This Questions & Answers document for Amendment 004 of solicitation 140G0125Q0052 addresses two key inquiries regarding the CERC A3 Single Phase Electrical Panel Upgrade project. The document clarifies power disruption requirements, stating that outages shall not exceed 24 hours per instance, with two disruptions planned: one for old disconnect removal and one for new panelboard installation, scheduled at least five business days apart.

The Q&A also addresses timeline concerns regarding the 10-day start and 14-day completion requirement specified in Box 11 of Form 1442. The response indicates that quotes should factor in material lead times, particularly for breakers and panels, which will be considered in the award timing. This electrical upgrade project at the Columbia Environmental Research Center involves replacing a 1200-amp disconnect with a new 600-volt 1200-amp distribution panel, with an estimated project value between $100,000 and $250,000.

View the file

Other files for this federal contract opportunity

Other files attached to CERC A3 Single Phase Electrical Panel Upgrade, newest first.
File Type Posted
B08_Attachment_11_Q_A_Amd_005_0005.docx DOCX document
Sol_140G0125Q0052_Amd_0005.pdf PDF
Sol_140G0125Q0052_Amd_0004.pdf PDF
Sol_140G0125Q0052_Amd_0003.pdf PDF
Sol_140G0125Q0052_Amd_0002.pdf PDF
B08_Attachment_1_SOW_Rev_1_0002.docx DOCX document
B08_Attachment_9_Q_A_Amd_002_0002.docx DOCX document
B08_Attachment_8_Q_A_Amd_001_0001.docx DOCX document
Sol_140G0125Q0052_Amd_0001.pdf PDF
B08_Attachment_6_Statement_and_Acknowledgement_of_Subcontractor_SF1413-13e.pdf PDF
B08_Attachment_1_SOW.docx DOCX document
B08_Attachment_3_WD_MO20250084.pdf PDF
Sol_140G0125Q0052.pdf PDF
B08_Attachment_2_Site_Images.docx DOCX document
B08_Attachment_5_Payroll_WH-347.pdf PDF
B08_Attachment_4_Payment_Bond_SF25A-16d.pdf PDF
B08_Attachment_7_Form_DI-137_Release_of_Claims.pdf PDF
Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

140G0125Q0052 Questions & Answers Amendment 004

1) Will a generator be required to provide temporary power during planned power outages?

i. Power disruptions shall be no more than 24 hours in a single instance with two power disruptions anticipated for this work: One disruption for the old disconnect removal and one for the installation of the new panelboard. The power disruptions will occur no less than five business days apart.

ii. Reference Amendment 002 Q&A #9.

2) Time frame on box 11 the 1442 states project is to start within 10 days and be completed within 14 days of contract award. Is this a firm date or is it flexible? Breakers and panels have lead times much longer than 14 days.

i. Your quote should include any lead times required for material and will be accounted for upon award.