This is a Questions and Answers document for federal contract opportunity 140L1726Q0043 addressing clarifications on solicitation discrepancies and project scope.
Key Clarifications:
The period of performance is 30 calendar days from award, with an anticipated award date of August 31, 2026. The applicable wage determination is WD 2015-5435, Revision 29, dated December 3, 2025 (revised May 13, 2026). The correct business size standard is $19.0 million under NAICS 238220. Line item numbering uses 00010 (0001), 00020 (0002), and 00030 (0003) on both the SF-1449 and price schedule. Responses to these questions were posted on SAM.gov without extension of the quotation due date. The Government provided a chiller inspection report documenting findings from September 18th.
Scope of Work:
The contract involves repair and maintenance of dual-circuit chiller systems. CLIN 0001 requires genuine OEM York components (pressure transducers, temperature sensors, and liquid line filter drier cores) based on equipment manufacturer specifications and system compatibility requirements. CLIN 0002 involves corrective maintenance including refrigerant recovery, filter drier replacement, triple evacuation, and recharge on System 2 (Circuit 2), along with sensor replacement on System 1 (Circuit 1). CLIN 0003 is a diagnostic, assessment, and reporting deliverable only—it requires troubleshooting, written findings assessment, recommended corrective repairs, and cost estimates, with any additional repairs to be addressed separately by Government authorization. The inspection report recommends replacing pressure transducers and temperature sensors on System 1 and replacing liquid line filter-drier cores with deep vacuum and recharge on System 2.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140L1726Q0043_Amd_0004.pdf | ||
| Sol_140L1726Q0043_Amd_0003.pdf | ||
| Sol_140L1726Q0043_Amd_0002.pdf | ||
| Sol_140L1726Q0043_Amd_0001.pdf | ||
| Sol_140L1726Q0043.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions & Answers 140L1726Q0043
1. The period of performance is stated three different ways. The Continuation Sheet states 08/31/2026 to 09/30/2026 and elsewhere references 30 calendar days from award, while Section F.1 and PWS Section 1.2 both state 90 calendar days from date of award. Which period governs?
a. The period of performance will be 30 calendar days. We are looking to award by 8/31/2026.
2. Section A.8 and Section E.2 incorporate SCLS Wage Determination 2015-5415, Revision 26, dated 07/08/2025. The wage determination actually attached to the solicitation is WD 2015-5435, Revision 29, dated 12/03/2025. Which wage determination applies to this acquisition?
a. Revised 5/13/2026 – WD 2015-5435
3. The SF-1449 cover page states a size standard of $19.0 million under NAICS 238220, while Sections A.1 and G state $22.0 million. Which size standard applies?
a. The correct business size is $19.0 million.
4. The Continuation Sheet identifies the line items as 00010, 00020, and 00030, while Section C and Section A.3 identify them as 0001, 0002, and 0003. Would the Government please confirm which numbering should be used on the SF-1449 and the Price Schedule?
a. 00010 = 0001, 00020 = 0002, and 00030 = 0003
5. Will responses to questions be issued as an amendment posted to SAM.gov, and will the quotation due date be adjusted?
a. The responses will be posted on SAM.gov – No, there is no plan to extend the due date at this time.
6. PWS Section 2.6 states that the listed work is the result of a previous troubleshooting effort.
Would the Government please provide the service notes, diagnostic findings, or contractor report from that effort? Prospective offerors and their technicians are being asked to install a specified list of components without the underlying basis for the diagnosis, and access to those findings would materially improve pricing accuracy.
a. Answer: Yes, please see chiller inspection report below.
7. Are OEM York components required for the pressure transducers, temperature sensors, and liquid line filter drier cores, or are functionally equivalent components acceptable? This question has a significant effect on the price of CLIN 0001.
a. Answer: Yes. Pursuant to existing equipment manufacturer specifications and system compatibility requirements, genuine OEM York components are required.
8. PWS Section 2.3 states that System 1 (Circuit 1) is displaying low suction pressure. However, PWS Section 2.4.2 assigns the refrigerant recovery, filter drier core replacement, triple evacuation, and recharge to System 2 (Circuit 2) only. Would the Government please confirm that this assignment is correct as written, or advise whether the circuit designations should be reversed?
a. Answer: Yes, the PWS is written correctly. Please review the attached report; review section labeled “Additional Notes” and “recommendation” for additional guidance
140L1726Q0043 Page 1 of 6
Questions & Answers 140L1726Q0043
9. Would the Government please confirm the scope and intent of CLIN 0003? Section C.1 and PWS Section 2.6 describe the deliverable as troubleshooting, a written assessment of findings, recommended corrective repairs, and a cost estimate for additional work. We read this as a diagnostic and reporting deliverable rather than a guarantee that the chiller will be restored to operation within the not-to-exceed amount, with any additional corrective repairs handled by separate authorization. Please confirm.
a. Answer: Correct. CLIN 0003 is a diagnostic, assessment, and reporting deliverable only. Any additional corrective repairs identified in the resulting report will be addressed separately by the Government.
140L1726Q0043 Page 2 of 6
The chillers were inspected on September 18th and below are the findings:
• System 1 (Circuit 1):
o The unit operates normally under warmer ambient conditions but trips on low suction/low charge alarms during colder weather.
o No signs of leaks or oil staining were observed on coils, headers, or service valves.
o Based on these findings, the most probable cause is drifting sensors, particularly the suction pressure transducer and liquid line temperature sensor. To eliminate nuisance alarms and stabilize control logic, I recommend replacing both pressure transducers (suction and discharge) as well as the suction and liquid line temperature sensors.
o While current behavior points more strongly toward sensor error, a weak or failing compressor could also present as low suction. At this time there is not enough evidence to confirm compressor failure. After sensor replacement, compressor performance should be monitored, and replacement considered if abnormal suction conditions continue.
• System 2 (Circuit 2):
o The sight glass was observed flashing with large bubbles when one compressor staged off, which indicates borderline refrigerant charge or a possible restriction at the liquid line filter-drier.
o When both compressors run, the sight glass clears, suggesting the charge is close but not holding a consistent liquid column under reduced load.
o Recommended corrective action is to replace the liquid line filter-drier cores, pull a deep vacuum, and recharge to factory nameplate specification. After recharging, sensors should be verified and replaced if readings remain inconsistent.
• Additional Notes:
o Both systems show low suction alarms in history, though the root cause differs (sensors on System 1 vs refrigerant/drier issue on System 2).
o Running System 2 alone places extra strain on that circuit and reduces system redundancy. Once corrective actions are completed, both systems should share the load to extend equipment life and maintain efficiency.
Chiller Inspection Report
140L1726Q0043 Page 3 of 6
140L1726Q0043 Page 4 of 6
140L1726Q0043 Page 5 of 6
Recommendation:
After reviewing System 1 and System 2 with the crew on site, the consensus is to begin with the less expensive corrective path. For System 1, that means replacing the suction and discharge pressure transducers along with the suction and liquid line temperature sensors. These components are the most likely cause of the low charge/low suction alarms observed in cooler weather. If, after replacement, System 1 continues to show abnormal suction readings, the next step would be to evaluate compressor health and consider replacement at that point.
For System 2, the plan is to replace the liquid line filter-drier cores, perform a deep triple evacuation, and recharge to the factory-specified charge weight. Sensor accuracy will be re-verified after recharge.