5-B08_WICR-_Pre_Bid_Question_Answers_9.3.19.xlsx
XLSX spreadsheet 20 KB Posted
- Attached to
- Visitor Center and Library Remodel Federal contract opportunity
- Solicitation number
- 140P2019R0072
About this file
Questions and Answers Spreadsheet
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 3-B08_WICR_Security_Camera_SOW.pdf | ||
| 2-B08_Bid_Option_1_Vol_II_PriceSched_(1).xlsx | XLSX spreadsheet | |
| 1-B08_SF30_Amendment_3.pdf | ||
| 4-B08_Security_Camera_Floor_Plan.pdf | ||
| E09_PPT_Pre-Proposal_(1).ppt | PPT presentation | |
| B08_SF30_Amendment_2.pdf | ||
| Pre-Bid_Sign_In_Sheet.pdf | ||
| Amendment_1_-_8-16-2019.pdf | ||
| 8-B03_Wage_Determinations_8-8-2019.pdf | ||
| 5-B08_Solit_PSP_Vol_II_PriceSched_(1).xlsx | XLSX spreadsheet | |
| 2-B08_PSP_VOL_2.pdf | ||
| 7-A06_WICR_Final_ConstDocuments_DrawingsPt1_05-06-19.pdf | ||
| 6-A06_Visitor_Center_and_Library_Remodel_-_CD_Specifications.pdf | ||
| 3-SF1442_Fillable.pdf | ||
| 4-B08_Solit_PSP_Vol_II_SBSubKCalc.xlsx | XLSX spreadsheet | |
| 9-B08_SF1442_and_Clauses.pdf | ||
| 1-B08_PSP_VOL_1.pdf | ||
| 7-A06_WICR_Final_ConstDocuments_DrawingsPt2_05-06-19.pdf |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Question and Answer Spreadsheet | 140P2019R0052 / WICR-251506 | |||
| Question No. | Sheet or Reference | Question | Response | Amendment Answered |
| 1 | Pre-Bid Tour Question | Exterior Demo Wall Thickness | Refer to glass wall sections on A12. Existing walls are shown nominal. NPS may provide PDF record drawings to bidding contractors at their discretion. Existing walls are basically three types: 1) 12" thick cast concrete with interior furred drywall 2) Hollow metal glazed storefront 3) Wood framed with drywall, batt insulation, and wood siding. | |
| 2 | Pre-Bid Tour Question | Ceiling in the Visitor Center gift shop come out except the Theater | See Keynote 5 on A3. Remove ceiling. | |
| 3 | Pre-Bid Tour Question | Do Exhibit area graphics to remain? | Protect existing conditions to remain from damage and soiling. | |
| 4 | Date Sent: 08/23/19 | On the plan set fort the Wilson's Cree National Battefield Project there are a couple of issues with the Mechanical Plans. The mechanical plans scale do not match corresponding sizes on the plan sets (for example the scale on M7 and the size of the duchwork do not correspond.) Also, the plumbing fixture schedule appears to have some type of text issue. | Sizes of HVAC ductwork shown are called out on the plans. Use size callouts versus scaling off plans. Plumbing schedules submitted in pdf form have no display issues. Perhaps printing issue is with the bidding contractor configurations. | |
| 5 | Date Sent: 08/26/19 | Based on the document provided: Drawing #A4 Floor Plan Area A and Section 105626-Motorized Mobile Storage Shelving Specification. |
1)Does this represent all of the current documentation available? If so, we require the following addl info.
2) You have indicated a maximum length of 144" and height of 84". What are the depth of these units?
3) You have indicated various shelving and cabinet types including; four post shelving, framed art storuage, museum cabinets, and weapons cabinets. What are the configurations of these various types, styles, sizes and quatities that are being placed on this mobile system?
4) The drawing shows 8 units please confirm. Are these all mobile or are the outside units static?
5) What is the overall length of the rails as shown on the drawing?
1) Yes.
2) 36"
3) Follow layout shown and submit for review and approval.
4) All are mobile.
5) 34'-6" 6 Date sent: 08/27/19 Per AHU 1&2 Schedule on M-13 calls them to have LP gas for heating. Don't see it addressed anywhere in the drawing as to where the gas is fed from or to them.
Where does H-@ get its feed water from? The detail to hook up the humidifiers with bckflows but, do not see where it is coming from. LP Gas is fed from existing LP tank farm located northwest of the Visitor's Center and Library buildings. A service line exists between the tank farm and each building. Existing regulators at each building shall be replaced with new regulators sized for 672 MBH input at outlet pressure of 11 IN.WC. Field route an 1-1/4" schedule 40 black steel service from outlet of pressure regulator to AHU.
Connect and extend a 3/4" copper water line from nearest domestic water branch in MECH 113 to serve H-2 shown on sheet M9. The 3/4" water line serving H-1 in MECH 132 is shown and called out on sheet M10.
| 7 | 076200 Flashing and Sheet Metal: Specification section calls for pre-manufactured coping and fascia. If shop is SPRI ES-1 certified, can shop-fabricated material be substituted? | Yes. |
| 8 | 075423 ACM System: Specification section calls for Knight Wall panel supports. Supports are not shown on plans or required for installation. Can these supports be excluded from the project? | Spec lists several available manufacturers and does not favor only one. Ultimately installation per the Execution section is "in accordance with manufacturer's instructions". Submittals shall define all final attachments based on the manufacturer. |
| 9 | 075425 Fully Adhered TPO Roofing: Specification section calls for ½” cover board and substrate board while plans only show cover board. Is a substrate board required? | Cover board and roof sheathing are noted on section details sheets A17 & A18. |
| 10 | 075425 Fully Adhered TPO Roofing: Specification section calls for a vapor barrier. The substrate board the vapor barrier is to be adhered to is not shown on plans. Can the vapor barrier be excluded from the project? | Vapor barrier is mandatory. Cover board and roof sheathing are noted on section details sheets A17 & A18. |
| 11 | 075425 Fully Adhered TPO Roofing: Specification section calls for min R-30 iso. Plans show min R-25 4” iso. Which is wanted? | R-25 min is correct. |
| 12 | Per AHU 1&2 Schedule on M-13 it calls them to have LP gas for Heating I don’t see it addressed anywhere in the Drawing as to where the gas is fed from or to them. | Dupe. See RFI #6 |
| 13 | Where does H-2 get its Feed water from? |
I see the detail to hook up the Humidifiers with backflows but I don’t
| see where its coming from | Dupe. See RFI #6 | ||
| 14 | Date sent: 08/30/19 | 1) Please confirm that Ozark Electrical Cooperative will remove existing "Pas Mt. "XFMR" and replace it with new "XFMR"? See page E3 key Note 3. |
| Tranformer will be removed by Ozark Electric. | ||
| 15 | 2) Please confirm that Ozark Electrical will connect primary line to "XFMR"? See Page E3 Key Note 3. | Primary feeders will be connected to transformer by Ozark Electric. |
| 16 | 3) Will the Ozard Electrical work be included in this contract or will the National Park Service provide that scope of work? See Page E3 Key Note 3. | Ozark Electric work shall be included in this contract. |
| 17 | 4) Please provide the required configurations for the Mobile Shelving. See Page A4 Key Note 2. | Please follow layout for bidding. |
| 18 | 5) Can you confirm that this is not a LEED Project? | Not a LEED Project. |
| 19 | 6) Can you confirm the standard wall assembly detail and wall thickness at exterior locations? | Refer to glass wall sections on A12. Existing walls are shown nominal. NPS may provide PDF record drawings to bidding contractors at their discretion. Existing walls are basically three types: 1) 12" thick cast concrete with interior furred drywall 2) Hollow metal glazed storefront 3) Wood framed with drywall, batt insulation, and wood siding. |
| 20 | 7) Are there any cables in the exterior concrete wall that we must be aware of for saw cutting the new door opening? | We are not aware of cable. |
| 21 | 8) On M14 the plumbing schedule text is not populating correctly. Can you reissue the PDF document? | Table appears okay to DOR. Perhaps issue with bidding contractor's printer configurations. |
| 22 | 9) On S12 the Beam Connection schedule text is not populating correctly. Can you reissue the PDF document? | Text on Beam Connection Schedule appears correct to DOR. Perhaps this is a issue with bidding contractor printer configuration. |
| 23 | 10) On S3 Earthwork Note 1, it states a Geotechnical Engineer is required to field test and verify existing subgrade to be 2000 PSF. Can you provide a spec of the requirements for the testing? | 31 23 00 - Earthwork, paragraph 3.4.E. |
| 24 | 11) If soil properties do not meet the 2000 PSF bearing capacity and additional work is required to improve its properties, will this work be a change order? Reference S3 Earthwork Note 1. | No. See Section 31 23 00 - Earthwork, paragraph 1.3.G Unauthorized excavation or remedial work will be the contractors expense. |
| 25 | 12) Can you confirm that the temporary bathrooms for public use will be provided by the National Park Service and not the Prime Contractor? | The contract does not require the contractor to provide temporary bathrooms for public use. However, the bathroom in the Library (Area A) is mechanically intact with exception of flooring in hall. |
Contractor to submit schedule per 01 32 16, paragraph 2.2.B.8.a that includes limitations and uninterruptible services. See also paragraph 1.4.A.3 for Preconstruction Conference to review constraints, work stages, partial or limited government occupancy.
| 26 | 13. Please confirm the number of hard coies and digital/USB drives required for submission of both volumes. | 1 flash drive is required no hard copies. If you can't get both volumes on 1 flash drive then submit 2. |
| 27 | 14. Can CCASS/CPARS performance evaluations be submitted in lieu of the Past Performance Questionnaire required for Volume 1, Technical Proposal, Factor 4 Past Performance? | No, use the PPQ in the solicitation package. |
Longshore, Jason James: Longshore, Jason James:
WICR PRE-BID REQUESTS FOR INFORMATION