Sol_140P2026R0081_Amd_0003.pdf
PDF 261 KB Posted
- Solicitation number
- 140P2026R0081
About this file
This document is Amendment 03 to Solicitation 140P2026R0081 for the stabilization of Kingsley Plantation shoreline, issued by the National Park Service (NPS) DSC Contracting Services Division in Denver, Colorado. The amendment extends the proposal due date to November 13, 2026, at 5:00 PM EST and provides answers to 51 Request for Information (RFI) questions, along with Attachment 14 (Appendix C—Procedure for Environmental Protection).
The project involves construction of a sheet pile wall to stabilize the shoreline at Kingsley Plantation in Florida, including demolition of existing infrastructure, installation of new PVC/fiberglass reinforced polymer (FRP) sheet piles, tie rods, deadman anchors, riprap stone placement, and Spartina vegetation planting with a 730-day establishment warranty period. Key clarifications from the RFI responses address sheet pile materials (steel and/or PVC/FRP experience acceptable), phasing requirements (sequential, no overlapping phases except early tree clearing), delivery scheduling (coordinated with Contracting Officer; primarily Mondays/Tuesdays when park is closed), permit responsibilities (contractor responsible for gopher tortoise relocation permitting; government providing NWP 13/54), and material specifications (limestone riprap, FDOT #57 stone, marine-grade aluminum pile caps). The work is classified under NAICS code 237990 with a $45 million size standard. There are three contract line items (CLINs 0001–0003) with no option CLINs. The contract includes standard federal forms and requires submission of General References forms and Limitation on Subcontracting reports. Contractors must acknowledge receipt of the amendment prior to proposal submission.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: is not is required copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7.ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
PAGESOF
Contractor
The hour and date specified for receipt of Offers to sign this document and return
Joseph Wingfield
See continuation page
NPS, DSC Contracting Services Div 1 Denver Federal Center, Building 50 P.O. Box 25287 Denver CO 80225-0287
PDS
140P2026R0081
10/05/2026
10/05/2026
1 9
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
140P2026R0081/0003
The purpose of Amendment 03 is to provide answers to RFI's submitted, extend the due date and add Attachment 14 - Appendix C-Procedure for Environmental Protection_2026-10-22_Opt.
The proposal due date is extended to 13 Nov
2026 at 5:00PM EST.
TIMU 335507 Stabilize Kingsley Plantation Shoreline RFI Responses Sol: 140P2026R0081
# Question Response
Section B refers to "base line items and all option line items," but only 3 CLINs 0001- 0003 are listed. Please confirm there are no option CLINs and that award will include all three CLINs?
Only 3 CLINs, No options
Section H lists "steel sheet pile" please confirm PVC/FRP sheet pile experience satisfies this. Can you use steel pile and/or PVC/FRP experience?
Yes. For key trades in both Section H and Section L, E.3. Factor 5 Project Experience. The intent is to show sheet pile driving experience. PVC/FRP experience satisfies this and steel and/or PVC/FRP experience is also acceptable.
Phasing (01 11 00): May Phase 3 clearing along the FRP wall be done early (January- February, before migratory bird nesting season), ahead of Phase 1 and 2 completion
Yes. Clearing is acceptable outside of the phasing requirements.
May phases overlap (a second crew starting Phase 2 or Phase 3 before the prior phase is substantially complete)?
No. Project should be bid in accordance with Specification 01 11 00 1.3. Value engineering proposals may be discussed following contract award.
May sheet piles and stone be delivered on days other than Monday/Tuesday if visitor areas are protected? May work start at 7:00 AM? Can you work 7 days a week?
Require coordination with COR for delivery on other days, however large deliveries are unlikely to be approved outside of Monday/Tuesday when the Park is closed to visitors. Work hours 8am to 5pm Monday to Friday, no work on the weekend.
Please provide all permits and any special conditions of NWP 13 SAJ-2000-03466, SJRWMD ERP 224839-1, the 401 WQC, the Submerged Land Letter of Consent, and the FWC gopher tortoise permit. Please identify any manatee, sea turtle, or nesting-bird work windows, and whether an in-water work window applies (31 10 00 indicates in-water work is required).
NWP 13/54 is provided in the amended solicitation. SJRWMD permits are currently in process with discussions captured in the drawings and specs of this soliciation package. Gopher Tortoise relocation and associated permitting will be the responsibility of the contractor. Appendix C to the specificationsis being developed with natural resource protection requirements and will be provided in the next amendment to this solicitation.
NPDES or UPPP: Drawing G0.1 says an approved general NPDES permit before disturbance; 01 57 23 uses a UPPP for sites under 1 acre. Which governs, and who files?
Will the project "owner" sign the permit in a timely manner if contractor required to obtain?
The anticipated disturbance for this project is less than 1 acre which would only require the UPPP submitted as part of the Division 01 submittals to be approved before mobilization (01 31 00 1.4.D.10). If the contractor's means and methods require greater than 1 acre of disturbance, the NPDES permit through the state with SWPPP is triggered and the contractor can coordinate obtaining the required information and signature of the project owner (park superintendent or delegated authority) as part of the list of required construction permits submittal before mobilization (01 31 00 1.4.D.12.c).
Please confirm NPS provides the archaeologicalist at no cost to the contractor, the availability, and the stop-work procedure and time compensation for a "find".
NPS will provide an archaeologist if needed. The Park has an archaeologist on staff who can respond to inadvertant finds. Stop-work and time compensation to be coordinated with CO. See 01 35 13.22 3.5.
S3.1 and the plans call for a 3/4" diameter rod, while the S5.1 details call for a "2.5"x0.75" HDG steel tie rod." Please confirm size, material grade, and connection detail.
The tie rod shall consists of 2.5"x0.75" rod head, turnbuckle, 0.75" extension rod and other accessories. For material specs refer drawing G0.1 (STEEL TIE RODS AND ACCESSORIES Section) and Division-2-49 Specification, Section 05 12 00. Details are as shown in Drawing S5.1 - SHEET PILE WALL DETAILS 1.
Tie rod corrosion protection: G0.1 requires HDG plus polymer coating, and 09 97 14 adds petrolatum tape. Are all three layers required, or HDG plus tape only?
Requirement for tie rod protection is HDG plus tape per Division-2-49 Specification, Section 09 97 14.
The geotechnical report recommends pre-augering/jetting, but 31 41 16.16 prohibits them. Will pre-augering or jetting be allowed if refusal occurs above tip elevation, and how will it be paid?
Pre-augering/jetting is prohibited for PVC/FRP pile driving. Refer Specification Division-2-49 Section 3.2, E6 of 31 41 16.16 for obstructions. The bidders shall include contingency in their bid for such unexpected obstruction.
The drawings specify limestone ; 31 37 16 prefers igneous and prohibits limestone in acid-sensitive waters. Please confirm limestone is acceptable, and provide the referenced sections 31 23 33 and 31 05 16 or delete the references.
Riprap stones shall be limestone. Refer General Notes drawings G0.1. Disregard reference for specification Sections 31 23 33 and 31 05 16. These Sections are not relavent for this project.
Please confirm deadman sheet length/embedment (S3.1 shows bottom at +3.50) and the total count and lengths of Type I and Type II deadmen.
Top of deadman wall is +8.5 (refer drawing S5.1) and the bottom of deadman wall is +3.5, so total embedment is 5 feet. Refer drawing S5.1 - SHEET PILE WALL DETAILS 1 for length of Type I and Type II deadman walls.
Existing tie rods/deadmen: Please confirm the extent of "cut and remove" vs. abandon in place (X1.1/X1.2), and the number of core-drilled 2" holes through the existing sheets.
Refer drawing X3.1 DEMOLITION SECTION, Section A for extent of cut and remove and abandon in place tie rods. Every alternate sheet piles of existing wall to be core drilled. Refer Section A, drawing S3.1.
May suitable excavated material be reused as backfill (31 23 00 all backfill as imported)?
Please identify disposal and stockpile limits.
Yes, excavated material behind the existing wall shall be used for backfill. Refer drawing S3.1 - SHEET PILE WALL DETAILS 1. - Section 1, Section A. Additional imported backfill material shall be as per Specification Section 31 23 00 Excavation and Fill .
Please provide planting areas and quantities (C3.1 gives none; the alterniflora band "+2 to +1.95" is effectively zero width). Please confirm how the 730-day period (32 93 00) relates to the 259-day contract duration, and how it is paid and released. How much retainage? Will QC and SSHO need to be on staff for inspections and any minor replanting?
The river bed is very flat at this location, so it is not zero width. The estimated Spartina Alterniflora planting area is 0.019 acre and Spartina Patens is 0.010 acre. Establishment period of 730 days shall commence as per Section 3.1G, Specification 32 93 00.The 730-day period will be handled as a warranty period on the plants similar to the 1-year general warranty on all work following final acceptance. Planting will be paid upon satisfactory completion of the work (initial planting), with no retainage. The government will periodically inspect and issue warranty letters for replacement of plants if needed during the warranty period. QC and SSHO will not be required for any inspection or replanting during the warranty period. Subcontractors should continue to follow established site safety and quality standards established for the project for any warranty inspection, maintenance, or replacement work.
Please confirm the haul road alignment and length (C1.4) and whether restored haul road/staging areas receive sod or just seeding.
The temporary haul road alignment shall be as shown in drawing C1.4. The haul road and staging area shall receive seeding. Road alignment must be based on existing site conditions, avoiding any disturbance of trees, and include pull-off areas. Contractor to define based on its equipment, laydown area and construcability needs.
Can the SSHO also serve as Environmental Manager and Waste Management? May the Superintendent also serve as SSHO? Must the QC Manager be on site full time during non-definable-feature work? Who can be dual hatted?
SSHO can serve as Enviromental Manager/Waste Manager and QC Manager.
Superintendent cannot have other role.
Do you need to be a Florida Licensed General Contractor or Marine Contractor to perform this work? Will you need local county contractor license registration of your Florida State License??
You will have to check with the state to see if they require license and registration.
Site visit RSVP deadline reads "December 12, 2025" and uses joseph_wingfield@nps.gov, which differs from the ios.doi.gov address elsewhere.
Confirm RSVP deadline and correct email for the Oct 20 site visit.
See Amendment 01 for the update.
Factor 5 asks for boardwalk construction and small building/utility work; Factor 1 refers to "historic seawall reconstruction." Neither appears in the Section C scope. Should offerors address these, or are they carryover text?
This response edits the text as follows:
Natural, Cultural, & Historical Resources - Working in close proximity and protecting (1) natural resources such as wetlands and (2) sensitive cultural resources where archaeological finds are likely similar to scope, magnitude and complexity of this solicitation.
Means/Methods – Construction of a seawall on-time and within budget that are similar in scope, magnitude, and complexity to this solicitation.
Section H, SR 1 says "fifteen 10 calendar days"; SF 1442 says 10 days. Confirm start-of-work period is 10 calendar days after NTP.
Start of work is ten (10) calendar days after NTP.
SF 1442 says offers due 1700 "local time" without naming the time zone (issuing office is Denver; project is in Florida). Confirm the time zone for the Nov 6 deadline.
17:00 Eastern Time
Section B refers to option line items, but only base CLINs 0001–0003 are listed. Confirm there are no option CLINs.
Only 3 CLINs, No option
Key personnel titles differ between Section H (Job Site QC Manager, Job Site Safety Manager) and Factor 6 (On-site QC Specialist, On-site Safety Specialist). Confirm these are the same positions.
Yes, these are the same positions.
NAICS code and size standard are blank in 52.219-1. Confirm NAICS code and size standard.
NAICS Code is 237990. The size standard is $45M.
Volume I "Other Submittals" says to include items, but none are listed. Confirm whether any other Volume I submittals are required.
No other submittals in Volume I are required.
In the solicitation on page 65 of 68 it requires under GENERAL REFERENCES: Complete and submit the attached "General References," form. Information will be used in determining Responsibility pursuant to FAR 9.103. There is no form provided for this requirement - can NPS upload the form which needs to be used on sam.gov?
See Attachment 07 - B08 - Attachment 07 - Vol_II - GenRefs.doc
On page 65 of 68 is states that there is a SUBCONTRACTING PERCENTAGE WORKSHEET: Complete and submit the attached "Report on Limitation on Subcontracting" form. The form itself requests input of amounts paid; however, for solicitation purposes, input projected amounts based on your proposed pricing and that of your anticipated Subcontractors . No form exists on sam.gov for this requirement.
See Attachment 10 - B08 - Attachment 10 - Limitation on Subcontracting Report Template
Sheet S5.1 calls for “MARINE GRADE ALUMINUM PILE CAP CONNECTED TO SHEET PILE THROUGH 3/8"x2 1/2" STAINLESS STEEL BOLTS”. It does not state what gauge aluminum to use for the cap. The specs also do not cover this. Please specify what gauge aluminum to use for the cap material.
Marine grade aluminum correspond to grade 6063 T6. Refer Division 2-49 Section 2.3-C Specification 31 41 16.16.
G1.1 Note 3 calls for the existing rubber trail to be reinstalled at the completion of the project. Is the existing rubber to be reused or new rubber to be used? If new rubber is to be used, please provide a detail for the rubber trail with material spec.
Existing rubbers shall be reused for reinstalling the trail after completion of construction activity.
C1.4 upper left corner note shows to install a fence to block access thru the trail during construction. Can a temporary chain link fence be used for this? Please provide the length of fence required.
Yes, this fence shall be temporarily installed and removed after completion of construction activity. The length of the temporary fence shall be sufficient to block pedestrian access during the construction the activity.
Spec 31 41 16.16 – Synthetic Sheet Piling – Installation requires us to use a blow hammer & count blows. Can we use a vibratory hammer to drive the sheets & drive them to the shown tip elevation on the drawings? The soils on the C drawings shows that a vibratory hammer should be able to drive the sheets to the proper tip elevation.
Vibratory hammer is acceptable if the Contractor find suitable for driving sheet piles at the project location. Refer Section 2.5-B, Specification 31 41 16.16.
Please provide the locations for construction temporary power & water connections. Water and electrical connections are not available on site. Contractor to provide, refer Specification 01 50 00 3.2-C & F.
Spec 31 41 16.16 – 3.5 calls for vibration control & monitoring within 200 feet from pile activity. It does not call out how many monitoring devices that you want used for this.
Do you want one at the Visitors Center, one at the Planters House & one at the Kitchen House? Please acknowledge if this is too many detection devices or if you want other structures monitored (Barn)?
The contractor shall install minimum two (2) monitoring devices, one at Visitor Center and other at Planter's House.
Spec 01 31 00 – 1.9 Permits - Are a Demolition & general building permits going to be required for this project from the city/county or are only the government procured regulatory permits listed in this section going to be required for this project?
Demolition and general building permits from city/county are not required for this project.
C1.4 Temporary Access Road – Is the entire temporary access road going to need to be removed after the project? If not, please specify the areas that can remain after construction is completed.
Yes. The entire temporary access road will need to be removed.
Has a gopher tortoise survey been completed by the government? Are any gopher tortoise burrows expected to be encountered by the contractor during construction?
Yes, please refer to drawing C1.4 for location of gopher tortoise burrows. The contractor will be responsible for obtaining the permit and relocating gopher tortoises as needed for construction.
Section 01 11 00 states that "All material deliveries must be planned on Mondays and Tuesdays". Does this restriction apply strictly to all deliveries (including minor couriers and small tools), or is it intended solely for heavy equipment and bulk material deliveries?
See response to #5. Require coordination with COR for delivery on other days, but generally intended to restrict heavy equipment and bulk material deliveries to days when the park is not open to the public.
Section 01 11 00 mandates that Phase 1, Phase 2, and Phase 3 must be conducted sequentially, with each phase substantially complete before the next begins. Will the National Park Service (NPS) allow for overlapping phases if the contractor utilizes multiple crews to accelerate the schedule?
No. Project should be bid in accordance with 01 11 00. See response to #3 for tree clearing exception.
The demolition plans and wall sections require the contractor to remove, salvage, and reinstall the 2"x6" horizontal facing timbers located above the splash zone. Given the existing wall's age and potential timber degradation, what percentage of the facing boards should bidders assume will need to be replaced with new timber?
Horizontal facing boards at or below splash zone to be demolished and replaced 100%. All boards above splash zone shall be reused except for those are in bad condition.
The typical PVC sheet pile wall section requires core drilling 2-inch holes through the existing PVC sheet piles to accommodate the new tie rods. Because the existing tie rods and concrete deadmen are to be abandoned in place, what is the approved protocol if a new tie rod coring location directly conflicts with the existing buried tie rods or hardware?
Existing tie rods shall be demolished and disposed up to the extent shown in drawing X1.1, X1.2 and X3.1. Core drilling 2" holes are for drainage purpose.
Section 31 41 16.16 prohibits pre-augering, spudding, or the use of water jets during synthetic sheet pile installation. If unanticipated dense soils or obstructions cause pile refusal before reaching the design tip elevation, how will the removal or penetration of these obstructions be compensated?
Refer response to question #11.
Section 31 23 00 designates "Gravel #57" for the gap between the existing and new walls. Can the NPS confirm that standard Florida Department of Transportation (FDOT) #57 stone is the acceptable material for this gravel fill?
Yes, FDOT Gravel #57 is acceptable material for filling the gap between existing and new wall.
Section 01 31 00 lists several government-furnished permits, including an Environmental Resource Permit (ERP) from the St. Johns River Water Management District and a Nationwide 13 permit from the U.S. Army Corps of Engineers. Will the full text of these permits be provided prior to the proposal deadline so contractors can review specific in-water work windows, turbidity monitoring mandates, or specialized marine protection conditions?
NWP 13/54 is provided in the amended solicitation. SJRWMD ERP permit is currently in process with discussions captured in the drawings and specs of this soliciation package. Permit will be shared when available. Appendix C to the specificationsis being developed with natural resource protection requirements and will be provided in the next amendment to this solicitation.
Section 32 93 00 establishes a 730-day (2-year) establishment period for the Spartina alterniflora and Spartina patens plantings. Will the contractor be responsible for all maintenance, watering, and replacement for the full two-year duration, and are there specific bonding requirements to cover this extended period after Substantial Completion?
See requirements of 32 93 00 for maintenance and replacement requirements.
The spartina plantings will be handled as a warranty item, no retainage or additional bonding required.
We respectfully request that the due date be extended to Friday, November 20, 2026, or to 14 calendar days after the amendment issuing Appendix C, whichever is later, with the question deadline reset to 7 days before the new due date. Please also state whether Appendix C will add work windows (nesting season or in-water restrictions), monitoring staff or reporting beyond the NWP conditions.
Appendix C has been included in Amendment 3 for requirements. The deadline will be extended to 11/13/2026 at 17:00 ET. Questions shall be submitted a minimum of 7-days prior to this new due date.
Placing stone with an excavator: S3.1 note 12 calls for hand-placed riprap. May the riprap be set with an excavator along the sheet pile wall, with hand chinking and hand setting against the wall where needed to meet the hand-placement requirement?
The stones may be transported to the location through excavator but needs to be hand installed. The contractor shall coordinate with the Contracting Officer for installation means and method and follow permit conditions. Refer Division 2-49 Section 3.1-B-13 Specification 31 37 16 for Hand Installation. No excavation is permitted infront of the existing wall.
Design quantities: Please provide the design tonnage for riprap and bedding stone and the design excavation cubic yardage so all offerors price on the same basis.
Plan dimension and cross sections for riprap shown in drawing S1.1, S1.2, S1.3 and C3.1. The bidders shall calculate the volume/tonnage based on these details.
Trees in conflict with tie rods and deadmen: The plans call for removal and replacement of one cedar tree, but the drawings show many existing trees directly in line with the new tie rods and deadmen. How will these trees be handled: are they removed only, or removed and replaced? Will a separate CLIN or unit price be provided per tree, or how should offerors budget for an unknown number of trees?
The contractor shall not remove any trees other than a ceder tree to be replaced shown in drawing S1.1. The contractor to inform the Contracting Officer if any tree is present at the deadman or tie rod location. The design will be modified based on the findings. Refer Note 6 & 7 of drawing S1.1 and S1.2. All palm trees to be protected during the contruction.
Aluminum cap vs. timber cap: The pile cap details (S5.1) show a marine-grade aluminum cap and a timber cap. Enlarged, the two appear to interfere. Should the timber cap be cut or notched to fit around the aluminum cap, or is only one of the two required?
Both are required. The timber board to be cut or notched to fit around the aluminum cap.
| Amendment of solicitation/modification of contract |
| Contract ID code |
| Amendment/modification number |
| Effective date |
| Requisition/purchase requisition number |
| Project number |
| Issued by |
| Code |
| Administered by |
| Code |
| Name and address of contractor |
| Code |
| Facility code |
| Amendment of solicitation number |
| Dated |
| Modification of contract/order number |
| Dated |
| This item only applies to amendments of solicitations |
| Accounting and appropriation data |
| This item applies only to modifications of contracts/orders. |
| This change order is issued pursuant to: |
| The above numbered contract/order is modified to reflect the administrative changes |
| This supplemental agreement is entered into pursuant to authority of: |
| Other |
| Important: |
| Description of amendment/modification |
| Name and title of signer |
| Contractor/offeror |
| Date signed |
| Name and title of contracting officer |
| Signature of Contracting Officer |
| Date signed |
| Previous edition unusable |
| Standard form 30 (rev. 11/2016) |
| Continuation sheet |
| Reference Number |
| Name of Offeror or Contractor |
| OPTIONAL FORM 336 (4-86)) |
Sponsored by GSA FAR (48 CFR) 53.110
Sheet1
File details come from the government source that posted it. Updated .