Amendment_Attachment_1_0001.docx
DOCX document 50 KB Posted
- Attached to
- Wayside Exhibit Planning, Design, Fabrication, and Federal contract opportunity
- Solicitation number
- 140P2124R0007
About this file
This document is an amendment to a solicitation for the Design/Build of Wayside Exhibits at San Antonio Missions National Historical Park. The purpose of this contract is to provide planning, design, fabrication, and audio description for wayside exhibits at the park, including 78 unique exhibits, 5 identical exhibits with unique "You Are Here" locations, 1 directional arrow, 5 tactile tables, and 5 exact duplicates. The contractor will be required to create wayside exhibit production-ready design layouts, research and purchase rights for up to 30 images, create all text content, provide Spanish translations, create 14 two-dimensional flat maps and 1 three-dimensional illustrated map, fabricate 89 panels and 87 painted aluminum bases, and create 6 bronze tactile elements. The total fixed-price contract value is $525,524, with a period of performance through October 25, 2021. The contractor will be required to travel to the park for a site visit and participate in periodic conference calls and webinar sessions.
View the file
Other files for this federal contract opportunity
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SAN ANTONIO MISSIONS NATIONAL HISTORICAL PARK
DESIGN/BUILD OF WAYSIDE EXHIBITS
I. BACKGROUND
This park preserves four Spanish frontier missions that were part of a colonization system that stretched across the Spanish Southwest in the 1600s, 1700s, and 1800s. The mission churches are still active today. The existing wayside exhibits lack cohesive interpretive information based on interpretive themes and World Heritage status.
II. PURPOSE
The purpose of this contract is to provide planning, design, fabrication, and audio description for wayside exhibits for San Antonio Missions National Historical Park.
III. SCOPE OF WORK
The contractor shall provide the National Park Service (NPS) with all labor, materials, equipment, facilities, and travel necessary to plan, design, fabricate, and audio describe wayside exhibits for San Antonio Missions National Historical Park.
This Task Order includes the following phases of work as detailed in the Wayside Exhibit Planning and Design Specifications: Section 1 Programmatic Accessibility, Section 2 Site Analysis, Section 3 Wayside Exhibit Proposal, Section 4 Research and Graphic Acquisition, Section 5 Wayside Exhibit Plan, Section 6 Graphic File Preparation, and supporting Attachments in Section J.
The Contractor shall:
A. Finalize Starter Proposal, see Attachment A, Starter Proposal, by adding designer created thumbnails, location information, map of exhibit locations, and changes agreed upon during site visit. The Government shall furnish the source file in File Maker Pro, upon award of contract.
B. Create wayside exhibit production ready design layouts for seventy-eight (78) unique exhibits, five (5) identical exhibits with unique You Are Here locations, one (1) directional arrow, five (5) tactile tables, and five (5) exact duplicates.
C. Research and purchase one-time use rights for up to thirty (30) images. Images to be determined by the contractor. The Government shall furnish contemporary photos of park activities, historic park images, and existing art.
D. Create all text. Content experts and reference material shall be provided during site visit. Existing wayside exhibit text may be used as reference material, see Attachment B, Reference.
E. Create Spanish translation for all English text, including English on tactile elements.
F. Create fourteen (14) two-dimensional flat maps, see Attachment B, Park Maps for trail reference:
| 1) | Ex 001B, Concepcion Orientation |
| 2) | Ex 020B, San Jose Orientation |
| 3) | Ex 021, Royal Roads |
| 4) | Ex 036B, Community Orientation |
| 5) | Ex 037, rotate Ex 036B map |
| 6) | Ex 060B, San Juan Orientation |
| 7) | Ex 066, Yanguana Trail Orientation |
| 8) | Ex 070, rotate Ex 066 map |
| 9) | Ex 075, Farm Trail Orientation |
| 10) | Ex 079A, rotate Ex 060B map |
| 11) | Ex 079B, Bike Trail Orientation |
| 12) | Ex 090B, Espada Orientation |
| 13) | Ex 106, rotate Ex 090B map |
| 14) | Ex 110, Rancho de las Cabras Orientation |
G. Provide accessible trail information for trail maps on Ex 066, 075, and Ex 11.
H. Edit one (1) existing park map. See Attachment B, Park Maps. The Government shall furnish the source files in Adobe Illustrator, upon award of contract. This map will be used in all Park Orientation exhibits with unique You Are Here locators.
H. Create one (1) three-dimensional illustrated map for Ex 050 to show how the dam backs up the water to feed the acequias.
| I. | Create thirteen (13) illustrations: | |
| 1) | Ex 001B, full color to show Mission Conception in 1755 | |
| 2) | Ex 002, simple black and white to show the dining area in 1755 | |
| 3) | Ex 003, full color to show friar putting supplies away | |
| 4) | Ex 004, full color to show friar at table writing | |
| 5) | Ex 006, full color to show kitchen and dining area with soldiers and friars | |
| 6) | Ex 007, full color to show historic church | |
| 7) | Ex 009, full color to show active quarry with soldiers | |
| 8) | Ex 023, full color to show bastion | |
| 9) | Ex 027, full color to show replicate Fresco on outside of church | |
| 10) | Ex 033, full color to show granary | |
| 11) | Ex 039, full color to show working mill | |
| 12) | Ex 052, full color to show how the water in the aqueduct goes over stream | |
| 13) | Ex 064, full color to show friar activity in Convento |
| K. | Fabricate eighty-nine (89) panels, material to be determined, according to the Wayside Exhibit Panel Specifications: | |
| 1) | Forty-seven (47) 42” x 24” (Ex 003, 004, 005, 006, 007, 009, 011, 021, 022, 023, 024, 026, 027, 028, 029, 030, 032, 033, 034, 035, 038, 039, 041, 050, 051, 052, 062, 063, 064, 065, 067, 068, 069, 071, 072, 073, 076, 077, 080, 092, 093, 094, 099, 100, 101, 103, and 105) | |
| 2) | Twenty-one (21) 6” x 12” (Ex 002, 012, 013, 014, 015, 031, 042, 043, 044, 045, 046, 074, 081, 082, 083, 095, 096, 097, 098, 102, and 104) | |
| 3) | One (1) 24” x 24” (Ex 008) | |
| 4) | Eleven (11) 36” x 48” (Ex 001A, 020A, 020B, 036A, 036B, 037, 60A, 079A, 079B, 090A, and 110A) | |
| 5) | One (1) 12” x 12” (Ex 78) | |
| 6) | Six (6) 24” x 36” (Ex 066, 070, 075, 090B, 110B and 106) | |
| 7) | Two (2) 36” x 36” (Ex 001B and 060B) |
| L. | Fabricate eighty-seven (87) painted aluminum bases according to the Wayside Exhibit Base Specifications: |
| 1) | Two (2) - double-in-line 36” x 48”, 36” x 36”, and 36” x 12” accessory panel with two brochure holders and changeable panel, in-ground (Ex 001AB and 060AB) |
| 2) | Twenty-one (21) – Plant ID (Ex 002, 012, 013, 014, 015, 031, 042, 043, 044, 045, 046, 074, 081, 082, 083, 095, 096, 097, 098, 102, and 104) |
| 3) | Eight (8) - 42” x 24” low profile sled (Ex 003, 004, 005, 006, 022, 023, 032, and 039) |
| 4) | Three (3) - 42” x 24” low profile baseplate (Ex 007, 011, and 064) |
| 5) | One (1) - 24” x 24” custom wall mount (Ex 008) |
| 6) | Thirty-three (33) - 42” x 24” low profile, in-ground (Ex 009, 021, 024, 026, 027, 028, 029, 030, 033, 034, 035, 038, 041, 050, 051, 052, 062, 063, 065, 071, 072, 073, 076, 077, 080, 092, 093, 094, 099, 100, 101, 103, and 105) |
| 7) | Three (3) – custom tactile table, baseplate, with roof (Ex 010, 061, and 091) |
| 8) | One (1) – 36” x 48” upright double-in-line, in-ground (Ex 020AB) |
| 9) | Two (2) - 36” x 48” upright double sided, in-ground (Ex 036AB and 079AB) |
| 10) | One (1) – 36” x 48” upright, in-ground (Ex 037) |
| 11) | One (1) – custom tactile table, sled, with roof (Ex 040) |
| 12) | One (1) – custom tactile table, in-ground, with roof (Ex 025) |
| 13) | Three (3) – 42” x 24” low profile, custom (Ex 067, 068, and 069) |
| 14) | Four (4) – 24” x 36” upright, in-ground (Ex 066, 070, 075, and 106) |
| 15) | One (1) – 12” x 12” upright single post, in ground (Ex 078) |
| 16) | Two (2) – double-in-line 36” x 48”, 24” x 36”, and 24” x 12” accessory panel with two brochure holders and changeable panel, in-ground (Ex 090AB and 110AB) |
M. Create six (6) bronze tactile elements:
| 1) | Ex 010AB, approximately nine (9) square feet, map with detailed buildings to orient visitors to present day Mission Concepcion with braille and raised letters (English and Spanish) and scale in key area. Contractor to determine if key area is separate or within map. |
| 2) | Ex 025AB, approximately nine (9) square feet, map with detailed buildings to orient visitors to present day Jan Jose with braille and raised letters (English and Spanish) and scale in key area. Contractor to determine if key area is sperate or within the map. |
| 3) | Ex 035, approximately 6” x 6” x 1/4”, replica of Ethel Harris decorative tile to attach to panel with braille and raised letters (English and Spanish) at full size. |
| 4) | Ex 040, approximately nine (9) square feet, model of mill and raised diagrams of how it works with braille, raised letters (English and Spanish) and scale. |
| 5) | Ex 061, approximately nine (9) square feet, map with detailed buildings to orient visitors to present day San Juan with braille and raised letters (English and Spanish) and scale in key area. Contractor to determine if key area is separate or within map. |
| 6) | Ex 091, approximately nine (9) square feet, map with detailed buildings to orient visitors to present day Espada with braille and raised letters (English and Spanish) and scale in key area. Contractor to determine if key area is separate or within map. |
N. Create audio description for all exhibits.
IV. TRAVEL, MEETINGS, AND PRESENTATIONS
A. Kick-off/Post-award call
The project manager shall participate in a 15-minute conference call to discuss contract, communications, and site visit.
B. Site Visit
A project manager, planner, designer, and illustrator shall travel to San Antonio Missions National Historical Park to meet with the Contracting Officer’s Representative (COR) and NPS staff for three 9-hour days to visit each wayside exhibit location, revise purpose statements, review available reference materials, and develop thumbnails for each exhibit. Project Manager shall take notes on the description of each site for Audio Describer.
C. Conference calls and Webex Sessions
Ongoing calls: The contractor shall conduct monthly conference calls, and webex session to facilitate a collaborative work process and to conduct submittal reviews. The contractor shall prepare agendas and take notes for each meeting, and submit proposed agendas and meetings notes to the COR.
V. DELIVERABLES AND DESTINATION POINTS
A. The contractor shall submit the following to the COR:
1) Kick-off/Post-award Conference Call notes -word file by email
| 2) | Wayside Exhibit Proposal | |
| -PDF of proposal by government-secured ftp site | ||
| -all site photos by government-secured ftp site | ||
| -two printed copies mailed | ||
| -PDF of work and payment schedule by email |
| 3) | Final Wayside Exhibit Proposal with illustrated thumbnails of art, tactile elements, and map direction | |
| -PDF of proposal by government-secured ftp site |
-source file by government-secured ftp site -two printed copies mailed
4) Draft Wayside Exhibit Plan with developed black and white art with sample color, and drawing of tactile elements showing text and braille -PDF of plan by government-secured ftp site -two printed copies mailed -PDF of updated work schedule by email
| 5) | Wayside Exhibit Plan with color art at 50% completion, refined drawings of tactile elements | |
| -PDF of plan by government-secured ftp site | ||
| -two printed copies mailed |
| 6) | Final Wayside Exhibit Plan with full color art and 3D files or photos of clay models of tactile elements | |
| -PDF of plan by government-secured ftp site | ||
| -two printed copies mailed |
7) Production-Ready Files with final art -one full-size color print of each unique wayside exhibit from fabricator mailed -one digital copy of the packaged production-ready InDesign files and all links by government-secured ftp site -final 3D files or photos of final clay models of the tactile elements by government-secured ftp site
| -PDF of shop drawings for bases by email |
| -Draft Audio Description text by email |
8) Bases, tactile elements, hardware, and assembly instructions. Tactile for Ex 035 shall be shipped mounted to base plate and through panel. All hardware for assembling bases and table tactile shall be provided.
| 9) | Close-out package on government-secured ftp site | |
| -As-printed wayside exhibit production files | ||
| -Raw scans and layered graphic source files |
-Word document of all final text -Production files for tactile elements -Accessible PDF for each exhibit. All images shall have unique alt text. At a minimum, the PDF shall pass the Adobe Acrobat Accessibility Full Check found under the "Tools" section of Adobe Acrobat. In addition, the contractor shall use and submit the PDF File Remediation checklist to verify accessibility compliance, which can downloaded from: https://section508.gov/refresh-toolkit/accessibility-testing#ElectronicDocuments -Final Audio Description text
B. Deliverables 1) through 7) and 9) shall be sent to Harpers Ferry Center, 67 Mather Place, Harpers Ferry, WV 25425.
Deliverable 8) shall be delivered to San Antonio Missions National Historical Park, 112 Huizar, San Antonio, TX 78214.
VI. TIME FOR COMPLETION
All work, including review and approval, shall be completed on or before October 25, 2021.
VII. REVIEW AND APPROVAL
The COR will notify the contractor, in writing, of approval or rejection of the work within 21 days. Any additions or corrections shall be completed within 21 calendar days. In the event the government delays comments beyond the period specified, the contractor shall be entitled to a day-to-day extension in the completion date.
VIII. POINT OF CONTACT FOR PANEL AND BASE DELIVERY
Prior to delivery of wayside bases, tactile elements, and hardware the contractor shall contact the COR to advise of exact dates and arrangements made for delivery.
IX. PAYMENT SCHEDULE
Upon completion and acceptance of work and receipt of a proper invoice, the contractor shall be paid a firm-fixed price of $525,524 in accordance with the following payment schedule:
| DESCRIPTION |
| AMOUNT |
| A. |
| Upon completion and acceptance of Draft Wayside Exhibit Proposal |
| $52,552 |
| B. |
| Upon completion and acceptance of the Final Wayside Exhibit Proposal |
| $78,829 |
| C. |
| Upon completion and acceptance of the Draft Wayside Exhibit Plan |
| $105,105 |
| D. |
| Upon completion and acceptance of the Revised Wayside Exhibit Plan |
| $78,829 |
| E. |
| Upon completion and acceptance of the Final Wayside Exhibit Plan |
| $52,552 |
| F. |
| Upon completion and acceptance of bases, hardware, and tactile elements |
| $131,381 |
| G. |
| Upon completion and acceptance of the Close-out. |
| $26,276 |
| TOTAL FIXED PRICE: | $517,267 | |
| TOTAL FIXED PRICE TRAVEL: | $ 8,257 |
X. ATTACHMENTS - The following items are attached and incorporated into this order:
| A. | Starter Proposal | 110 pages | |||
| B. | Reference | 36 pages | |||
| C. | Maps | 9 pages |