This document is a Scope of Work for repairing and recoating the Fish Creek water tank in Glacier National Park, Montana. The project involves blasting the interior of the 35,000-gallon steel tank, applying a primer coat, repairing steel defects, applying an intermediate and final coating, and recoating the exterior. The work is split into two contract line items - CLIN#1 for interior work and CLIN#2 for exterior work. Specific coating products and application requirements are detailed. The work must be completed in the shoulder seasons when the tank is drained, between September 16, 2024 to November 1, 2024 or April 7, 2025 to May 12, 2025. The contract will be awarded by the National Park Service Intermountain Region. Key requirements include wildlife protection, natural resource protection, material handling and waste management, quality control, and safety protocols.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCOPE OF WORK

REPAIR AND R ECOAT FISH CREEK WATER

TANK

GLACIER NATIONAL PARK, MONTANA

REVISED – 06/18/2024

Repair and Recoat Fish Creek Water Tank

Scope of Work 2 06/18/2024

0.0 TABLE OF CONTENTS

1.0 Overview & Project Description

2.0 Existing Conditions

3.0 Scope of Work

4.0 Codes & Authorities

5.0 Required Meetings, Submittals, & Closeout

6.0 Special Conditions & Requirements

7.0 Period of Performance

8.0 Attachments

1.0 OVERVIEW & PROJECT DESCRIPTION

This project will make repairs to and recoat the Fish Creek water tank. Constructed in the 1960s, the Fish Creek water tank is an above-ground 35,000-gallon welded steel structure that is approximately 20’ diameter by 15’ height. The tank stores potable water for the Fish Creek Campground, a 177-site seasonal campground on the west side of Glacier National Park.

The tank is in generally good condition, but the coating is showing signs of deterioration. Corrosion and steel pitting is evident along the welded steel seams, beams, columns, and walls on the interior and exterior of the structure. Regular maintenance of the structure is essential for the safe, continued operation of the system per Montana DEQ requirements in DEQ Circulars 1, 3, and 16. The Contractor shall make repairs to and repaint the water tank according to Section 3.0 Scope of Work. All interior surfaces will be blasted, repaired, and recoated. All exterior surfaces that show signs of deterioration will be repaired and recoated.

The Fish Creek Water Tank tested negative for lead-based coatings. Lead coatings were removed from the tank in 2010 to 2011 by construction contract.

All field work is to occur at the Fish Creek water tank. The water tank is accessed by navigating to the Fish Creek Ranger Station (1099 Fish Creek Campground Road, West Glacier, MT 59936), then turning left onto the gravel Inside North Fork Road, continuing 0.4 miles to the Rocky Point Trailhead parking area on the left, then continuing past a gate and 0.5 miles up a gravel road to the water tank.

The Fish Creek Campground is open from roughly mid-May to Labor Day each year. Work shall be completed in the shoulder seasons while the tank is drained.

There are two Contract Line Item (CLIN) for this project – CLIN#1 covers all interior tank work, and bid option item CLIN#2 covers all exterior work. CLIN#1 is the base bid, and CLIN#2 will be awarded based on price at the discretion of NPS. A lump-sum bid price shall be provided for each CLIN and shall include all preparation, mobilization, facilities, management, supervision, labor, subcontracts, equipment, materials, tools, testing, commissioning, training, permitting, insurance, bonds, taxes, and other costs incurred to complete the requirement as defined under Section 3.0 Scope of Work.

Refer to Section 2.0 Existing Conditions for a description of the existing conditions for the CLIN. Refer to Section 8.0 Attachments for a list of materials and data provided by NPS.

2.0 EXISTING CONDITIONS

2.1. Fish Creek Water Tank characteristics (see Site Photos attachment)

2.1.1. Diameter – 20’

Scope of Work 3 06/18/2024

2.1.2. Height – 15’

2.1.3. Volume – 35,000 gallons

2.1.4. Above ground

2.1.5. Constructed of steel sheet panels that were welded in place

2.1.6. 24” diameter side access manway bolted on, located on east side of tank

2.1.7. 24” diameter access hatch at top of tank, accessible by exterior ladder and leading to an interior ladder

2.1.8. Cylindrical steel column structure support at the center of tank

2.1.9. 20 steel beams spanning radially from the center of the tank to the outer perimeter for structural support of the ceiling

2.1.10. 4” drain on floor

2.1.11. 6” inlet on floor

2.1.12. Overflow pipe at top of tank

2.1.13. Top fill pipe

2.1.14. Coatings

a. Brown painted exterior

b. White painted interior

c. Existing coatings are lead-free. A contract completed in 2010 to 2011 removed all lead paint and recoated the Fish Creek Water Tank.

3.0 SCOPE OF WORK

3.1. The following task list does not dictate the sequence of construction. The Contractor shall determine the appropriate means and methods to accomplish the project objectives. Inspect all existing conditions and understand the full scope of related tasks. Bring any questions or unforeseen conditions to the attention of the CO.

3.2. Water Tank Pre-Inspection

3.2.1. Prior to the start of work, the Contractor shall thoroughly inspect all elements of the tank’s interior and exterior and develop a comprehensive list of all deteriorated areas in the interior and exterior of the water tank. Deteriorated areas may include, but are not limited to, areas of corrosion, steel pitting, cracking, and paint deterioration or delamination. Submit, for approval by the CO, the list of deteriorated areas that are to be repaired.

3.3. CLIN#1 - Interior Repairs and Coatings

3.3.1. General

a. On all interior surfaces of the water tank, the Contractor shall surface blast clean, apply a primer coat, repair steel defects, apply an intermediate coat, and apply a final coat as specified in Sections 3.3.2. to 3.3.6. below.

b. All interior welds, joints, corners, and seams shall have an additional “stripe coat” applied as specified in Section 3.3.7. below.

c. The Contractor shall use a non-destructive method of measuring coating thickness to verify the applied thickness of all coatings. The coating thicknesses shall conform to the manufacturer’s recommendations.

d. Block off all drains, fill lines, or other openings so that foreign materials do not enter the supply or distribution pipes.

3.3.2. Surface Blast Cleaning

Scope of Work 4 06/18/2024

a. The Contractor shall blast clean the entire interior surface of the water tank, including all interior elements such as pipes, ladders, and structural members. Blast clean to a near-white metal finish, removing all mill scale, rust dirt, paint, or other foreign matter by any of the recommended methods outlined in the Society of Protective Coatings Specification SSPC-SP6/NACE 3 Commercial Blast Cleaning to establish a minimum angular anchor profile of 1.5 mils, or per the coating manufacturer’s recommendation.

b. All abrasives shall be dry, clean, free of oils or grease, dirt, chemicals, and other contaminants that may interfere with adhesion of the coating. Abrasives shall not be reused from another project or this project. Abrasives shall be fully contained, collected, and removed from the jobsite as not to pollute the natural environment.

3.3.3. Primer Coat

a. Immediately after surface preparation and before any rusting occurs, apply Tnemec

Series 94-H20 Hydro-Zinc Primer (zinc-rich aromatic urethane) or an approved equal product. Apply manufacturer’s recommended 2.5 to 3.5 mil dry film thickness. Apply per manufacturer recommendations.

b. Minimum product qualifications: a zinc-rich primer that offers long-term corrosion resistance for interior use on steel potable water tanks, certified by NSF International in accordance with NSF/ANSI Std. 61 and extraction requirements of NSF/ANSI 600, meets AWWA D102 requirements for interior potable water tank coatings, and uses zinc pigments to meet the requirements of ASTM D520 Type III and contains less than 0.002% lead.

3.3.4. Steel Repairs

a. After application of the primer coat, spot fill any pits deeper than 1/16” and less than

1/2” with Tnemec Series 215 Surfacing Epoxy (modified polyamine epoxy) in 1200 White color or an approved equal product, until flush with the existing surface.

Minimum product Ensure the surface is clean, dry, and free of oils, grease, or other contaminants.

b. Minimum product qualifications: a 100% solids epoxy filler and surfacer for interior use on steel potable water tanks, certified by NSF International in accordance with NSF/ANSI Std. 61 and extraction requirements of NSF/ANSI 600.

c. Pits, seams, or other defects greater than 1/2” in size that would require a weld repair are not anticipated. Should the Contractor’s Pre-Inspection note any areas that will require a weld repair, the Contractor shall notify the CO. After inspection and repair approval by NPS, the cost of repairs will be negotiated with the Contractor.

3.3.5. Intermediate Coat

a. Apply Tnemec Series 21 Epoxoline (phenalkamine epoxy) in 39BL Delft Blue color or an approved equal product. Apply manufacturer’s recommended 4.0 to 20.0 mils dry film thickness. Apply per manufacturer recommendations. Ensure the surface is clean, dry, and free of oils, grease, or other contaminants.

b. Minimum product qualifications: a topcoat that offers long-term corrosion resistance, certified by NSF International in accordance with NSF/ANSI Std. 61 and extraction requirements of NSF/ANSI 600, meets AWWA C210, meets AWWA D102, and certified for use interior use on tanks, reservoirs, pipes, and fittings.

3.3.6. Final Coat

a. Along all interior joints and seams apply Tnemec Series 21 Epoxoline (phenalkamine epoxy) in WH16 Off-White color, or an approved equal product. Apply

Scope of Work 5 06/18/2024 manufacturer’s recommended 4.0 to 20.0 mils dry film thickness. Apply per manufacturer recommendations. Ensure the surface is clean, dry, and free of oils, grease, or other contaminants.

b. Minimum product qualifications: a topcoat that offers long-term corrosion resistance, certified by NSF International in accordance with NSF/ANSI Std. 61 and extraction requirements of NSF/ANSI 600, meets AWWA C210, meets AWWA D102, and certified for use interior use on tanks, reservoirs, pipes, and fittings.

3.3.7. Stripe Coat

a. Within a minimum 4” in all directions (for a minimum total width of 8”) of all interior welds, joints, corners, and seams, apply Tnemec Series 21 Epoxoline (phenalkamine epoxy) in WH16 Off-White color, or approved equal product. Apply manufacturer’s recommended 4.0 to 20.0 mils dry film thickness. Apply per manufacturer recommendations. Ensure the surface is clean, dry, and free of oils, grease, or other contaminants.

b. Minimum product qualifications: a topcoat that offers long-term corrosion resistance, certified by NSF International in accordance with NSF/ANSI Std. 61 and extraction requirements of NSF/ANSI 600, meets AWWA C210, meets AWWA D102, and certified for use interior use on tanks, reservoirs, pipes, and fittings.

3.3.8. Interior Ladder Hardware

a. Eight steel nuts and bolts connect sections of the interior ladder. Remove and replace with stainless steel nuts and bolts of the same size.

3.3.9. Disinfection

a. Upon completion and acceptance of all interior work, the Contractor shall disinfect the interior of the water tank per AWWA Standard C652 by spraying all water-contact surfaces with a solution of 200 mg/L available chlorine.

3.4. Option CLIN#2 Exterior Repairs and Coatings

3.4.1. General

a. The water tank’s exterior is in generally good condition and only spot repairs are needed on the exterior to keep the tank in safe operating condition. In all areas of deterioration as agreed upon by the Contractor and CO per the Contractor’s Pre- Inspection, the Contractor shall surface clean, apply a primer coat, and apply an intermediate coat as specified in Sections 3.4.2. to 3.4.4. below.

b. Regardless of condition, the entire exterior of the water tank shall have a final coat applied as specified in Section 3.4.5. below.

c. The Contractor shall use a non-destructive method of measuring coating thickness to verify the applied thickness of all coatings. The coating thicknesses shall conform to the manufacturer’s recommendations.

3.4.2. Surface Cleaning

a. Remove all visible oils, grease, soil, dirt, chalk, and other soluble contaminants per

SSPC-SP WJ-4/NACE WJ-4 Light Cleaning by use of Low Pressure Water Cleaning between 3,500 and 5,000 psi using a 0-degree rotating nozzle. Remaining contaminants, including loose mill scale, loose rust, or other corrosion products should be removed using SSPC-SP2 Hand Tool Cleaning or SSPC-SP3 Power Tool Cleaning criteria.

3.4.3. Primer Coat

a. Immediately after surface preparation and before any rusting occurs, apply Tnemec

Series 118 Uni-Bond Mastic (mastic waterborne acrylic) in 1281 White color or an

Scope of Work 6 06/18/2024 approved equal product. Apply manufacturer’s suggested 7.0 mil dry film thickness (minimum 6.0, maximum 8.0 mil dry film thickness). Apply per manufacturer recommendations.

b. Minimum product qualifications: a high-build, rust-inhibitive, primer coating that offers corrosion resistance for use on exterior steel surfaces, meets LEED Low- Emitting Materials requirements.

3.4.4. Intermediate Coat

a. After application of primer coat, apply an intermediate coat of Tnemec Series 1096

Endura-Shield (aliphatic acrylic polyurethane, eggshell finish) in a color to best match the existing tank color, or an approved equal product. Coordinate color selection with NPS. Apply manufacturer’s suggested 2.5 mil dry film thickness (minimum 2.0, maximum 5.0 mil dry film thickness) per coat. Apply per manufacturer recommendations.

b. Minimum product qualifications: a low VOC topcoat that provides color and gloss retention for use on exterior steel surfaces, meets LEED Low-Emitting Materials requirements.

3.4.5. Final Coat

a. After application of the intermediate coat, apply a final coat of Tnemec Series 1096

Endura-Shield (aliphatic acrylic polyurethane, eggshell finish) to all exterior tank surfaces in a color to best match the existing tank color, or an approved equal product. Coordinate color selection with NPS. Apply manufacturer’s suggested 2.5 mil dry film thickness (minimum 2.0, maximum 5.0 mil dry film thickness) per coat.

Apply per manufacturer recommendations.

b. Minimum product qualifications: a low VOC topcoat that provides color and gloss retention for use on exterior steel surfaces, meets LEED Low-Emitting Materials requirements.

3.5. General

3.5.1. The Contractor shall provide facilities to clean brushes and other tools. Coatings shall not be washed out onto the ground surface. All debris from surface blasting or grinding shall be immediately collected, contained, and all material and waste shall be legally disposed outside of Park boundaries.

3.5.2. All work shall be completed per the coating manufacturer’s recommendations, including application methods and environmental conditions during application.

4.0 CODES & AUTHORITIES

4.1. All work shall be performed in accordance with the following codes. Should codes conflict, the more stringent requirement shall apply.

4.1.1. Health and Safety Codes

a. 29 CFR 1910 Occupational Safety And Health Standards

1) https://www.osha.gov/laws-regs/regulations/standardnumber/1910

b. 29 CFR 1926 Safety And Health Regulations For Construction

1) https://www.osha.gov/laws-regs/regulations/standardnumber/1926

c. NFPA 241 Standards For Safeguarding Construction, Alteration, And Demolition Operations

1) https://www.nfpa.org/codes-and-standards/nfpa-241-standard-development/241

4.1.2. Montana State Codes

Scope of Work 7 06/18/2024

a. Montana DEQ Circulars, current editions

1) https://deq.mt.gov/water/resources

4.2. The following standards shall apply for all used materials, installations, and tests, including but not limited to:

4.2.1. ASTM American Society For Testing And Materials International

a. https://www.astm.org/

4.2.2. AWWA American Water Works Association

a. https://www.awwa.org/Publications/Standards

4.2.3. ANSI American National Standards Institute

a. https://www.ansi.org/

4.2.4. AISC American Institute Of Steel Construction

a. https://www.aisc.org/

4.2.5. AISI American Iron And Steel Institute

a. https://www.steel.org/

4.2.6. AMPP Association for Materials Protection and Performance

a. https://www.ampp.org/home

4.2.7. AWS American Welding Society

a. https://www.aws.org/

4.2.8. NSF National Sanitation Foundation

a. https://www.nsf.org/

4.2.9. UL Underwriters Laboratories

a. https://www.shopulstandards.com/

5.0 REQUIRED MEETINGS, SUBMITTALS, PAYMENTS, & CLOSEOUT

5.1. Pre-Construction Meeting

5.1.1. A pre-construction meeting will be held with the Contractor, CO, COR, and NPS to cover basic procedures and regulations. This meeting will include, at minimum: discussions on Park rules and regulations, wildlife management, correspondence procedures, progress meetings, lines of authority, roles and responsibilities, coordination of subcontractors, submittal procedures, construction schedule, progress payments, acceptance and rejection of work, liquidated damages, labor standards, payroll reports, contract modifications, accident prevention, quality control, waste management and recycling, emergency procedures, road and site constraints, environmental considerations, and value engineering.

5.1.2. Meeting notes will be recorded and distributed by NPS.

5.2. Submittals

5.2.1. Submittals will be reviewed by the COR and CO. Submit at least 14 days prior to needed approval.

5.2.2. Submit the following items within 10 days of contract award. Once approved, the CO will issue the Notice to Proceed.

a. Performance Bonds (if required by contract)

b. Certificate of Insurance

c. SF1413 forms for all Contractors and Subcontractors

5.2.3. Submit the following items after contract award but before the start of work using the provided NPS CM-16 form. Submittals shall be specific to the project.

a. Material technical and safety sheets for all proposed materials

Scope of Work 8 06/18/2024

b. Letter of Site Superintendent Designation

c. List of all Subcontractors (shall match that given in the Contractor’s proposal)

d. Final Construction Schedule

e. Quality Control Plan (see Section 6.9.)

f. Safety and Accident Prevention Plan (see Section 6.10.), incorporating a Hazardous

Spill Plan

5.2.4. Submit the following items during work or prior to requesting a final inspection using the provided NPS CM-16 form:

a. Contractor Daily Reports

b. Contractor Quality Control Reports

c. Digital Photos

d. Testing Reports, as applicable

5.3. Payments

5.3.1. The Contractor shall submit payments (for approval by the CO) at the completion of all work under the Contract Line Item.

5.3.2. The Contractor shall provide all field notes, invoices and payroll reports, and other records relating to the basis of payment to the CO.

5.4. Project Closeout

5.4.1. Submittals

a. Submit all deliverables listed in Section 5.3. Submittals and make any corrections required by the CO’s review.

5.4.2. Final Cleaning

a. The Contractor shall perform a final cleaning of the project area, including removal of all tools, equipment, materials, waste, and any grease, stains, labels, or other foreign materials. The project area shall be clean and ready for use by NPS.

5.4.3. Substantial Completion, Final Inspection, and Acceptance

a. As the project is nearing completion, submit written certification that the project, or designated portion of the project, is substantially complete and ready for a Substantial Completion Inspection. After the Substantial Completion Inspection, the CO will issue a punch list for any deficiencies noted. The CO will issue a Letter of Substantial Completion.

b. At the completion of the punch list items, the Contractor shall request a Final Inspection. The CO will ensure that all work and punch list items are completed to the satisfaction of NPS.

c. All deficiencies shall be corrected within 10 days, weather permitting. The CO will issue a Letter of Acceptance when all deficiencies are corrected. If the Contractor fails to complete the work within 10 days of issuance of the punch list, the CO may correct the work with an appropriate reduction in the contract price or charge for re-inspection costs.

6.0 SPECIAL CONDITIONS & REQUIREMENTS

6.1. Wildlife Protection

6.1.1. Wildlife protection is of utmost importance. All Contractors and Subcontractors shall receive a briefing from NPS biologists about working around wildlife, including bears, prior to the start of work. Notify the CO at least 14 days prior to the start of work to schedule this briefing. All construction personnel are required to fully understand and

Scope of Work 9 06/18/2024 abide by all Park requirements, which will be strictly enforced at all times. Failure to comply may result in a citation and fine. A copy of Bear, Wildlife, and Sanitation Requirements While Working in Glacier National Park will be provided to the Contractor. Key points of this document include:

a. Food handling and storage

1) When not in use, food, beverages, containers, and utensils shall be kept inside of buildings, enclosed vehicles or trailers, storage sheds, or bear-proof coolers.

b. Material handling and storage

c. Petroleum product, antifreeze, and chemical handling and storage

1) Petroleum products, antifreeze, and other chemicals are known to attract and kill wildlife. When not in use, these materials shall be kept in bear-resistant containers.

d. Equipment use, maintenance, and refueling

1) Leaky equipment should be repaired immediately.

2) Refueling and servicing shall not occur within 100 feet of a water body.

e. Sanitation requirements, including site cleanliness, trash handling and disposal, and portable toilet requirements

1) Portable toilets must be lockable and be firmly staked into the ground to resist the force of 70 mph winds, or that of a curious grizzly bear.

2) Construction debris and trash must be disposed of in bear-proof bins or dumpsters, unless kept inside of buildings, enclosed vehicles or trailers, storage sheds, or bear-proof containers.

3) Construction debris and food waste shall not be mixed.

4) Immediately collect and contain scraps and waste.

f. Wildlife safety and potential wildlife interactions

1) All personnel should have bear spray readily available.

2) Activities shall be suspended if a bear, wolf, mountain lion, or other aggressive, conditioned, or habituated animal comes near the construction area and creates a potential human-wildlife conflict. Notify Glacier Dispatch immediately for resolution of the potential conflict.

3) Report wildlife sightings to the CO and COR.

6.1.2. Protect natural habitats, including nests, and ecological systems at or near the project site.

6.1.3. Protect any unknown or undiscovered threatened, endangered, or special status species. Immediately stop work and contact the CO and COR if these species are found at the site.

6.2. Natural Resource Protection

6.2.1. Air, Water, and Soil Pollution

a. Employ construction practices that minimize dust production and combustion byproducts.

b. Avoid materials that can leach toxic chemicals into the groundwater. Do not allow toxic chemicals to enter sewers or storm drains. Apply Best Management Practices, including vehicle wash-down areas, equipment storage and maintenance areas protection, and roadway sweeping related to hauling activities.

c. Air quality impacts are expected to be temporary and localized. To reduce tailpipe emissions, vehicles and equipment shall not be left idling any longer than is necessary for safety and mechanical reasons.

Scope of Work 10 06/18/2024

d. Volatile wastes shall be stored according to best industry practices and in covered containers.

e. Repair leaky equipment immediately.

1) Do not use equipment that is leaking.

2) Keep a supply of acceptable absorbent materials at the job site in the event of spills.

3) Acceptable absorbent materials are those manufactured specifically for containment and clean-up of hazardous materials.

f. Protect against erosion, contamination, and topsoil depletion.

6.2.2. Invasive Species

a. To prevent the introduction of noxious weeds to the Park, the Contractor shall thoroughly pressure wash all earth-moving and off-road vehicles and equipment with minimum 122°F water at 2,900 psi prior to entering the Park. All equipment must be free of soils, plant matter, and other debris as determined the COR.

Coordinate inspections with the COR at least two business days prior to bringing equipment to the Park. Failed inspections must be corrected at the Contractor’s expense. Vehicles and equipment that are re-entering the Park do not have to be cleaned again, provided that it has not operated on a different jobsite. Coordinate with the COR.

6.2.3. Soundscapes

a. Use of equipment that generates more than 80 dB shall be minimized.

6.3. Visitor Management

6.3.1. The Fish Creek water tank is not in a public area of the Park. The tank is accessed via a gated access road. The Contractor shall ensure that this gate is properly closed at all times.

6.3.2. The Contractor is responsible for jobsite safety and security. The Contractor shall secure the jobsite to prevent any potential hazards to visitors and NPS staff at all times.

6.3.3. Minimize interference with NPS operations, visitors, and traffic near the project area.

Coordinate with NPS.

6.4. Contractor Access to the Park and Facilities

6.4.1. The Park does not provide lodging or campsites to Contractors. The Contractor shall not set up undesignated camps at (or near) the project site. The Contractor is responsible for finding accommodations on their own.

6.4.2. Coordinate with the COR for Park entry passes. Entry passes are required to be displayed on the dashboard of all Contractor vehicles and shown to NPS personnel at the Entrance Station. Entry passes are of no cost to the Contractor.

6.4.3. Coordinate with the COR for access to gates and buildings. The Contractor shall be responsible for safekeeping any loaned keys. The Contractor shall pay to replace lost or damaged keys.

6.5. Contractor Use of Utilities

6.5.1. There is no water, sewer, electric, internet, or cell service available at the project site.

Plan accordingly.

6.5.2. The Contractor shall provide and maintain portable toilet facilities for the duration of the project. Portable toilets shall be lockable and staked into the ground to resist the force of 70 mph winds, or that of a curious grizzly bear. Alternatively, a vault toilet is

Scope of Work 11 06/18/2024 available for Contractor use at the Fish Creek Picnic Area, located approximately 0.2 miles from the Fish Creek Ranger Station.

6.5.3. The Contractor shall provide and maintain any needed heating or cooling facilities.

6.5.4. The Contractor shall fully remove all temporary facilities prior to the final inspection.

6.5.5. Accidental utility disruptions or damage to the utility system shall be remedied immediately at no cost to NPS.

6.6. Contractor Use of Site

6.6.1. The Contractor shall keep the site neat and orderly at all times. Schedule regular

“housekeeping” to ensure this. The site must always be free of wildlife attractants and potential hazards to NPS and visitors.

6.6.2. The Contractor shall be responsible for any damage caused by the Contractor that is outside of the scope of this project. Any damage shall immediately be remedied at no cost to NPS.

6.6.3. The Contractor shall minimize the footprint of the site.

6.6.4. The Contractor shall confine operations to within the cleared area surrounding the water tank.

6.6.5. The Contractor shall prevent undue damage to the site’s natural surroundings.

a. The Contractor shall restore damaged areas outside of the immediate project area, including but not limited to, vegetation restoration and tree repair or replacement.

6.6.6. The Contractor shall allow for NPS occupation or visitation of the site and always keep driveways and entrances serving premises clear and available to NPS and emergency vehicles.

6.7. Vehicles, Equipment, Parking & Staging Areas

6.7.1. The Contractor shall clean vehicles and equipment to prevent the introduction of invasive species or noxious weeds into the Park, as described in Section 6.2. Natural Resource Protection above.

6.7.2. Comply with all local, state, and federal loading and hauling restrictions.

a. The railroad overpass bridge at the intersection of US-2 and Going to the Sun Road in West Glacier has as clearance of approximately 13’-6”. Verify clearance and vehicle height before taking this route. The alternate route is to take the North Fork Road to Camas Road into the Park.

6.7.3. Parking and staging areas shall not obstruct emergency traffic, visitor traffic, or prevent NPS occupation or visitation of the site.

6.7.4. Do not park or operate vehicles and equipment on vegetated surfaces, unless within the defined site. Do not damage trees or shrubs that are to remain.

6.7.5. Parking, staging, and storage is at the risk of the Contractor.

6.7.6. Parking and staging is allowed in the cleared area surrounding the Fish Creek water tank.

Limit material staging to the smallest practical area.

6.7.7. All coatings and application equipment shall be kept in a bear-proof locker or enclosed vehicle or trailer when left unattended. Containers must be fully sealed and leak-free.

6.8. Material Handling & Waste

6.8.1. The Contractor shall handle and store materials and waste as described in Section 6.1.

Wildlife Protection above.

6.8.2. Materials shall be used efficiently. Select materials and use construction practices that achieve the most efficient use of resources and materials. Minimize waste generation

Scope of Work 12 06/18/2024 due to over-packaging, poor planning, breakage, mishandling, contamination, error, or other factors. Reuse, recycle, or salvage as much of the waste generated as is economically feasible. Minimize waste disposal in landfills.

6.8.3. Materials shall be delivered in the manufacturer’s original, sealed packaging with labels legible and intact. Materials shall be handled and stored per the manufacturer’s recommendations.

6.8.4. Contaminated, damaged, unsealed, or materials not conforming to the specifications shall not be used. Rejected materials must be removed from to jobsite and replaced at no additional cost to NPS.

6.8.5. Materials shall be recycled to the maximum practical extent. Recyclable materials include carboard, paper, packaging, wood, containers, concrete, metals, drywall, paint, glass, and plastics.

6.8.6. All waste shall be disposed of outside of the Park in accordance with local, State, and Federal requirements.

6.9. Quality Control

6.9.1. Quality Control Program

a. A site-specific Quality Control Program (QCP) shall be developed by the Contractor.

The plan shall include, at minimum:

1) A list of personnel responsible for quality control and assigned duties. Include each person's qualifications.

2) A copy of a letter of direction to the Contractor's Quality Control Supervisor (QCS) that will carry out and oversee the QCP. The QCS (and alternate QCS, if applicable) shall be qualified and competent to perform these duties.

3) Names, qualifications, and descriptions of laboratories to perform sampling and testing and samples of proposed report forms, if required.

4) Methods of performing, documenting, and enforcing quality control of all work.

5) Methods of monitoring and controlling environmental pollution and contamination as required by regulations and laws.

b. The quality of all work shall be the responsibility of the Contractor. Inspect and test all work as needed to ensure that the quality of materials, workmanship, construction, finish, and functional performance follows applicable specifications and drawings. Quality Control Daily Reports shall be completed by the QCS. Daily Test Reports shall be completed by the person performing the test.

6.9.2. Testing and Reporting

a. All work shall be tested, as applicable, to ensure that the quality of materials, workmanship, construction, finish, and functional performance is within the contract documents.

b. All measuring devices, laboratory equipment, and instruments shall be calibrated at established intervals against certified standards in accordance with NBS requirements. Upon request, measuring and testing devices shall be made available for use by NPS for verification tests.

6.9.3. Enforcement

a. The Contractor shall stop work on any item or feature pending satisfactory correction of any deficiency noted by the QCS or the CO.

6.10. Safety and Accident Prevention

6.10.1. Quality Assurance

Scope of Work 13 06/18/2024

a. A site-specific Safety and Accident Prevention Plan (SAPP) shall be developed by the Contractor to identify, assess, and mitigate potential hazards associated with the project through all phases of work. The SAPP should encompass detailed safety protocols, emergency response procedures, and protective measures aimed at ensuring the well-being of all Contractor and Subcontractor personnel, NPS employees, and visitors on or around the site.

b. A qualified and competent supervisor (and alternate supervisor, if applicable) shall be named to oversee and carry out the SAPP.

c. The Contractor shall ensure that all employees are physically qualified to perform their assigned duties safely. Do not allow employees to work if their abilities are impaired. Operators of all equipment shall be able to understand signs, signals, and operating instructions and be capable of operating such equipment.

6.10.2. Hazardous Spills

a. The Contractor shall incorporate preventative measures into their SAPP to prevent hazardous spills. Hazardous spills shall be reported to Glacier Dispatch and the CO immediately.

6.10.3. Safety Measures

a. The Contractor shall provide and make readily-accessible to all personnel, the following:

1) First Aid supplies

2) PPE that meets NIOSH and MSHA standards

3) Safety Data Sheets for all used materials

4) Emergency instructions, including phone numbers and reporting instructions for

Glacier Dispatch and emergency medical care.

5) Adequate egress at all times, following Life Safety Code NFPA 241

6) Hard hats for all employees and visitors

7) Posted signs in all designated hard hat areas

8) Hazardous spill clean-up kit

9) Fire prevention and protection equipment, as outlined in Section 6.13. Fire

Prevention and Protection

b. Training

1) Provide training for first aid and hazardous material handling and storage.

2) On-site safety meetings with all personnel shall be conducted at least once per week.

3) All Contractor personnel are required to be trained in hazards associated with confined space entry. All confined space entries and work in a confined space shall adhere to 29 CFR 1910.146 requirements.

4) All Contractor personnel are required to be trained in hazards associated with working at elevated heights. All work shall be completed in compliance with 29 CFR 1910.501 requirements for fall protection. The top of the water tank is approximately 15’ above grade.

c. Enforcement

1) The Contractor shall stop work on any item or feature pending satisfactory correction of any safety issue noted by any of the Contractor's staff, the subcontractor's staff, COR, or the CO.

d. Accident Reporting

1) Reportable accidents, defined as death, occupational disease, traumatic injury to

Contractor's personnel, NPS employees or the public, property damage of any

Scope of Work 14 06/18/2024 accident more than $100 and fires, must be reported immediately. Complete an Accident/Property Damage Report using the NPS standard Form CM-22 and forward to the CO within seven days.

6.11. Fire Prevention and Protection

6.11.1. Fire Safety

a. Observe and enforce standards of fire prevention. No open fires shall be allowed.

b. Capable and qualified person shall be in change for fire protection and prevention.

Their responsibilities include locating and maintaining fire protection equipment and establishing and maintaining safe torch cutting and welding procedures.

6.11.2. Vehicles and Equipment

a. Provide one fire extinguisher on each vehicle or piece of equipment. A minimum of one fire extinguisher shall be readily available in all work areas. Extinguishers shall have a minimum UL rating of 2-A:10-B:C.

6.11.3. Hazard Control

a. Take all necessary precautions to prevent fire during construction. Do not store flammable or combustible liquids in enclosed areas. Provide adequate ventilation during use of volatile or noxious substances.

6.11.4. Spark Arrestors

a. Equip all gasoline or diesel-powered equipment used in potential forest or grass fire locations with spark arresters approved by the U.S. Forest Service. Written determinations of areas and periods of potential fire hazard will be issued by CO.

Locate internal combustion equipment so that exhausts discharge well away from combustible materials. Shut down equipment before refueling.

6.11.5. Smoking

a. Smoking inside of structures near potentially combustible materials is prohibited.

Cigarette butts shall be discarded in non-combustible containers and disposed of properly.

6.11.6. Welding and Grinding

a. Cutting by torch or grinding shall only be performed when adequate fire protection is provided and readily available.

6.11.7. Stage 2 Fire Restrictions

a. Should the Park enter Stage 2 Fire Restrictions during the period of performance, the Contractor may be required to obtain a Stage 2 Fire Restriction Exemption Permit from the GLAC Fire Management Office. Additional firefighting tools may be required to be readily available during work.

b. Stage 2 Fire Restrictions prohibit the following activities, without an exemption permit:

1) Building, maintaining, attending, or using a campfire

2) Smoking, outside of an enclosed vehicle or area clear of flammable materials

3) The following acts are prohibited between 1:00 pm and 1:00 am, and a one-hour foot patrol is required following the cessation of the following activities:

1. Operation of an internal combustion engine, except for use of generators with an approved spark arrestor in an enclosed vehicle or building or area cleared of any flammable materials within three feet of the generator.

2. Welding or use of a torch with an open flame

3. Use of explosives

4) Operation of motorized vehicles off designated roads or trails.

Scope of Work 15 06/18/2024

7.0 PERIOD OF PERFORMANCE

7.1. The allowable on-site work window for the completion of this project shall be from September 16, 2024 to November 1, 2024 or April 7, 2025 to May 12, 2025. Please take weather factors into account when creating a construction schedule. Snow may affect work in late-October or April.

7.1.1. The Fish Creek Campground is open from roughly Memorial Day weekend to Labor Day weekend annually. NPS utility crews will drain the tank soon after Labor Day. The tank must be filled roughly 10 days prior to campground opening on Memorial Day weekend.

All work shall be completed while the water tank is drained.

7.2. Work may generally be performed from 7 am to 6 pm, Monday to Friday. Weekends and holidays may be worked if approved at least two business days in advance by the COR and CO.

8.0 ATTACHMENTS

8.1. Project Scope of Work (this document)

8.2. Site Photos

8.3. Tnemec Product Data and Safety Data Sheets

8.3.1. Tnemec Series 21 Epoxoline

8.3.2. Tnemec Series 94 H2O Hydro-Zinc Primer

8.3.3. Tnemec Series 118 Uni-Bond Mastic

8.3.4. Tnemec Series 215 Surfacing Epoxy

8.3.5. Tnemec Series 1096 Endura-Shield