2-YOSE_158675B_Div_1_01_27_00_Def_of_CLINs_2-14-18.pdf
PDF 93 KB Posted
- Attached to
- Rehabilitate El Portal Sanitary Sewer Phase II
- Solicitation number
- 140P2018R0013
About this file
Revised Spec Section
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_No._2.pdf | ||
| YOSE_158675B_Q_and_A's_as_of_2.22.18,Amend_2.xlsx | XLSX spreadsheet | |
| 3-ContractPriceSchedule11.02.17.xlsx | XLSX spreadsheet | |
| SF_30,_Amendment__1.pdf | ||
| 7-Pre-proposal_meeting_attendees_2.06.18.pdf | ||
| 6-YOSE_158675B_Pre-proposal_Mtg_Notes_02.06.18.pdf | ||
| 4-SB_SubKting_Plan_Calcs.xlsx | XLSX spreadsheet | |
| 1-Clarification_Section_F.pdf | ||
| 8-YOSE_158675B_Q_and_A's_as_of_2.14.18,Amend_1.pdf | ||
| 5-YOSE_158675B-II,_Pre-Proposal_Slides.pdf | ||
| 3PSP_VOL_II.pdf | ||
| 4B08_Wage_Determination_01-05-2018.pdf | ||
| 7Drawings.pdf | ||
| 6YOSE_158675B_VOL_2-49_Specs.pdf | ||
| 1RFP.pdf | ||
| 5YOSE_158675B_VOL_1_Specs.pdf | ||
| 2PSP_VOL_I.pdf |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
YOSE – 158675B Revised 2/14/2018 01 27 00 - 1
DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00
PART 1 – GENERAL
1.1 SUMMARY
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
All construction shall result in complete, fully functional, properly operating systems/facilities meeting applicable codes, NPS Denver Service Center (DSC) standards, and industry standards-at no additional cost. All usual appurtenances and incidental/associated work shall be included-at no additional cost.
PART 2 – PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
Contract Line Item No. 1: Old El Portal Sewer and Erosion Control Improvements – Elements A-J
A. Element A: Sanitary Sewer Service Laterals Open Cut (Old El Portal).
1. This element consists of furnishing all materials, equipment and labor for construction of the removal and replacement of existing sewer service laterals between sewer main and building through open cut, (upon NPS approval may also utilize pipe burst and/or horizontal directional drill methods); includes manhole and mainline tie-in connections, installation of double wye cleanouts, restoration of natural vegetation, homeowner’s landscaping and hardscape, walls, AC, concrete and gravel surface;
traffic control, debris removal and disposal.
2. Sewer lateral piping are piping that serve one or two residences only as shown on the Drawings.
3. Also included is temporary gravity pipe flow, vacuum collection, or bypass pumping to provide uninterrupted sewer service for sewer laterals.
4. No separate measurement will be made.
5. Payment will be made at the contract lump sum price.
YOSE – 158675B Revised 2/14/2018 01 27 00 - 2
B. Element B: Sanitary Sewer Mains CIPP (Old El Portal).
1. This element consists of furnishing all materials, equipment and labor for rehabilitation and construction of cured in place pipe (CIPP) inside existing sewer pipe main lines, manhole and service lateral tie-in connections; includes all-natural vegetation, AC, concrete and gravel surface restoration, traffic control, debris removal and disposal.
2. This element also includes CCTV inspection of pipe segments prior to construction to accurately locate existing service laterals that will need to be reconnected and to determine level of pipe preparation required, e.g. root cutting, jetting, etc., prior to receiving improvements.
3. No separate measurement will be made.
4. Payment will be made at the contract lump sum price.
C. Element C: Sanitary Sewer Mains Pipe Burst (Old El Portal).
of the rehabilitation and replacement of existing sewer pipe through pipe burst methods; manhole and service lateral tie-in connections; AC, concrete and gravel surface removal; includes all-natural vegetation, AC, concrete and gravel surface restoration, traffic control, debris removal and disposal.
2. This element also includes CCTV inspection of pipe segments prior to construction to accurately locate existing service laterals that will need to be reconnected prior to receiving improvements.
4. Payment will be made at the contract lump sum price above.
D. Element D: Sanitary Sewer Mains Pipe Horizontal Directional Drill (Old El Portal).
of the new sewer pipe alignment between existing manholes through horizontal directional drilling methods; manhole tie-in connections; AC, concrete and gravel surface removal; includes all-natural vegetation, AC, concrete and gravel surface restoration, traffic control, debris removal and disposal.
2. This element also includes CCTV inspection of pipe segments prior to construction to accurately locate existing service laterals that will need to be reconnected prior to receiving improvements.
E. Element E: Sanitary Sewer Mains Open Cut (Old El Portal).
of the removal and replacement of existing sewer pipe, service lateral tie-in connections, and manholes; AC, concrete and gravel surface removal; includes all-natural vegetation, AC, concrete and gravel surface restoration, traffic control, debris removal and disposal.
2. Sewer mains are piping located between manholes as shown on the Drawings and convey flow from more than one residence.
YOSE – 158675B Revised 2/14/2018 01 27 00 - 3
YOSE – 158675B Revised 2/14/2018 01 27 00 - 4
F. Element F: Manhole Repair Rehabilitate & Epoxy Line (Old El Portal).
of manhole repair, rehabilitation and field applied epoxy lining; includes cleaning, manhole surface profiling (void patching), bench and channel repair, and other manhole component restoration from manhole channel up to and including manhole rim; pipe to manhole tie-in connections; AC, concrete and gravel surface removal; includes all natural vegetation, AC, concrete and gravel surface restoration, traffic control, debris removal and disposal.
2. No separate measurement will be made.
3. Payment will be made at the contract lump sum price above.
G. Element G: New Manhole Construction (Old El Portal).
of new precast manholes with an epoxy coating; includes removal of existing manhole for installation of new manhole as shown on drawings and excavation and installation of new manholes along new sewer alignments; AC, concrete and gravel surface removal; includes all, natural vegetation, AC, concrete and gravel surface restoration, traffic control, debris removal and disposal.
H. Element H: Sewer Bypass Operations (Old El Portal).
1. This element consists of furnishing all materials, equipment and labor for sewer bypass operations (or other accepted method to provide uninterrupted sewer service) during construction and rehabilitation of new and existing sewer main piping; includes plan and permit review approval; includes all-natural vegetation, AC, concrete and gravel surface restoration as needed, traffic control, debris removal and disposal.
I. Element I: CCTV Piping and Manhole Inspection (Old El Portal).
1. This element consists of furnishing all materials, equipment, traffic control plan and labor for sewer pipeline and manhole cleaning followed with closed circuit television inspection and analysis; involves pipe cleaning as needed to clear piping of roots, debris and buildup associated with sewer piping to adequately inspect pipe;
includes traffic control, debris removal and disposal.
J. Element J: Erosion Mitigation (Old El Portal).
rehabilitation of grading and drainage for the construction of rolled curb and gutter including driveway tie-in improvements; includes all-natural vegetation, AC, concrete and gravel surface restoration, traffic control, debris removal and disposal.
YOSE – 158675B Revised 2/14/2018 01 27 00 - 5
3. Payment will be made at the contract lump sum price.
Contract Line Item No. 2: Trailer Court Sewer Improvements – Elements K-P
K. Element K: Sanitary Sewer Mains CIPP (Trailer Court).
sewer pipe main lines, manhole and service lateral tie-in connections; includes all-natural vegetation, AC, concrete and gravel surface restoration, traffic control, debris removal and disposal.
2. This element also includes CCTV inspection of pipe segments prior to construction to accurately locate existing service laterals that will need to be reconnected and to determine level of pipe preparation required, e.g. root cutting, jetting, etc., prior to receiving improvements.
L. Element L: Sanitary Sewer Mains and Laterals Open Cut (Trailer Court).
connections, and manholes; AC, concrete and gravel surface removal; includes all, natural vegetation, AC, concrete and gravel surface restoration, traffic control, debris removal and disposal.
2. Sewer mains are piping located between manholes as shown on the Drawings and convey flow from more than one residence.
3. Sewer lateral piping are piping that serve one or two residences only as shown on the Drawings.
4. Temporary gravity pipe flow, vacuum collection, or bypass pumping to provide uninterrupted sewer service for sewer mains and service laterals is covered under Element O.
5. No separate measurement will be made.
6. Payment will be made at the contract lump sum price above.
M. Element M: Manhole Repair Rehabilitate & Epoxy Line (Trailer Court).
of manhole repair, rehabilitation and field applied epoxy lining; includes cleaning, manhole surface profiling (void patching), bench and channel repair, and other manhole component restoration from manhole channel up to and including manhole rim; pipe to manhole tie-in connections; AC, concrete and gravel surface removal; includes all natural vegetation, AC, concrete and gravel surface restoration, traffic control, debris removal and disposal.
YOSE – 158675B Revised 2/14/2018 01 27 00 - 6
N. Element N: New Manhole Construction (Trailer Court).
of new precast manholes with an epoxy coating; includes removal of existing manhole for installation of new manhole as shown on drawings and excavation and installation of new manholes along new sewer alignments;
AC, concrete and gravel surface removal; includes all, natural vegetation, AC, concrete and gravel surface restoration, traffic control, debris removal and disposal.
O. Element O: Sewer Bypass Operations (Trailer Court).
service) during construction and rehabilitation of new and existing sewer main and service lateral piping; includes plan and permit review approval;
includes all natural vegetation, AC, concrete and gravel surface restoration as needed, traffic control, debris removal and disposal.
P. Element P: CCTV Piping and Manhole Inspection (Trailer Court).
television inspection and analysis; involves pipe cleaning as needed to clear piping of roots, debris and buildup associated with sewer piping to adequately inspect pipe;
includes traffic control, debris removal and disposal.
Contract Line Item No. 3: Rancheria Flat Sewer Improvements – Elements Q-X
Q. Element Q: Sanitary Sewer Service Laterals Open Cut (Rancheria Flat).
of the removal and replacement of existing sewer service laterals between sewer main and building through open cut, (upon NPS approval may also utilize pipe burst and/or horizontal directional drill methods); includes manhole and mainline tie-in connections, installation of double wye cleanouts, restoration of natural vegetation, homeowner’s landscaping and hardscape, walls, AC, concrete and gravel surface;
traffic control, debris removal and disposal.
2. Sewer lateral piping are piping that serve one or two residences only as shown on the Drawings.
3. Also included is temporary gravity pipe flow, vacuum collection, or bypass pumping to provide uninterrupted sewer service for sewer laterals.
4. No separate measurement will be made.
5. Payment will be made at the contract lump sum price.
YOSE – 158675B Revised 2/14/2018 01 27 00 - 7
R. Element R: Sanitary Sewer Mains CIPP (Rancheria Flat).
sewer pipe main lines, manhole and service lateral tie-in connections; includes all-natural vegetation, AC, concrete and gravel surface restoration, traffic control, debris removal and disposal.
2. This element also includes CCTV inspection of pipe segments prior to construction to accurately locate existing service laterals that will need to be reconnected and to determine level of pipe preparation required, e.g. root cutting, jetting, etc., prior to receiving improvements.
S. Element S: Sanitary Sewer Mains Pipe Burst (Rancheria Flat).
of the rehabilitation and replacement of existing sewer pipe through pipe burst methods; manhole and service lateral tie-in connections; AC, concrete and gravel surface removal; includes all-natural vegetation, AC, concrete and gravel surface restoration, traffic control, debris removal and disposal.
2. This element also includes CCTV inspection of pipe segments prior to construction to accurately locate existing service laterals that will need to be reconnected prior to receiving improvements
4. Payment will be made at the contract lump sum price above
T. Element T: Sanitary Sewer Mains Open Cut (Rancheria Flat).
connections, and manholes; new sewer pipe with new alignments; new manholes;
sewer pipe tie-in to fifteen inch (15”) sewer trunk main; abandonment of sewer pipe (slurry filled) and manholes (sand filled); AC, concrete and gravel surface removal;
includes all natural vegetation, AC, concrete and gravel surface restoration, traffic control, debris removal and disposal.
2. Sewer mains are piping located between manholes as shown on the Drawings and convey flow from more than one residence.
U. Element U: Manhole Repair Rehabilitate & Epoxy Line (Rancheria Flat).
of manhole repair, rehabilitation and field applied epoxy lining; includes cleaning, manhole surface profiling (void patching), bench and channel repair, and other manhole component restoration from manhole channel up to and including manhole rim; pipe to manhole tie-in connections; AC, concrete and gravel surface removal; includes all natural vegetation, AC, concrete and gravel surface restoration, traffic control, debris removal and disposal.
YOSE – 158675B Revised 2/14/2018 01 27 00 - 8
V. Element V: New Manhole Construction (Rancheria Flat).
of new precast manholes with an epoxy coating; includes removal of existing manhole for installation of new manhole as shown on drawings and excavation and installation of new manholes along new sewer alignments; AC, concrete and gravel surface removal; includes all, natural vegetation, AC, concrete and gravel surface restoration, traffic control, debris removal and disposal. No separate measurement will be made.
2. Payment will be made at the contract lump sum price above.
W. Element W: Sewer Bypass Operations (Rancheria Flat).
service) during construction and rehabilitation of new and existing sewer main piping; includes plan and permit review approval; includes all-natural vegetation, AC, concrete and gravel surface restoration as needed, traffic control, debris removal and disposal.
X. Element X: CCTV Piping and Manhole Inspection (Rancheria Flat).
television inspection and analysis; involves pipe cleaning as needed to clear piping of roots, debris and buildup associated with sewer piping to adequately inspect pipe;
also includes portion of fifteen inch (15”) sewer trunk main downstream of new sewer manhole tie-ins to ensure construction debris has not entered trunk main piping; includes traffic control, debris removal and disposal.
Contract Line Item No. 4: Rock Excavation (El Portal, Trailer Court, Rancheria Flat, and the Wastewater Treatment Plant Entrance Sewer)
1. This item consists of furnishing all materials, equipment, and labor for excavation of rock for footings, trenches, manholes, and lift station facilities. The work includes, but is not limited to, excavation of large rock pieces or solid rock along the utility trench corridor. Rock excavation is defined in Spec Section 31 23 16.13. Payment will only be made for rock meeting this definition.
2. Payment will be made at the contract price per each cubic yard.
YOSE – 158675B Revised 2/14/2018 01 27 00 - 9
Contract Line Item No. 5: Bid Option A – Waste Water Treatment Plant Entrance Sewer Improvements
1. This item consists of furnishing all materials, equipment and labor for construction of the removal, replacement and re-connection of the fifteen inch (15”) sewer trunk main into the waste water treatment plant headworks to include construction of three new manholes necessary for sewer pipe realignment that include installation of sewer flow paced measurement and effluent sampling equipment. Also includes installation of level sensor in night soil stack vault. Installation involves AC saw cut, open cut trench work and associated excavation, twelve (12) inch waterline realignment, four (4) inch sewer force main realignment, electrical, telemetry (communication and data hard wire to WWTP control room), AC surface removal and restoration, and traffic control.
3. Payment will be made at the contract price per lump sum price.
Contract Line Item No. 6: Bid Option B1 – 5638 Foresta Road Lift Station and Overflow Storage (Old El Portal).
the removal of one lift station and installation of one wet-well lift station serving the single family residence located at 5638 Forest Road; with minimum eight hundred forty eight (848) gallon total storage capacity comprised of 212 gallons daily flow and six hundred thirty six (636) gallon emergency overflow storage capacity in a single wet well and new force main to existing manhole EP6; manhole EP6 to be modified: AC, and gravel surface removal. Installation involves AC saw cut, open cut trench work and associated excavation, electrical, telemetry (Alarm hard wire dial out to WWTP), AC, gravel and natural ground surface restoration, debris removal and disposal.
Contract Line Item No. 7: Bid Option B2 – Electrical Service for 5638 Foresta Road Lift Station by Utility Company (Old El Portal).
1. This item consists of all design, materials, equipment and labor provided by the Power
Utility, Pacific Gas and Electric, (PG&E) for installation of new electrical service for the 5638 Foresta Road lift station. The work includes all design, connection, and administrative fees by PG&E, payment of the power utility's order/connection fees, and the installation of any necessary components, i.e., transformer, meter, conduit and conductor. Work performed by the NPS Contractor for completion of this item including, but not limited to coordination with the Power Utility, excavation, conduit bedding, surface restoration and backfill, is not included under this item and shall be considered subsidiary to elements of work covered under Contract Line Item No. 6.
2. Measurement for payment will be complete Electrical Service designed, installed, tested, and accepted including but not limited to all excavation, bedding, backfill, surface restoration, of any necessary components, i.e., conduit, transformer pad, transformer, meter, conductors, boxes, controls and incidentals.
YOSE – 158675B Revised 2/14/2018 01 27 00 - 10
3. Payment will be made to the Contractor for the actual payments made by the Contractor (without any markups) to PG&E for "Electrical Service - 5638 Foresta Road lift station", after written documentation of payment by the Contractor is presented. Payment for this CLIN shall be full compensation for all of the power utility administration, connection, and design fees, materials, labor, transportation, equipment, and incidentals necessary to complete the work described and shown in the contract documents for Electrical Service for the 5638 Foresta Road Lift Station. The value shown in the Contract Price Schedule for CLIN 7 is an allowance to be used by all offerors in their price proposals, but payment to the Contractor shall be based on actual payments by the Contractor to the utility company, as indicated above.
Contract Line Item No. 8: Bid Option C1 – Sanitary Sewer Lift Station and Overflow Storage (Trailer Court).
the removal of the Trailer court lift station pumps and components; including electrical panels replaced with a new lift station pumps and components; including electrical panels, five thousand (5,000) gallon emergency overflow storage tank, permanent installation of propane powered generator and propane tank, permanent structure over generator and control panel, permanent structure over generator, pressure test existing 4 inch sewer force main, new gravity sewer main with diversion manhole to overflow storage tank and upstream manhole with muffin monster (or approved equal). Installation involves open cut pit and trench work and associated excavation, electrical, telemetry (install new radio transmission alarm and data components to WWTP), includes all, natural vegetation, and gravel surface restoration, debris removal and disposal.
Dewatering for construction, which may be significant, shall be included at no additional cost.
Contract Line Item No. 9: Bid Option C2 – Electrical Service for Trailer Court Lift Station by Utility Company (Trailer Court).
1. This item consists of all design, materials, equipment and labor provided by the Power
Utility, Pacific Gas and Electric, (PG&E) for installation of new electrical service for the Trailer Court lift station. The work includes all design, connection, and administrative fees by PG&E, payment of the power utility's order/connection fees, and the installation of any necessary components, i.e., transformer, meter, conduit and conductor. Work performed by the NPS Contractor for completion of this item including, but not limited to coordination with the Power Utility, excavation, conduit bedding, surface restoration and backfill, is not included under this item and shall be considered subsidiary to elements of work covered under Contract Line Item No. 8.
2. Measurement for payment will be complete Electrical Service designed, installed, tested, and accepted including but not limited to all excavation, bedding, backfill, surface restoration, of any necessary components, i.e., conduit, transformer pad, transformer, meter, conductors, boxes, controls and incidentals.
YOSE – 158675B Revised 2/14/2018 01 27 00 - 11
3. Payment will be made to the Contractor for the actual payments made by the Contractor (without any markups) to PG&E for "Electrical Service – Trailer Court lift station", after written documentation of payment by the Contractor is presented. Payment for this CLIN shall be full compensation for all of the power utility administration, connection, and design fees, materials, labor, transportation, equipment, and incidentals necessary to complete the work described and shown in the contract documents for Electrical Service for the Trailer Court Sanitary Sewer Lift Station. The value shown in the Contract Price Schedule for Contract Line Item No. 9 is an allowance to be used by all offerors in their price proposals, but payment to the Contractor shall be based on actual payments by the Contractor to the utility company, as indicated above.
END OF SECTION