Attachment_3_-_Amendment_1_Q_As_0001.docx
DOCX document 18 KB Posted
- Attached to
- MORAN FURNACE REPLACEMENT
- Solicitation number
- 140P1426Q0095
About this file
This is an Amendment to a federal solicitation providing clarifications and revisions to the scope of work for HVAC system replacement at the Moran Entrance Station in Grand Teton National Park. Amendment 0001 to Solicitation No. 140P1426Q0095, issued July 1, 2026, deletes the requirement to demolish and remove the existing evaporative cooler, which shall remain in place outside the contract scope. Key technical clarifications include: existing PVC venting must be removed with penetrations properly sealed; refrigerant line sets shall penetrate above the existing rock exterior; the outdoor condensing unit may be ground-mounted or roof-mounted provided manufacturer requirements are met; existing propane lines may be capped inside the building with tank removal excluded from scope; and existing propane tank removal is not included in the project.
The amendment clarifies that the specified Carrier Model FG5ANXC36L00 is for reference only, and offerors may propose equal or equivalent systems meeting performance requirements. The required system consists of a 3-ton electric air handler with electric heat strips and central air conditioning for the approximately 1,000-square-foot building. Offerors may propose either standard air-conditioning units or heat pump systems, with full installation including refrigerant piping, line sets, electrical disconnects, and associated electrical connections. This amendment is issued by the National Park Service Intermountain Region, Department of the Interior, and all other solicitation terms and conditions remain unchanged except as modified herein.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
July 1, 2026
AMENDMENT 0001
Solicitation No. 140P1426Q0095 Replace HVAC Heating & Cooling in the Moran Entrance Station Grand Teton National Park
Amendment 0001 to Solicitation No. 140P1426Q0095 is issued to provide the following:
1. Responses to questions received regarding the Scope of Work, Solicitation, and Site Visit conducted on July 1, 2026. (Attachment 3)
2. Site Visit Participant List (Attachment 4)
3. Photos of the Existing HVAC System (Attachment 5)
4. Revised Scope of Work (Attachment 6)
RESPONSES TO QUESTIONS:
The following responses are provided to clarify the Solicitation requirements and shall be considered part of the Solicitation.
Question: The Scope of Work requires that the contractor demolish and remove the evaporative cooler.
Response: The requirement to demolish and remove the existing evaporative cooler is deleted from the Scope of Work. The existing evaporative cooler shall remain in place and is not included in the scope of this contract. Attachment 6 contains the revised Scope of Work. Offerors shall base their proposals on the revised Scope of Work issued with this amendment.
Question: Does the existing PVC venting need to remain?
Response: The existing PVC venting shall be removed, and all resulting penetrations shall be properly patched and sealed.
Question: Where may the outdoor unit be installed?
Response: The outdoor unit may be mounted on a ground-mounted frame adjacent to the building or mounted on the building at a higher elevation, provided the installation complies with the manufacturer's clearance and ventilation requirements.
Question: Where should the refrigerant line sets penetrate the building?
Response: Refrigerant line sets shall penetrate the building above the existing rock exterior.
Question: What should be done with the existing propane lines and tank?
Response: Existing propane lines may be terminated inside the building and capped. Removal of the existing propane tank is not included in this project.
Question: Is the Carrier Model FG5ANXC36L00 specified in the Scope of Work required?
Response: No. The Carrier Model FG5ANXC36L00 identified in the Scope of Work is provided for reference only. Offerors may propose an equal or equivalent system that meets or exceeds the performance requirements of the project. The proposed system shall consist of a 3-ton electric air handler equipped with electric heat strips and central air conditioning suitable for the approximately 1,000-square-foot building.
Question: Is a heat pump acceptable?
Response: Yes. Offerors may propose either a standard air-conditioning condensing unit or a heat pump system. The Scope of Work requires installation of an outdoor condensing unit, including refrigerant piping, line sets, electrical disconnects, and associated electrical connections. Regardless of the system proposed, the installation shall include a 3-ton electric air handler equipped with electric heat strips (electric furnace) as specified in the revised Scope of Work.
ATTACHMENTS:
· Attachment 3 – Amendment Responses
· Attachment 4 – Site Visit Participant List
· Attachment 5 – Photos of Existing HVAC System
· Attachment 6 – Revised Scope of Work The responses and revisions contained in this amendment clarify and revise the requirements of the Solicitation. Except as modified by this amendment, all other terms and conditions of the Solicitation remain unchanged.
END OF AMENDMENT 0001