This document is Amendment 00006 to a solicitation (140P2026R0013) issued by the National Park Service (NPS), Desert Landscape Conservation Cooperative (DSC) Contracting Services Division, for Titus Canyon Road repair work. The amendment extends the proposal deadline to Tuesday, February 10, 2026, at 9:00 AM Mountain Time in response to contractor questions.
The amendment comprises 43 questions and answers addressing clarifications on project specifications and requirements. Key substantive answers include: compaction testing is required only for material with less than 50% retained on a No. 4 sieve, with contractors responsible for independent testing lab costs; clay from cuts may be mixed with un-cohesive soils where beneficial; temporary resource protection fencing is only required where shown on plans; no office trailer is required; truck turnarounds cannot be enlarged beyond plan limits; contractors may work Monday through Friday only with no night work permitted; an NPS archeological monitor will be present during all ground-disturbing activities; the project allows up to two simultaneously active work sites per resource monitoring type (maximum six total); the roadway will remain closed to the public for the entire project duration; no culvert installations or gravel imports are anticipated; riprap must be imported from outside the project; and rock chips are available at Daylight Pass Mixing Table Site from station 443+58 to 458+75. The project completion timeline is 365 days from Notice to Proceed, with the government's goal being issuance of NTP on or before April 1, 2026.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: is not is required copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7.ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
PAGESOF
Contractor
The hour and date specified for receipt of Offers to sign this document and return
Rachel Dyer
See continuation page
NPS, DSC Contracting Services Div 1 Denver Federal Center, Building 50 P.O. Box 25287 Denver CO 80225-0287
DOI, NPS, DSC Contracting Services 1 Denver Federal Center, Building 50 P.O. Box 25287 Denver CO 80225-0287
PDS
PDS
140P2026R0013
01/17/2026
12/10/2025
1 11
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
140P2026R0013/0006
THE PURPOSE OF AMENDMENT 00006 IS TO ANSWER
QUESTIONS FOR THIS PROJECT.
Question 1: 1. Reference: Sheet D-10. During the walkthrough, the idea of mixing the clean gravel material (that's already onsite) with the clay in cuts was discussed. referring to sheet D-10 Notes and Callouts: "Place 25% clay and 75% 3" minus, evenly mixed to the acceptance of the NPS CO, Salvaged material in
6" lifts, see note 1" - Is this application allowed in road ripping with rock chip applications? Is this for more areas than just what's on D-10 (the geogrid area)? If so, please clarify. Is this for the rock chip application of 50/50 clean gravel material? Do you want this mixture on anything beyond the 6" fill areas? Also, if this is the end product, then the FP-24 states a compaction and moisture test is needed for anything with <50% retained on #4. Does D-10 clearly state that the NPS CO overrides the FP-24 in the field, or will the
Contractor refer to the FP-24 and pay for the required independent testing Lab?
Answer 1: The clay material in the cuts identified in the plans may also be used for mixing with un-cohesive soils anywhere it would be beneficial but is not required outside of the areas indicated in the plans. Sheet D-10 does not state or imply that the CO overrides the referenced FP-24 requirement for compaction testing for material with less than 50% retained on a No. 4 sieve.
Question 2: Please confirm 1. Required testing and acceptance criteria for this blended material (gradation, moisture-density, etc.).
2. Field determined or independent lab. If lab, is that contractor's responsibility? 3. Whether this requirement applies uniformly or only were shown on specific details or locations confirmed in your response.
Answer 2: Field determination can suffice if method of testing is accepted. Testing is required only where plans, specifications, or referenced specifications indicate. For
Continued...
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C) example, the FP-24 requires compaction testing for material with less than 50% retained on a
No. 4 sieve.
Question 3: Reference: Section31 23 00, Paragraph 1.4 Submittals (Items G.1. and G.2.)
Section 31 23 00 references material submittals but does not clearly identify testing requirements. Please confirm, whether maximum density curves are required for: Native material, blended clay/aggregate material, imported aggregate. Furthermore, is the contractor required to retain and pay for an independent testing lab or if testing will be performed by the Government? We're guessing at least 10 different soil types on site.
Answer 3: Per the referenced FP-24 Section 204, compaction testing is required for material with less than 50% retained on a No. 4 sieve.
The contractor is responsible for obtaining the services of a testing lab.
Question 4: Reference: Grading Notes;
Environmental Protection requirements, several plan details state "no side casting of material." Please clarify whether the
Contractor may: Blade the roadway between work areas, side cast loose rock within the roadway to prevent tire damage, perform this work particularly on steep sections beyond White
Summit. If not permitted, please identify approved handling methods.
Answer 4: "Side casting" in this contract refers to the practice of pushing or dumping excavated material (spoil) over the downslope side of the road embankment. It is permissible to use excavated material from the inboard
(cut) side of the road to fill gullies or holes in the outboard side of the road, but not permissible to dump that material over the edge of the roadway bench to waste it.
Question 5: Reference: temporary Access Notes;
Turnaround Callouts - Please clarify whether truck turnarounds may be enlarged beyond the plan limits to accommodate construction
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C) equipment, provided final restoration is performed and impacts remain within approved disturbance limits.
Answer 5: Truck turnarounds may not be enlarged beyond the limits shown on the plans.
Question 6: Reference: environmental Protection
/ avoidance area plans - Please confirm whether temporary fencing is required to prevent tire tracks or equipment encroachment outside approved work limits and identify locations where suck controls are mandatory (i.e. rock walls, etc.).
Answer 6: Temporary resource protection fencing is only needed where shown on the plans. For example, around station 443+00 on Sheet P18.
Question 7: Reference Section 01 50 00-3 temporary Facilities - Please confirm whether the contractor is required to supply an office trailer or whether alternative arrangements are acceptable.
Answer 7: The contractor is not required to supply an office trailer. The government will not provide this.
Question 8: Sheet P32 - On P32 of the plans, at station 609 there's a callout that states,"
Utilized secondary flake retouched bifacially."
What does this mean?
Answer 8: Please disregard this callout.
Question 9: If a desert tortoise is encountered off the roadway, please confirm whether construction equipment may continue traveling along the roadway to access other work areas and continue work, provided the tortoise is not within the travel path.
Answer 9: Yes, construction equipment and vehicles may continue to use the roadway to access work in other areas.
Question 10: Please confirm whether the Titus
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
Canyon Road corridor has been fully surveyed for archaeological resources and whether additional stop-work notices are anticipated during construction.
Answer 10: An NPS archeological monitor will be present during all ground-disturbing activities within NRHP-eligible properties to ensure they are not impacted. The monitor will have the authority to temporarily halt construction if potential cultural resources are encountered, and to redirect activities away from sensitive areas. If previously unknown cultural resources are encountered during the road repair project, all work within 50 feet of the discovery will cease and the find will be immediately reported to the project archeologist and NPS cultural resources staff. Any resource will be protected in place until it can be evaluated for NRHP eligibility and appropriate treatment measures can be determined in consultation with the SHPO and affiliated tribes. If NRHP-eligible sites cannot be avoided and will be impacted by the road repair project, appropriate data recovery and curation measures will be implemented to mitigate the loss of important cultural information. Data recovery may include detailed recordation, mapping, photography, and selective excavation of threatened features or deposits.
Question 11: Do you anticipate NTP happening on or before April 1, 2026?
Answer 11: Yes, that is the government's goal.
Question 12: The solicitation states 365 days to complete after NTP but the specifications say project completion Dec 31, 2026, please clarify.
Answer 12: This is an estimated date. It will be 365 days to complete work from notice to proceed (NTP). Once award is made the contractor will have a better idea of when work will start and end 365 days from NTP.
Question 13: Milestone/ Pay Items I am assuming
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C) this will be negotiated after award?
Answer 13: Pay items will not be negotiated.
Milestone submissions shall be submitted by contractor and will be a factor of award and negotiated after award.
Question 14: Compaction Testing can you guys please clarify compaction testing requirements.
Answer 14: Per the referenced FP-24 Section
204, compaction testing is required for material with less than 50% retained on a No. 4 sieve. The contractor is responsible for obtaining the services of a testing lab. For material with more than 50% retained on a No. 4 sieve, testing is not required but compaction must comply with FP-24 Section 204.11(a) and
(b).
Question 15: Are there environmental noise restrictions during certain times of the year we need to be aware of? IE migratory bird seasons. Additionally, will contractors be allowed to work 6 days a week M-S with the option for night work in the summer extreme heat?
Answer 15: There are no special noise restrictions for certain times of year.
Contractors will be allowed to work Monday through Friday only. Night work will not be allowed.
Question 16: Can an Interest-bearing CD be used in lieu of a traditional bond if awarded?
Answer 16: No, that will not be accepted.
Question 17: Without the CAD files or a quantity from the Government it is very difficult to tell how much exclusion fencing will need to be provided for the sensitive areas. The Contractor is respectfully requesting the Government provide a rough quantity of fencing the Contractor will need to provide so all bids will be similar and
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C) comparable and also to limit future change orders.
Answer 17: The Government respectfully declines the request due in part to known minor anomalies in the CAD files. Please use the plans provided to estimate quantities.
Question 18: Do the Superintendent, SSHO and QC
Manager need to be 3 separate individuals?
Answer 18: The Quality Control Supervisor must have no other duties. The Superintendent and
Safety Officer may be the same individual.
Question 19: Please provide the site visit attendee sign in sheet.
Answer 19: This was posted under amendment 5.
Question 20: Please provide bidding quantities for damaged base course or confirm repairs due to discovery of damaged base course demolition will be treated as differing site conditions under FAR 52.236¿2 or addressed as a change under FAR 52.243¿4.
Answer 20: There is no existing base course in the project area.
Question 21: Is there a bulk water fill i.e. a hydrant or water source we can pump from for grading operations in close proximity?
Answer 21: Per specification 01 50 00 - 1
040225 TEMPORARY FACILITIES AND CONTROLS, Water
Service: There is no available potable or non-potable water source on site. The
Contractor will need to provide all necessary potable and non-potable water. The Contractor may contact Beatty Water and Sanitation
District to coordinate the purchase of water for use on the project. 1. Beatty Water and
Sanitation District, 101 N. 2nd St., Beatty, Nevada (775) 553-2931.
Question 22: Does this project require phasing?
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
Answer 22: No phasing is required.
Question 23: Is this project tax exempt?
Answer 23: No.
Question 24: When do you anticipate on site work starting?
Answer 24: When the notice to proceed is issued to the awardee.
Question 25: Are third party inspections required?
Answer 25: No.
Question 26: Is permitting required?
Answer 26: Yes. See specifications section 01
31 00 - 8, PROJECT MANAGEMENT AND
COORDINATION.
Question 27: Please provide staking data points for the project.
Answer 27: Staking data points will not be provided. See Sheet C2 Note 4 for further details.
Question 28: Are red, yellow, and blue tops required?
Answer 28: No.
Question 29: Is it the contractor's responsibility to provide an Archeologist and
Biologist? If so, will the Archeologist be required to be onsite for all ground disturbing activities?
Answer 29: No.
Question 30: Is it the contractor's responsibility to provide planetological services? If so, what are the requirements?
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
Answer 30: No.
Question 31: Is an SWPPP required?
Answer 31: Yes.
Question 32: Should FP-24, as referenced in the specifications, be used as the baseline, with the project-specific specifications taking precedence where they supersede?
Answer 32: Yes.
Question 33: Will any scope of work for this project be processed as QL pay items? If so, which ones?
Answer 33: No, none.
Question 34: Can we shut down roadway access, or do we need to maintain one lane for travel?
Answer 34: The roadway will remain closed to the public for the entire duration of the project. See specifications section 01 11 00 -
3, SUMMARY OF WORK for more details.
Question 35: What are the limitations for construction intervals (for proposed road work)?
Answer 35: There can be up to two simultaneously active work sites for each type of resource monitoring area. For example, there can be work happening simultaneously in two archeological sensitive areas and in two tortoise monitoring and in two paleontological sites (a maximum of six active resource sites total at the same time). There are no construction interval restrictions for work outside of resource monitoring areas.
Question 36: Please provide lay down/staging area for construction.
Answer 36: Temporary truck turnarounds shown on the plans may be used for laydown and staging.
The largest turnaround is shown on Sheet P33 at
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C) station 628+00.
Question 37: Will the contractor be able to install anchor points on top of the slope for safety scaling?
Answer 37: Yes.
Question 38: Once the anchors are set in the ground, they will not be able to be moved. Does the NPS want the contractor to cut the anchors off flush or leave in place for possible future safety scaling?
Answer 38: Cut anchors flush.
Question 39: What are the hauling restrictions for this project?
Answer 39: Per specifications section 01 11 00
- 3, SUMMARY OF WORK, Hauling Restrictions:
Comply with legal load restrictions in hauling of materials. Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the
Office of the Park Superintendent. A special permit will not relieve Construction Contractor of liability for damage which may result from moving of equipment.
Question 40: "Per the specs "Any repairs to portions of Titus Canyon Road that contribute to its historic significance will follow the
Secretary of the Interior's standards for rehabilitation of a historic structure 36 CFR
68.3(b)." Where are the features that are in need of protection? There are no locations shown on the drawings.
Answer 40: The features consist primarily of low stacked rock walls, berms and fills. These areas are indicated in red on the plans. These features are to be protected from damage. There is a wooden box culvert at station 493+79 that is of historic significance that needs to be
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C) protected from damage.
Question 41: After reviewing documents, I am still unclear as to the number of culverts that need to be installed, specific type of culvert and size of requested culverts. The documents speak about cleaning out existing culverts however the quantity of how many need to be cleaned out is also unclear. Do you guys have a rough estimate of how much Rip Rap and Gravel need to be hauled in from an outside source;
this is also a little unclear in the documents?
Answer 41: No culvert installations are included in the project. No gravel import is anticipated to be needed. Riprap needs to be imported from outside the project as indicated on the plans. No riprap quantities are available (please estimate quantities from plans).
Question 42: Can you please provide chip rock locations?
Answer 42: The rock chips are available at
Daylight Pass Mixing Table Site, as indicated on the plans cover sheet. The rock chip application area is from station 443+58 to
458+75.
Question 43: Can the solicitation be extended to provide more time for answered questions?
Answer 43: Yes, the solicitation is hereby extended to Tuesday, February 10, 2026, due no later than 9:00am MT.
| Amendment of solicitation/modification of contract |
| Contract ID code |
| Amendment/modification number |
| Effective date |
| Requisition/purchase requisition number |
| Project number |
| Issued by |
| Code |
| Administered by |
| Code |
| Name and address of contractor |
| Code |
| Facility code |
| Amendment of solicitation number |
| Dated |
| Modification of contract/order number |
| Dated |
| This item only applies to amendments of solicitations |
| Accounting and appropriation data |
| This item applies only to modifications of contracts/orders. |
| This change order is issued pursuant to: |
| The above numbered contract/order is modified to reflect the administrative changes |
| This supplemental agreement is entered into pursuant to authority of: |
| Other |
| Important: |
| Description of amendment/modification |
| Name and title of signer |
| Contractor/offeror |
| Date signed |
| Name and title of contracting officer |
| Signature of Contracting Officer |
| Date signed |
| Previous edition unusable |
| Standard form 30 (rev. 11/2016) |
| Continuation sheet |
| Reference Number |
| Name of Offeror or Contractor |
| OPTIONAL FORM 336 (4-86)) |
Sponsored by GSA FAR (48 CFR) 53.110
File details come from the government source that posted it. Updated .