P6220B0002_Amd_0005.pdf PDF
B09 - Amendment5Attachment29_S101_0005.pdf PDF
B09 - Amendment5Attachment27_A101_0005.pdf PDF
B09 - Amendment5Attachment31_QandA_0005.pdf PDF
B09 - Amendment5Attachment25_075323_0005.pdf PDF
B09 - Amendment4Atch22UtilityDetails2000_0004.pdf PDF
B09 - Amendment4Atch24BrandNameJustification_0004.pdf PDF
B09 - Amendment4Atch15Section232500_0004.pdf PDF
Sol_140P6220B0002_Amd_0004.pdf PDF
B09 - Amendment4Atch23QuestionsandAnswers_0004.pdf PDF
B09 - Amendment4Atch20HVACPlanLowerLevel2000_0004.pdf PDF
B09 - Amendment4Atch18E103_Rev1_0004.pdf PDF
B09 - Amendment4Atch19HVACPipingPlans2000_0004.pdf PDF
B09 - Amendment4Atch13Parking_0004.pdf PDF
B09 - Amendment4Atch21LowerLevelFloorPlan2000_0004.pdf PDF
B09 - Amendment4Atch16M200_Rev1_0004.pdf PDF
B09 - Amendment4Atch17M501_Rev1_0004.pdf PDF
Sol_140P6220B0002_Amd_0003.pdf PDF
Sol_140P6220B0002_Amd_0002.pdf PDF
140P6220B0002Amendment2Attachment_0002.pdf PDF
Base_B08 - SolicitationAtch4Pictures1.pdf PDF
Base_B08 - SolicitationAtch10OF17.pdf PDF
Base_B08 - SolicitationAtch5SubmittalList.pdf PDF
Base_B08 - SolicitationAtch7WageDetermination.pdf PDF
Base_Sol_140P6220B0002.pdf PDF
Base_B08 - SolicitationAtch8TechPic1.pdf PDF
Amend_0001_Sol_140P6220B0002_Amd_0001.pdf PDF
Base_B08 - SolicitationAtch2Drawings.pdf PDF
Base_B08 - SolicitationAtch6CloseoutSubmittalList.pdf PDF
Base_B08 - SolicitationAtch12NoticetoContractorsCPARS.pdf PDF
Base_B08 - SolicitationAtch3SenitiveAreaMap.pdf PDF
Base_B08 - SolicitationAtch9TechPic2.pdf PDF
Base_SolicitationAtch1Specifications06242020.pdf PDF
Base_B08 - SolicitationAtch11SF24BidBond.pdf PDF
Show all 37

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOSM – 241749 221429 - 1

031414 SUMP PUMPS

SECTION 221429

SUMP PUMPS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Submersible sump pumps.

2. Sump-pump basins and basin covers.

1.2 ACTION SUBMITTALS

A. Product Data: For each type of product.

1.3 CLOSEOUT SUBMITTALS

A. Operation and maintenance data.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

B. UL Compliance: Comply with UL 778 for motor-operated water pumps.

2.2 SUBMERSIBLE SUMP PUMPS

A. Submersible, Fixed-Position, Single-Seal Sump Pumps:

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Grundfos Pumps Corp.

b. Little Giant; a Franklin Electric brand.

c. Pentair Pump Group.

d. Weil Pump Company, Inc.

e. Zoeller Company.

2. Description: Factory-assembled and -tested sump-pump unit.

3. Pump Type: Submersible, end-suction, single-stage, close-coupled, overhung-impeller, centrifugal sump pump as defined in HI 1.1-1.2 and HI 1.3.

4. Pump Casing: Cast iron, with strainer inlet, legs that elevate pump to permit flow into impeller, and vertical discharge for piping connection.

5. Pump and Motor Shaft: Stainless steel or steel, with factory-sealed, grease-lubricated ball bearings.

6. Seal: Mechanical.

140P6220B0002 Attachment 14 Amendment 4

FOSM – 241749 221429 - 2

7. Motor: Hermetically sealed, capacitor-start type; with built-in overload protection; lifting eye or lug; and three-conductor, waterproof power cable of length required and with grounding plug and cable-sealing assembly for connection at pump.

2.3 SUMP-PUMP BASINS AND BASIN COVERS

A. Basins: Factory-fabricated, watertight, cylindrical, basin sump with top flange and sidewall openings for pipe connections.

1. Material: Polyethylene.

2. Reinforcement: Mounting plates for pumps, fittings, and accessories.

3. Anchor Flange: Same material as or compatible with basin sump, cast in or attached to sump, in location and of size required to anchor basin in concrete slab.

B. Basin Covers: Fabricate metal cover with openings having gaskets, seals, and bushings; for access to pumps, pump shafts, control rods, discharge piping, vent connections, and power cables.

1. Reinforcement: Steel or cast iron, capable of supporting foot traffic for basins installed in foot-traffic areas.

2.4 MOTORS

A. Comply with NEMA designation, temperature rating, service factor, enclosure type, and efficiency requirements for motors specified in Section 220513 "Common Motor Requirements for Plumbing Equipment."

1. Motor Sizes: Minimum size as indicated. If not indicated, large enough so driven load will not require motor to operate in service factor range above 1.0.

B. Motors for submersible pumps shall be hermetically sealed.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Pump Installation Standards: Comply with HI 1.4 for installation of sump pumps.

3.2 CONNECTIONS

A. Where installing piping adjacent to equipment, allow space for service and maintenance.

3.3 FIELD QUALITY CONTROL

A. Perform the following tests and inspections:

1. Perform each visual and mechanical inspection.

2. Leak Test: After installation, charge system and test for leaks. Repair leaks and retest until no leaks exist.

3. Operational Test: After electrical circuitry has been energized, start units to confirm proper motor rotation and unit operation.

4. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and equipment.

FOSM – 241749 221429 - 3

B. Pumps and controls will be considered defective if they do not pass tests and inspections.

C. Prepare test and inspection reports.

END OF SECTION

File details come from the government source that posted it. Updated .