Sol_140P2024R0016_Amd_0006.pdf
PDF 145 KB Posted
- Attached to
- GRSM 213075 Laurel Falls construction Federal contract opportunity
- Solicitation number
- 140P2024R0016
About this file
This document provides information on an upcoming federal contract opportunity to rehabilitate the Laurel Falls Trail in Great Smoky Mountains National Park. The National Park Service seeks to award a firm-fixed price construction contract requiring both technical and price proposals. Work includes demolishing and removing the existing trail surface, rehabilitating the trail foundation and retaining walls, replacing culverts, rehabilitating the viewing platform and visitor areas, installing new retaining walls, and constructing new and rehabilitated parking areas along Fighting Creek Gap Road. The period of performance is 540 days with an estimated price range of $5-10 million. Interested vendors should monitor SAM.gov for solicitation number 140P2024R0016, which is anticipated to be issued on or about November 6, 2023, subject to availability of funding. The proposal receipt date will be specified in the solicitation.
View the file
Other files for this federal contract opportunity
Show all 27
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140P2024R0016 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
PDS
Denver CO 80225-0287 P.O. Box 25287 12795 W. Alameda Pkwy NPS, DSC Contracting Services Div
01/16/20240006
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
01/16/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Amendment 006:
The purpose of this Amendment is to provide NPS Responses and Revisions based on the
Pre-Bid Questions received as of March 7, 2024.
Pre-bid questions are now closed.
Proposal due date is extended from March 14, 2024 to March 25, 2024 at 4:00 PM EST.
All other terms and conditions remain unchanged.
All amendments must be acknowledged.
This project will rehabilitate the Laurel Falls trail. Work includes demolition and removing the existing surface, rehabilitating the trail foundation, and widening the trail
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Cary Atwood
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140P2024R0016/0006 where required. Retaining walls will be rehabilitated and culverts replaced.
Work also includes rehabilitating the viewing platform, replacing all directional and informational signage, and rehabilitating the visitor viewing area around the falls. New retaining walls will be installed to prevent erosion, and areas degraded by high visitor traffic will be restored and native vegetation replanted. Existing visitor viewing areas will be rehabilitated and new viewing locations will be evaluated and added as required.
This project includes new and rehabilitated parking areas along the Fighting Creek Gap Road between the Elkmont Campground Entrance Road and
Maloney Point. Work includes removing the existing surface, rehabilitating existing parking areas, and constructing new parking areas. New retaining walls will be installed to allow for the new parking areas.
PROJECT TEAM:
NPS PM/COR: Herbert Kupfer
NPS PS: Melissa Bagga
NPS CO: Cary Atwood
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
REVISED RFP ITEMS
Attachments:
Revision #3 Provide as additional attachment to this Solicitation:
1. NPS Responses for Pre-Bid Questions 34-53.
Solicitation Response Date Update:
The Solicitation Response date is extended from: March 14, 2024, to March 25, 2024 by 4:00 PM Eastern Time.
Pre-Bid Questions:
Pre-Bid Questions are now closed.
Solicitation Reminders:
Prospective Offerors and interested vendors are responsible for ensuring that they have the complete and the most current Solicitation information through the Government Point of Entry (GPE) at SAM.gov under Solicitation No. 140P2024R0016 for GRSM 213075. Once you open the Solicitation Notice for 140P2024R0016, you may click on the Follow button in the upper right-hand corner to receive automatic notifications through the SAM.gov system, with respect to this notice. No other notifications will be provided.
File details come from the government source that posted it. Updated .