RFI_02_-_140P1325Q0027_0002.pdf

PDF 38 KB Posted

Attached to
OSTB-REPLACE SECURITY SYSTEM CAMERAS/MON
Solicitation number
140P1325Q0027
Issued by

About this file

This document is a Request for Information (RFI) for the Department of the Interior National Park Service Intermountain Region's project to replace security system cameras. The RFI contains three key questions seeking clarification on technical requirements: (1) whether Axis brand cameras are mandatory or if equivalent models from other manufacturers are acceptable, (2) the scope of cabling installation including whether infrastructure will be pre-installed or must be provided by the contractor, and (3) noting that drawing plans for pages 8 and 9 of the Statement of Work are currently missing and will be provided separately. The brand name justification for camera specifications was previously uploaded to sam.gov as an attachment to amendment 01, and cabling will need to be installed from cameras to one of two phone/data rooms located in the building's basement, with existing infrastructure between those rooms.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI 02 140P1325Q0027 - 0044007460_OSTB-REPLACE SECURITY SYSTEM CAMERAS

1. Camera Brand Requirement: Is there a requirement for the cameras to be Axis brand, or are equivalent models from other reputable manufacturers acceptable?

Brand name justification was uploaded to sam.gov as an attachment to amendment 01.

2. Cabling Scope: Does the scope of work include installation of all necessary cabling throughout the building for full system integration, or will the infrastructure be pre-installed? Cabling will need to be provided and installed from cameras to one of the two phone/data rooms in the basements. There is existing infrastructure between the two phone/data rooms. See building plan for additional information.

3. I believe the drawing plans that are supposed to be on pages 8 and 9 of the SOW are missing. There is a label, but no drawing. Drawing plans/pages 8 and 9 will be provided.