CHIC 240631 WTP AND MAINTENANCE BUILDING Federal contract opportunity
Solicitation number
140P2025R0014
Issued by
Department of the Interior National Park Service National Office

About this file

This document is a Questions and Answers (Q&A) file for Solicitation 140P2025R0014, a federal contract opportunity to construct a water treatment plant and maintenance building. The solicitation involves a Design-Build project with specific requirements for Architectural-Engineering (AE) and General Contractor (GC) teams, including submission of Standard Form 330, past performance documentation, and project experience. Key details include:

The solicitation requires each team to submit 3-5 past performance projects, with specific conditions: the GC must have been the prime contractor on at least one project, the AE must have developed detailed design documents for at least one project, and preferably the AE and GC have previously worked together. The proposal submittal due date was extended to September 22, 2025, at 1:00 PM Mountain Time. Offerors must demonstrate a bonding capacity of at least $15 million for a single project, and while there is no specified dollar range for project experience, the government will evaluate technical qualifications and specialized experience based on project size, scope, and complexity.

View the file

Other files for this federal contract opportunity

Other files attached to CHIC 240631 WTP AND MAINTENANCE BUILDING, newest first.
File Type Posted
B09_Amendment_5_Questions_and_Answers_0005.pdf PDF
Sol_140P2025R0014_Amd_0005.pdf PDF
Sol_140P2025R0014_Amd_0004.pdf PDF
Sol_140P2025R0014_Amd_0003.pdf PDF
B09_Amendment_3_Questions_and_Answers_0003.pdf PDF
Sol_140P2025R0014_Amd_0002.pdf PDF
B09_Amendment_01_Questions_and_Answers_0001.pdf PDF
Sol_140P2025R0014_Amd_0001.pdf PDF
B08_Attachment_4_SF330.pdf PDF
B08_Attachment_7_Limitations_on_Subcontracting_Report.xlsx XLSX spreadsheet
B08_Attachment_2_POR_Appendices.pdf PDF
Sol_140P2025R0014.pdf PDF
B08_Attachment_6_General_References.docx DOCX document
B08_Attachment_5__Past_Performance_Questionnaire.docx DOCX document
B08_Attachment_1_CHIC_240631_POR.pdf PDF
B08_Attachment_3_Wage_Determination.pdf PDF
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

140P2025R0014

CHIC 240631 CONSTRUCT WATER TREATMENT PLANT AND MAINTENANCE

BUILDING

Question No.

Sheet or

Reference Question Response

Date Answered

Amendment Number

1 Section L

“Each Offeror shall complete and provide the attached Standard Form 330 Part I and II for the AE and GC on the DB team and documentation sufficient to demonstrate the extent of the Offeror’s past experience for at least three (3) but no more than five (5) projects of similar size, scope, and complexity (as further defined in this evaluation factor). Of this group of similar projects, the GC must have served as the prime contractor of at least one project, the AE must have had responsibility for developing the detailed design and construction documents for at least one project, and the AE and GC worked together of at least on project.”

1) Can the government provide any additional context as to what constitutes “similar, size, scope and complexity” when it comes to past performance, including the required dollar range?

Phase I Factor 2 Technical Qualifications and Specialized Experience provides context for size, scope, and complexity for Phase I Factor 3 Past Performance.

NPS does not specify a required dollar range.

8/21/2025 1

2 Section L

2) Can the government provide additional context as to what is meant by the line “…and the AE and GC worked together on at least one project?” Is it the government’s intention that this requirement be restricted to a GC and AE having worked together on a Design Build project of similar size, scope and complexity, whereby the AE was under contract to the GC? Or is it also acceptable if the GC and AE worked together on a Design Bid Build project where the AE was the designer of record for the owner? Or are both scenarios (Design Build and Design Bid Build) acceptable?

"and the AE and GC worked together of at least on project. ” Is changed to "Indicate where the AE and GC have worked together on a project(s). Prior experience working together will be rated more favorably."

This requirement is not restricted to a GC and AE that have previously worked together on Design Build Project.

8/21/2025 1

3 POR

Do you have a higher quality set of drawings? Then ones we downloaded off of Sam.Gov are pixelated in important areas.

The lower quality figures in the POR document are available in the Attachment 2 POR Appendices document in higher quality.

8/28/2025

4 Section L Phase 1, Volume 1, Factor 3 – Due to the recent reduction in force, there is no one remaining to fill out a past performance questionnaire for a relevant experience. Can we submit previously completed and signed questionnaires?

The preference is to have recent PPQs; however, previous PPQs are better than no PPQs.

8/28/2025

Question No.

Sheet or

Reference Question Response

Date Answered

Amendment Number

5 Section L

Phase 1, Volume 1, Factor 2, page 77 – I have a few questions about the SF 330 requirements.

Page 77 says the GC is supposed to fill out this form. However, this form is typically for the AE team and even states that it is for Architect-Engineering Qualifications. For example, the list of disciplines on page 5 of the SF 330 mentions a construction manager, but there’s not a code for roles required for this project, such as superintendent and quality control manager. Is there another form that the GC can complete? Or can the GC provide project information / write-ups in the proposal rather than on this form?

The SF 330 requires personnel resumes via page 10 of the form, but Phase 2, Factor 4 also requires key personnel resumes. Do we just fill out the past performance part of the SF330?

The GC can provide project information / write-ups in the proposal that provide similar quality information as a comparable to the SF330 form (Attachment 4 of Solicitation) that is more aligned to Architect-Engineer Qualifications

Yes, fill out the past performance part of SF330. NPS can seek additional information in clarification/questions if applicable

8/28/2025

6 Section L The third full paragraph on page 77 states, “Both the prime contractor and the design firm(s) shall each submit no more than five (5) projects.” Just to clarify, is that 5 projects total or 5 projects each?

Submit no more than 5 each. 8/28/2025

7 Section L

Page 77 states, “The Offer may provide a supplemental narrative (not project lists) not to exceed two (2) pages, explaining how any corporate experience that is not directly related to the specific projects above is applicable to this project and how the Government will benefit.”

Is that per project or total for all 3-5 projects?

As it states this supplemental narrative is not directly related to the projects above. It is a 2 page total limit, not 2 pages per project. It is up to the offeror to determine the content so long as its not just a project list.

8/28/2025

8 Section L Page 78 says, “Submit proof of bonding capacity with a minimum of $15 million for a single project. Proof of bonding capacity is a go/no-go factor under Phase 1.” I don’t see a go/no-go list anywhere else.

There is no list 8/21/2025 1

We would like to request a 1-week extension based on these questions and on the upcoming Labor Day holiday.

Proposal submittal due date is extended to September 22, 2025 at 1300 Mountain Time.

8/28/2025

10 Section L On the past experience projects, it states between 3 and 5 projects. Can you clarify if that is combined for the AE and GC or is it 3 to 5 for the GC and 3 to 5 for the AE?

Please see Question 6 8/28/2025