140P2020R0027-0005_Att01_ContractPriceSchedule_200605_0005.xlsx

XLSX spreadsheet 15 KB Posted

Attached to
STLI 211568-Stabilize Ellis Island Seawall
Solicitation number
140P2020R0027
Issued by

About this file

This document contains a revised contract price schedule for solicitation number 140P2020R0027 to stabilize the Ellis Island seawall. The National Park Service is seeking offers for base line items including demolition, temporary floating berths, north and west seawall strengthening, slip and island seawall strengthening, fender and bollard replacements, ferry slip scour restoration, settlement monitoring, and rehabilitation repairs. Option line items include potential south east island and south slip seawall strengthening. Offerors must provide pricing for all base and option line items. Unit pricing is required for unit priced items with extended totals, and lump sums for lump sum items. The total proposed price should include the base price plus all option prices. Offerors are advised to review the definition of contract line items specification for measurement and payment details.

View the file

Other files

File Type Posted
Sol_140P2020R0027_Amd_0009.pdf PDF
140P2020R0027-0009_Att01_QuestionsAndResponses_01-116_2007xx_0009.docx DOCX document
Sol_140P2020R0027_Amd_0008.pdf PDF
140P2020R0027-0008_Att01_QuestionsAndResponsesW-Attachments_200702_0008.zip ZIP file
140P2020R0027-0007_Att01a_ContractPriceSchedule_200622_0007.xlsx XLSX spreadsheet
Sol_140P2020R0027_Amd_0007.pdf PDF
140P2020R0027-0007_Att01_QuestionsAndResponses_01-116_200626_0007.pdf PDF
140P2020R0027-0007_Att01b_Response116-SpecSection-01_27_00corrected_0007.pdf PDF
140P2020R0027-0006_Att01_QuestionsAndResponses_01-71_200619_0006.pdf PDF
140P2020R0027-0006_Att02_RevWageDeterminations_200619_0006.zip ZIP file
Sol_140P2020R0027_Amd_0006.pdf PDF
Sol_140P2020R0027_Amd_0005.pdf PDF
140P2020R0027-0005_Att02_QuestionsAndResponses_01-52_200609_0005.zip ZIP file
Sol_140P2020R0027_Amend 0004.pdf PDF
140P2020R0027-0004_Att01_PrepropMigDocs_200521_0004.zip ZIP file
Sol_140P2020R0027_Amd_0003.pdf PDF
140P2020R0027-0002_Att02_DVB_GD-NY03_NewYork-Heavy_200501_0002.pdf PDF
140P2020R0027-0002_Att03b_PreproposalPresentation-ProjectRqmts_200512_0002.pdf PDF
Sol_140P2020R0027_Amd_0002.pdf PDF
140P2020R0027-0002_Att03a_PreproposalPresentation-ContractRqmts_200511_0002.pdf PDF
140P2020R0027-0002_Att01_PropSumissionPkg_RevCPSs_200515_0002.zip ZIP file
140P2020R0027-0002_Att04_PostIVAccessForm_200513_0002.xlsx XLSX spreadsheet
Sol_140P2020R0027_Amd_0001.pdf PDF
140P2020R0027-0001_SF1442r1_200508_0001.pdf PDF
140P2020R0027-Att02a_Combined Drawings_001-100of235_200226.pdf PDF
140P2020R0027-Att02b_Combined Drawings_101-235of235_200226.pdf PDF
140P2020R0027-Att04_Permit and Env Compliance Documentation_200214.zip ZIP file
140P2020R0027-Att05_PropSubmissionPkg-forms_200505.zip ZIP file
Sol_140P2020R0027.pdf PDF
140P2020R0027-Att03_Construction Wage Rates_200410.zip ZIP file
140P2020R0027_Att01_Specifications_200410.pdf PDF
140P2020R0027-Att05_PropSubmissionPkg-sample_200505.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Revised BLANK

CONTRACT PRICE SCHEDULE
Solicitation Number: 140P2020R0027
PARK - PMIS: STLI-211568
Developed Area: Statue of Liberty
Project Title: Stabilize Ellis Island Seawall
Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all option line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts govern. Round totals and extended prices to whole dollars.
Contract Line Item Number (CLIN)Contract Line Item (CLI) TitleQuantityUnit of MeasureUnit PriceTotal Price
1Demolition, Removals, Site Work1LS$0.00$0.00
2Temporary Floating Berth1LS$0.00$0.00
3North and West Seawall Strengthening
3ACombi Wall1,340LF$0.00$0.00
3BNew Steel Sheet Pile Wall399LF$0.00$0.00
3CAccess Bridge Stabiliation1LS$0.00$0.00
4Slip North Seawall Strengthening662LF$0.00$0.00
5North Island Seawall Strengthening596LF$0.00$0.00
6Replace Fender System370LF$0.00$0.00
7Bollards and Cleat Reinstallations17EA$0.00$0.00
8Ferry Slip Scour Restoration1LS$0.00$0.00
9Settlement and Vibration Monitoring Program1LS$0.00$0.00
10Rehabilitation Repairs
10AToe Wall Rehabilitation768LF$0.00$0.00
10BConcrete Repair Type 1A2SF$0.00$0.00
10CConcrete Repair Type 1B3SF$0.00$0.00
10DConcrete Repair Type 22EA$0.00$0.00
10EConcrete Repair Type 35SF$0.00$0.00
10FConcrete Repair Type 4100SF$0.00$0.00
10GMasonry Type 127,734LF$0.00$0.00
10HMasonry Type 230EA$0.00$0.00
10IMasonry Type 3166EA$0.00$0.00
10JMasonry Type 4863LF$0.00$0.00
11Miscellaneous Work
11AWave Erosion Repair25000SF$0.00$0.00
11BShore Power Replacement1LS$0.00$0.00
11CMonitoring Personnel180DAY$0.00$0.00
11DMisc Sitework1LS$0.00$0.00
11EContaminated Material Management and Disposal2,500CY$0.00$0.00
TOTAL BASE PRICE (Contract Line Item Number 1 through 11) ----------------------------------------------------------------------------------------------------------------$0.00
12Option A: South East Island Seawall Strengthening185LF$0.00$0.00
13Option B: South Slip Seawall Strengthening
13AStabilization573LF$0.00$0.00
13BPassenger Access Ramps1LS$0.00$0.00
TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Number 12 through 13) ---------------------------------------------------------------------------------------------$0.00
TOTAL PROPOSED PRICE - BASE PLUS ALL OPTIONS (Contract Line Item Number 1 through 13) -------------------------------------------------------------------$0.00
Refer to Division 01 Specifications Section 01 27 00 Definition of Contract Line Items for additional measurement and payment information.

File details come from the government source that posted it. Updated .