SECTION F – DELIVERIES OR PERFORMANCE

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR

1984)

The Contractor shall be required to (a) commence work under this contract within 15 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and

(c) complete the entire work ready for use not later than 425 calendar days after the Notice to Proceed is issued. The time stated for completion shall include final cleanup of the premises.

(End of clause)

SECTION F – Deliveries or Performance
52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)