ROCR_185767-FinalCDSpecs-101019.pdf
PDF 2 MB Posted
- Solicitation number
- 140P2020R0005
About this file
This federal contract opportunity notice solicits proposals for construction services to preserve and protect Meridian Hill Park in Washington, DC. The project scope includes restoration of exposed aggregate concrete features, drainage improvements, replacement of trees and landscaping, repairs to stairs and walls, and installation of accessible walkways. The National Park Service seeks to award a firm-fixed price contract from January to February 2020, with an estimated value between $5-10 million. Proposals are due by December 5, 2019. Interested vendors must register in the System for Award Management and have a DUNS number to conduct business with the federal government. The NAICS code is 237990 for other heavy and civil engineering construction. Small businesses are encouraged to participate, and a subcontracting plan is required for large businesses.
Specifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B08_Amend 02_111919.pdf | ||
| B08_Amend 04_120919.pdf | ||
| B08_Amend 01_110719.pdf | ||
| B08_Amend 05_121719.pdf | ||
| B08_Amend 03_120219.pdf | ||
| B08_Attch_4_Bid_Bond.pdf | ||
| Langan Storm Sewer Report.pdf | ||
| B08_Attch_8_Prop_Equals.doc | DOC document | |
| B03_Solicit_Wages_140P2020R0005.pdf | ||
| ROCR_185767_Final_Construction_Documents_reduced.pdf | ||
| B08_Attch_6_PP_Qstr.docx | DOCX document | |
| B08_Attch_7_Sub_Plan_Sample.doc | DOC document | |
| B08_Attch_10_Haz_Mat.doc | DOC document | |
| Architrave Report.pdf | ||
| B08_Attch_9_Gen_References.doc | DOC document | |
| B08_Attch_5_Exp_Qstr.docx | DOCX document | |
| Langan Geotech Report.pdf | ||
| B08_SF1442_ROCR_185767_140P2020R0005.pdf |
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MERIDIAN HILL PARK
WASHINGTON, DC
CONTRACT # P15PC00042
PRESERVE AND PROTECT MERIDIAN HILL PARK PHASE 5 & 6
ROCR
PMIS NO. 185767
PROJECT SPECIFICATIONS
FINAL CONSTRUCTION DOCUMENTS
NATIONAL PARK SERVICE
DENVER SERVICE CENTER
OCTOBER 10, 2019
ROCR 185767 TOC-1
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
011100 Summary of Work 012601 Contract Modification Procedures 012700 Definition of Contract Line Items 013100 Project Management & Coordination 013216 Construction Schedule 013233 Photographic Documentation for Historic Preservation Projects 013323 Submittal Procedures
013513.22 Archeological Protection
013523 Safety Requirements 013591 Historic Preservation Treatment Procedures 014000 Quality Requirements 014200 Reference Standards 015000 Temporary Facilities and Controls 015639 Temporary Tree & Plant Protection
015719.12 Noise & Acoustics Management
015723 Under An Acre Pollution Prevention 016700 Product Requirements 017329 Cutting and Patching 017340 Execution 017419 Construction Waste Management and Disposal 017700 Closeout Procedures 017823 Operation and Maintenance Data 018113 Sustainable Design Requirements
DIVISION 02 – EXISTING CONDITIONS
021600 Excavation Support Systems 022400 Dewatering 024119 Selective Structure Demolition
DIVISION 03 – CONCRETE
030134 Concrete Patching 030500 Architectural Concrete Materials and Mixtures 032100 Reinforcing Steel 032150 Coating Existing Reinforcing Steel and Setting Steel in Epoxy 033000 Cast-in-Place Concrete 033310 Cast-in-Place Architectural Concrete - Horizontal 033320 Cast-in-Place Architectural Concrete - Vertical 037300 Patch Repair of Spalled Concrete
DIVISION 05 – METALS
050200 Structural Steel 057000 Decorative Metal
ROCR 185767 TOC-2
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
071416 Cold Fluid Applied Waterproofing - PMMA 071917 Silane Water Repellent 079200 Joint Sealants
DIVISION 09 – FINISHES
099600 High Performance Coatings
DIVISION 10 – SPECIALTIES
101416 Signage
DIVISION 26 – ELECTRICAL
260519 Low Voltage Electrical Power Conductors and Cables 260526 Grounding and Bonding for Electrical Systems 260529 Hangers and Supports for Electrical Systems 260533 Raceways and Boxes for Electrical Systems 260544 Sleeves and Sleeve Seals for Electrical Raceways and Cabling 260553 Identification for Electrical Systems
DIVISION 31 – EARTHWORK
311000 Site Clearing 312000 Earth Moving
DIVISION 32 – EXTERIOR IMPROVEMENTS
329100 Soils 329200 Turf and Grasses 329300 Plants 329451 Soil Cells Modular Units
DIVISION 33 – UTILITIES
331100 Water Distribution Systems 334100 Storm Utility Drainage Piping
ROCR - 185767 01 11 00 - 1
091015 SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Work under other contracts.
3. Contractor use of premises.
4. Public use of site.
5. Work Restrictions.
6. Soils Investigation Report.
7. Additional Reports.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: Meridian Hill Park, 16th and W Streets, Washington, DC.
B. The Work consists of the following:
1. The Work includes restoration of historic exposed aggregate concrete masonry paving, walls and elements; new plantings to re-establish the historic design of the Park; restoration of one drinking fountain; restoration of and new light fixtures; installation of regulatory and interpretive signage; stabilization of displaced pavement; drainage repair and replacement; temporary protection of historic features during construction.
C. Project will be constructed under a single prime contract.
1.3 WORK UNDER OTHER CONTRACTS
A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate the Work of this Contract with work performed under separate contracts.
B. Concurrent Work: Government will award separate contract(s) for the following construction operations at Project site. Those operations will be conducted simultaneously with work under this Contract.
1. Reconstruction of the Armillary Sphere: A separate contract will be awarded to for fabrication and installation of a reproduction of the original Armillary Sphere located in the circular exedra south of the Reflecting Pool..
ROCR - 185767 01 11 00 - 2
1.4 CONTRACTOR USE OF SITE
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to the immediate vicinity of areas where work is undertaken. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limits: Confine constructions operations to the immediate vicinity of the area of work. Do not disturb tree root zones or block sidewalks unless necessary.
2. The allowable area for contractor’s staging and limits of work are shown on drawing G2 Site and Staging Access Plan.
3. Contractor to coordinate equipment for pleaching frame delivery and installation, which may require size restrictions due to available space within the park.
4. There is no parking available on site. Contractor is responsible for locating and paying for all parking.
B. Storage of Materials: Confine storage of materials to approved staging areas within the Park boundary as approved by the Contracting Officer.
C. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with
Contracting Officer and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
D. Preservation of Historic Features: The concrete structures and plantings in Meridian Hill Park are all character-defining features of this National Historic Landmark and must be protected during all construction operations. Refer to Section 015000 and drawings for information concerning protection.
E. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
F. Construction Camp: Establishment of a camp within the park will not be permitted.
G. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for
ROCR - 185767 01 11 00 - 3
vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
1.5 PUBLIC USE OF SITE
A. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public.
Path and area closures will be permitted, when required, upon specific approval of Contracting Officer for both the area to be closed and schedule for closure.
1. The entire Lower Plaza, including the area between the Reflecting Pool and W Street may be closed to the public for the duration of construction.
1.6 OCCUPANCY REQUIRMENTS FOR BUILIDINGS
A. Existing Facilities
1. Partial Government Occupancy: Government and members of the public will occupy the premises during entire construction period, with the exception of areas under construction.
Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government’s operations. Maintain existing exits, unless otherwise indicated.
a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the Contracting Officer (CO).
2. Allow Government access for maintenance of fountains and other utilities and structures throughout the project.
1.7 CONDUCT OF OPERATIONS
A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer. Submit requests 72 hours in advance of the work to the Contracting Officer for approval.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
1.8 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 8:00 a.m. to 5:00 p.m., Monday through Friday, except when otherwise indicated.
ROCR - 185767 01 11 00 - 4
1. Weekend Hours: Weekend work is only permitted with a minimum of 72 hours advance notice to the Contracting Officer and specific approval of hours of work.
2. Early Morning Hours: Operation of power tools, equipment, compressors, diesel engine idling, and other noise-producing activities are not permitted prior to 8:00 am.
3. Hours for demolition and compressor or generator use: 8:00 am – 5:00 pm.
B. Existing Utilities
1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than two days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer’s written permission.
3. Hours for Utility Shutdowns: Do not shutdown utilities without written permission from the Contracting Officer. Maximum allowable shutdown to be no more than four hours.
D. Nonsmoking Building: Smoking is not permitted within the site, in any construction area, or within 25 feet of entrances, operable windows, or outdoor air intakes.
1. In addition to traditional cigarettes and cigars, this also incudes chewing tobacco, e-cigarettes, and vaping products.
1.9 SPECIAL CONSTRUCTION REQUIREMENTS
A. Project Website: A project website administered by the NPS will be used for purposes of managing communication and documents during the construction stage.
1. See Section 01 31 00 “Project Management and Coordination” for requirements on using the Project Website.
B. Meridian Hill Park is a National Historic Landmark noted for its unique exposed aggregate concrete features, including walks, stairs, walls, curbs, benches, balustrades, decorative urns and obelisks, fountains, and niches. It is also highly significant as a piece of historical American landscape design, and retains both its original design as well as a collection of historic plantings. All work in the Park must comply with the Secretary of the Interior’s Standards for Treatment of Historic Properties. Care must be taken at all times to prevent damage to any existing feature, including both plantings and structures.
C. Meridian Hill Park is used intermittently for large gatherings on a permit basis. A large celebration is held on Independence Day. Contractor shall cooperate with NPS to accommodate these gatherings by cleaning up site and providing secure fence protection at areas closed to the public. NPS will provide a minimum of one week advance notice of any scheduled activities.
ROCR - 185767 01 11 00 - 5
1.10 ADDITIONAL REPORTS
A. Available reports:
1. Meridian Hill Park – Replication and Repair of Decorative Concrete” prepared by architrave, p.c. architects, The Armbruster Company, and others.
2. “Aggregate Samples” dated March 28, 2010 prepared by The Armbruster Company. (This is a supplement to the above report.)
3. “Storm Sewer Cleaning and Condition Assessment Report, Topographical Survey” dated March 19, 2018 prepared by Langan.
4. “Geotechnical Engineering Report” dated December 1, 2017 by Langan.
B. A copy of these reports is available to all plan holders with this package.
C. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
ROCR - 185767 01 26 01 - 1
031414 CONTRACT MODIFICATION PROCEDURES
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. The work of this section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager, Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
ROCR - 185767 01 26 01 - 2
6. Scheduling
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: This is the hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums , such as:
1) Social Security
2) Medicare
3) Workers Compensation– Policy and company calculation to be made available.
4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.
5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.
ROCR - 185767 01 26 01 - 3
6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement.
Contractor may utilize the government provided Contractor Estimate Form, or their
ROCR - 185767 01 26 01 - 4
own form, provided that it contains the same information and level of detail as the Gov’t provided form.
3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.
Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.
5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.
Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. The labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by the NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for the work being performed.
2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.
3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region)
b. Construction Blue Book
ROCR - 185767 01 26 01 - 5
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals.
Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.
6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.
8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
Overhead………………10% Profit………………7.8%
2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
ROCR - 185767 01 26 01 - 6
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION 012601
ROCR - 185767 01 27 00 - 1
082714 DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins. See sketch following this Section.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item No. 1.: Lower Plaza Restoration
1. This item consists of:
a. Architectural concrete paving and repairs as indicated in the Drawings and Division 03 Concrete including pavement, curbs, borders, and elements. This item includes all submittals, mockups, removals, subgrade and preparation, cleaning, concrete work, and clean up.
b. Restoration of Reflecting Pool lighting.
c. Replacement of underground storm drainage and related connections and accessories where indicated. Extend all utility connections beyond the limits of the Lower Plaza as indicated.
d. Installation of new planting soil and modular soil cell units for new trees installed within paved areas.
e. Preparation and installation of soil and turf in panel at Buchanan Memorial plaza.
f. See Sheet L4 for other planting included in the Base Bid.
2. Measurement for payment will be percent complete of Work.
3. Payment will be made at the contract lump sum price.
B. Contract Line Item No. 2: Great Terrace Stairs and Walls
1. This item consists of:
a. Repairs to the Great Terrace Stairs, including new trench storm drains and new routing of drains to the south; concrete repairs to the interior spaces below the stairs;
repairs to existing architectural concrete on the stairs, walls, railings, and balusters.
ROCR - 185767 01 27 00 - 2
b. Restoration of concrete water fountain at the Lodge House, including verification of utility connections.
2. Measurement for payment will be percent complete of Work.
3. Payment will be made at the contract lump sum price.
B. Contract Line Item No. 3: Buchanan Memorial Stabilization
1. This item consists of repairs to the Buchanan Memorial, including but not limited to joint sealant repairs to the upward facing masonry joints.
2. Measurement for payment will be percent complete of Work..
3. Payment will be made at the contract lump sum price.
C. Contract Line Item No. 4: Barrier-free Walkways at the Lower Plaza
1. This item consists of:
a. New accessible, barrier-free walkway from 16th Street to the Buchanan Memorial.
This item includes cutting through the existing 16th street architectural concrete wall, forming a new opening, new sloped walkway compliant with ABAAS design measurements, grading, footings, retaining wall, storm drainage, architectural concrete paving, landscaping, and new lighting along walkway.
2. Measurement for payment will be percent complete of Work.
3. Payment will be made at the contract lump sum price.
D. Contract Line Item No. 5: Site Drainage Work West of the Lower Plaza
1. This item consists of:
a. All site drainage piping, structures, inlets, etc. for the area to the west/southwest of the Lower Plaza.
1) All Work west of manhole 14.
2) All Work between manhole 01 and inlets 76 and 78.
b. All concrete paving and repair work in this area, including repair or replacement of paving and other concrete elements damaged or disturbed by utility work.
2. Measurement for payment will be percent complete of Work.
3. Payment will be made at the contract lump sum price.
E. Contract Line Item No. 6: Site Utility Work East of the Lower Plaza
1. This item consists of:
a. All site drainage piping, structures, inlets, etc. for the area to the east/southeast of the Lower Plaza.
1) All Work between manhole 01 and manhole 21.
2) All Work between manhole 21 and drop inlets 90 and 91.
3) All Work between manhole 01 and trench drains 21 and 29 and drop inlet 80.
ROCR - 185767 01 27 00 - 3
b. All concrete paving and repair work in this area, including repair or replacement of paving and other concrete elements damaged or disturbed by utility work.
2. Measurement for payment will be percent complete of Work.
3. Payment will be made at the contract lump sum
F. Contract Line Item No. 7: Option 1 Lower Plaza Landscaping.
1. This item consists of all Lower Plaza landscaping within the paved areas with the exception of the replacement of (8) Columbia Planetrees at the Lower Plaza, the turf panel at the Buchanan Memorial, and landscaping noted in Option 2. See Sheet L4.
2. Measurement for payment will be percent complete of Work.
3. Payment will be made at the contract lump sum price.
G. Contract Line Item No. 8: Option 2 Lower Plaza West Landscaping
1. This item consists of restoration of west landscaping as indicated in the Drawings and specifications to the east of the 16th Street park entrance. See Sheet L4.
2. Measurement for payment will be percent complete of Work.
3. Payment will be made at the contract lump sum price.
H. Contract Line Item No. 9: Option 3 Linden Allee.
1. This item consists of replacement of landscaping at the Linden Allee as indicated and as required to restore the site after construction; and installation of new pleaching frames and footings.
2. Measurement for payment will be percent complete of Work.
3. Payment will be made at the contract lump sum price.
I. Contract Line Item No. 10: Alternate 1 Replication of Lower Plaza Paving
1. This item consists of replicating sections of exposed aggregate concrete removed in lieu of salvaging, conserving, and reinstalling. This is a deduct alternate.
a. In sheets A3 – A8, all areas indicated for removal and salvage of concrete panels for reinstallation, Note R1, shall instead be designated with note R5, for salvage of panels as models for replication only for Alternate 1.
b. The base bid includes Note R1 treatment as indicated in Sheets A3 – A8.
c. In sheets A9 – A14, for Alternate 1, areas indicated as reset pavement shall be replicated pavement. Areas designated with note A1 shall instead be note A3. Areas of note A2 regarding surface repair of reset panels shall be disregarded.
d. Replication of concrete panels and pebble dash shall be according to Division 3 specifications.
2. Measurement for payment will be percent complete of Work.
3. Payment will be made at the contract lump sum price.
4. Alternate 1 shall include a credit for salvage, conservation, and reinstallation of panels.
END OF SECTION 01 27 00
ROCR - 185767 01 31 00 - 1
091015 PROJECT MANAGEMENT AND COORDINATION
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Construction Coordination.
2. Submittals
3. Coordination Drawings.
4. Requests for Information (RFIs).
5. NPS/DSC SharePoint Project Website.
6. Project meetings.
7. Environmental Coordination.
8. Permits
B. Related Requirements:
1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.
1.2 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
ROCR - 185767 01 31 00 - 2
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Permit requirements.
7. Pre-installation conferences.
8. Project closeout activities.
1.3 SUBMITTALS
A. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.
1. Letter designating Project Superintendent.
2. Construction Schedule.
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention Plan.
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.
7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the
Contactor and all subcontractors.
8. Waste Management Plan.
9. Quality Control Plan.
10. Temporary Storm Water Pollution Prevention Plan (SWPP or UPPP).
11. Historic Preservation Treatment Plan
12. Contractors Commissioning Plan.
13. Site Logistics Plan.
14. Environmental Coordination Measures for tree and vegetation removal.
15. List of Required Construction Permits. Include the following information for each permit:
a. Name of Permit.
b. The Agency(ies) with Jurisdiction issuing the permit.
c. Information required from the Government to complete the permit application.
B. All items listed must be provided to the Contracting Officer before the Pre-Construction Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.
ROCR - 185767 01 31 00 - 3
1.4 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI utilizing the form created on the NPS/DSC SharePoint Project website.
1. CO will not respond to RFIs submitted by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially.
2. Date.
3. RFI subject.
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution. If Contractor's suggested resolution impacts the
Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
8. Contractor's signature.
9. Requested date for response.
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Form: Complete the RFI Form on the NPS/DSC SharePoint website as follows:
1. Enter the general information at the top of the form.
2. Under the “Action” section at the bottom of the form, select “Question” then select “CMR” in the drop-down of the “Send to” box.
3. Enter the details of the question and attach related documents.
4. Select “Submit Form” at the bottom of the page.
D. Contracting Officer’s Action: CO will review each RFI, determine action required, and respond.
CO will determine the critical nature of each RFI and issue a response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in the Contract Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
ROCR - 185767 01 31 00 - 4
2. CO's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.
3. CO's action on RFIs may result in the need for a change to the Contract Time or the Contract Sum. All contract changes will be processed following the terms and conditions of the contract.
1.5 PROJECT WEB SITE
A. Use the NPS/DSC SharePoint Project website for communication throughout the contract period.
The NPS/DSC SharePoint Project website will be used for the following functions:
1. Project directory.
2. Project correspondence.
3. Meeting agendas and minutes.
4. Contract modifications forms and logs.
5. RFI form and processing.
6. Task and issue management.
7. Photo documentation.
8. Baseline schedule, schedule updates and calendar management.
9. Submittal form and processing.
10. Payment coordination documentation.
11. Drawing and specification document hosting, viewing, and updating.
12. Online document collaboration.
13. Reminder and tracking functions.
14. Archiving functions.
15. Notification of submittal and RFI statuses and current responsible party.
16. Permits and addendums
B. Some documents however are not suitable to be shared using the NPS/DSC SharePoint Project website. Documents containing Personal Identifying Information (PII) (i.e. certified payrolls) shall not be shared using the NPS/DSC SharePoint Project website and shall be coordinated with the SharePoint Project team as appropriate.
C. Submit to the CO a list of all employees who will need access to the website. The users will receive an invitation to register from the Department of Interior (DOI). Once the user is registered on the DOI website, they will be given access to the NPS/DSC SharePoint Project website. For login procedures and other SharePoint information, refer to the Workflows website at http://www.nps.gov/dscw/precon_spproj.htm.
D. All users will be required to have the following software packages:
1. Internet Explorer version 7 or later.
2. Adobe Acrobat Professional (Pro) version 9 or later
1.6 PROJECT MEETINGS
A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. The meeting agenda will include the following as a minimum:
ROCR - 185767 01 31 00 - 5
1. Roles & Responsibilities/ Lines of Authority.
2. Park rules and regulations.
3. Jobsite Safety.
4. Resolution of comments on required Division 01 documents.
5. Coordination of Subcontractors.
6. Labor law application.
7. Modifications.
8. Schedule of Values.
9. Payments to Contractor.
10. Payroll reports.
11. Contract time.
12. Liquidated damages.
13. Contractor Performance Evaluation.
14. Display of Hotline posters.
15. Notice to proceed.
16. Correspondence procedures.
17. NPS/DSC SharePoint Project website.
18. Acceptance/rejection of work.
19. Progress meetings.
20. Submittal procedures.
21. NPS Final Accessibility Inspection.
22. Environmental requirements, including coordination for tree and vegetation removal.
23. Permit requirements.
24. As-constructed drawings/operation and maintenance (O&M) manuals.
25. Saturday, Sunday, holiday and night work.
26. Reference materials.
27. Value engineering.
B. Progress Meetings: The Contracting Officer will schedule weekly meetings with the Contractor.
1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. The meeting agenda will include the following:
a. Approval of minutes of previous meetings.
b. Submittal status.
c. Review of off-site fabrication and delivery schedules.
d. Requests for information (RFI) and other issues.
e. Modifications.
f. Work in progress and projected.
g. Construction Schedule update (provide updated CPM).
h. Status of Project Record Drawings and O&M manuals.
i. Other business relating to work.
j. Permit requirements.
ROCR - 185767 01 31 00 - 6
1.7 ENVIRONMENTAL COORDINATION
A. Contractor’s Environmental Manager: Designate an on-site party responsible for overseeing the Contractor’s conformance to environmental goals for the project and implementing procedures for environmental protection.
1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to those of this project; must be familiar with environmental regulations applicable to construction operations.
2. Responsibilities: Responsibilities shall include:
a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.
b. Implementation of the Waste Management Plan(WMP).
c. Implementation of the Indoor Air Quality (IAQ) Management Plan.
d. Implementation of the Storm Water Pollution Prevention Plan(SWPPP).
e. Present an overview of environmental issues and summarize site specific procedures relating to management plans at the Preconstruction conference.
f. Training for Contractor personnel in accordance with their position requirements.
g. Monitoring and documentation of environmental procedures.
B. Perform project quality control in accordance with requirements specified in Related Sections, including:
1. Quality Requirements.
2. Regulatory Requirements.
3. Noise & Acoustics Management.
4. Temporary Storm Water Pollution Prevention Environmental Management.
5. Construction Waste Management.
C. Contractor’s Environmental Training Program: Contractor shall provide environmental training for workers performing work on the project site. Training shall include the following:
1. Overview of environmental issues related to the building industry.
2. Overview of environmental issues related to the Project.
3. Review of site specific procedures and management plans:
a. Construction Waste Management.
b. Noise & Acoustics Management.
c. Temporary Storm Water Pollution Prevention.
D. Environmental Coordination : Coordinate with Contracting Officer and Park Resource Protection Specialist for the following :
1. Contracting Officer and Park Resource Protection Specialist shall use conservation measures to minimize effects to Migratory Birds, Birds of Conservation Concern.
a. Contracting Officer nad Park Resource Protection Specialist shall schedule all tree and vegetation removal and grading outside of the peak bird breeding season to the maximum extent practicable.
b. When project activities cannot occur outside the bird nesting season, Contracting Officer and Park Resource Protection Specialist shall conduct surveys prior to
ROCR - 185767 01 31 00 - 7
scheduled activity to determine if active nests are present within the area of disturbance.
c. Coordinate with Contracting Officer and Park for Resource Protection Specialist for seasonal restrictions.
E. Provide documentation for environmental procedures as specified herein and in accordance with approved Waste Management Plan and Storm Water Pollution Prevention Plan.
1.8 PERMITS
A. General:
1. Permits and Responsibilities: The Contractor shall, without additional expense to the
Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that occur as a result of the Contractor’s fault or negligence. The Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the work.
2. For the purpose of this contract the Contractor will not be considered an agent of the Government. Therefore the Contractor will comply with the appropriate Federal, State and local laws.
B. Coordination with Agency(ies) with Jurisdiction Issuing Permits
1. Coordination: Contact the Agency(ies) with Jurisdiction as needed and sufficiently in advance to avoid delaying the work: Coordinate meetings, reporting requirements, inspections, or any other requirements.
C. Administrative Procedures:
1. Coordinate scheduling and timing of required administrative provisions of project permits with Agency(ies) with Jurisdiction, Construction Manager, and Park to avoid conflicts and to ensure orderly execution of the Work.
2. Supply all needed information to Agency(ies) with Jurisdiction issuing permits, pay any fees required and provide all material needed to comply with the permit’s conditions and provisions.
3. Upload permits to the NPS/DSC SharePoint project website when the permits are obtained.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 31 00
ROCR - 185767 01 32 16 - 1
031414 CONSTRUCTION SCHEDULE
SECTION 01 32 16 – CONSTRUCTION SCHEDULE
PART 1 - GENERAL
1.1 SUMMARY
A. This Section consists of Construction Schedule requirements including but not limited to the following:
1. Schedule of Values
2. Construction Schedule Requirements.
3. Construction Schedule Updates.
4. Time Impact Analysis.
B. Purpose: The purpose of the Construction Schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. The Construction Schedule will assist the Contractor and Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the Contractor's monthly progress payment.
1.2 DEFINITIONS
A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.
1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
B. Cost Loading: The allocation of the Schedule of Values for the completion of an activity as scheduled. The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.
C. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on…