Attachment_P_Questions_Responses_0004_0004.xlsx

XLSX spreadsheet 24 KB Posted

Attached to
HIF CONSTRUCTION Federal contract opportunity
Solicitation number
140G0121R0015
Issued by
Department of the Interior US Geological Survey Office of Acquisitions and Grants

About this file

This document contains questions and responses related to specifications for a federal construction contract opportunity. The opportunity involves constructing a new Hydrologic Instrumentation Facility on the campus of the University of Alabama for the Department of the Interior US Geological Survey. Key specifications covered in the questions and responses include controlled environment room conditions, sales tax exemptions, insurance requirements, permitting needs, elevator specifications, security clearance requirements, and definitions of contractor versus owner furnished equipment. Clarification is also provided on finish schedules, signage, casework, and other detailed facility aspects.

View the file

Other files for this federal contract opportunity

Other files attached to HIF CONSTRUCTION, newest first.
File Type Posted
Attachment_C_Price_Breakout_0011.xlsx XLSX spreadsheet
Sol_140G0121R0015_Amd_0011.pdf PDF
Attachment_P_Questions_Responses_0010_0010.xlsx XLSX spreadsheet
Sol_140G0121R0015_Amd_0010.pdf PDF
Attachment_T_Addendum_3_0010.pdf PDF
Attachment_U_Unit_Price_Schedule_0010.xlsx XLSX spreadsheet
Sol_140G0121R0015_Amd_0009.pdf PDF
Attachment_P_Questions_Responses_0008_0008.xlsx XLSX spreadsheet
Sol_140G0121R0015_Amd_0008.pdf PDF
Attachment_P_Questions_Responses_0007_0007.xlsx XLSX spreadsheet
Attachment_S_Addendum_2_0007.pdf PDF
Sol_140G0121R0015_Amd_0007.pdf PDF
Sol_140G0121R0015_Amd_0006.pdf PDF
Attachment_R_Addendum_1_0006.pdf PDF
Attachment_R_Addendum_1_0005.pdf PDF
Attachment_P_Questions_Responses_0005_0005.xlsx XLSX spreadsheet
Sol_140G0121R0015_Amd_0005.pdf PDF
Attachment_Q_Site_Visit_Sign-In_Sheet_0004.pdf PDF
Sol_140G0121R0015_Amd_0004.pdf PDF
Attachment_N_Interested_Parties_List_0003.xlsx XLSX spreadsheet
Attachment_O_Questions_Responses_0003_0003.docx DOCX document
Sol_140G0121R0015_Amd_0003.pdf PDF
Sol_140G0121R0015_Amd_0002.pdf PDF
Attachment_O_Questions_Responses_0002_0002.docx DOCX document
Sol_140G0121R0015_Amd_0001.pdf PDF
Attachment_N_Interested_Parties_List.xlsx XLSX spreadsheet
Attachment_M_Sample_Small_Business_Subcontracting_Plan.pdf PDF
Attachment_F_Bid_Bond_SF24.pdf PDF
Attachment_E_AL_Dept_of_Revenue_Purch_Agent_Appt_ST_PAA-1.pdf PDF
Attachment_C_Price_Breakout.xlsx XLSX spreadsheet
Attachment_B_2_Vol_2_Drawings.zip ZIP file
Sol_140G0121R0015.pdf PDF
Attachment_L_Past_Performance_Questionnaire.doc DOC document
Attachment_J_Payroll_WH-347.pdf PDF
Attachment_I_Statement_and_Acknowledgement_of_Subcontractor_SF1413.pdf PDF
Attachment_B_1_Vol_I_Drawings.zip ZIP file
Attachment_B_3_Vol_3_Drawings.zip ZIP file
Attachment_B_4_Vol_4_Drawings.zip ZIP file
Attachment_K_Release_of_Claims.pdf PDF
Attachment_H_Performance_Bond_SF25.pdf PDF
Attachment_G_Payment_Bond_SF25A.pdf PDF
Attachment_D_Wage_Decision_AL20210098.pdf PDF
Attachment_A_Specification.zip ZIP file
Show all 43

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Item No.RegardingReference Spec/ Sheet/ DetailInformation RequestedAnswer
1Project Alternates01 23 00Soliciation for bid, page 3 of 39, indicates CLNS item No. 00011 "Alternate: Natural Indiana Limestone in lieu of Cast Stone…". Project manual, specification section 01 23 00, incidates in section Part 1, 1.03, "Alternate No. 1: Audio Visual Equipment." Please indicate which alternate(s) is/are applicable and provide an updated bid form if applicable.Solicitation for bid is correct. Section 01 23 00 will be removed from specifications manual per future addendum
2Controlled Environment Room13 21 00Please specify the relative humidity conditions for the controlled environment room. The Controlled Environment Room Schedule included in section 3.6.A of the Division 132100 Specifications lists the Relative Humidity Range as “TBD.”Please disregard section 3.6 - the content was a draft paragraph that was meant to be deleted from the final version. Relative humidity performance will be outlined in secton 2.3, with additional requirements for controls and uniformity listed under section 2.6. This spec is being reviewed and will be updated via addendum in the near future. The recommendation from the basis of design manufacturer is 5% to 95% RH within a dew point range of -5C to 40C. Outside of those dew point ranges, and when internal temperature goes below freezing, the humidity will not be precisely controlled.
3Controlled Environment Room13 21 00Please provide additional details on the intended use of the controlled environment room.It will be used to calibrate temperature and humdity sensing devices
a.a. Will it be used for stress-testing equipment?The primary purpose is calibration of devices; stress testing may be a secondary function
b.b. How frequently will the temperature need to fluctuate?It needs to be able to move through full temperature range (up and down) over the course of a few hours. It's unknown how often the users will cycle it however.
c.c. Is there a Rate of Change requirement?It's not quantified, see comment above.
4Sales Tax ExemptionSol_140G0121R0015Solicitation for bid, page 35 of 39, section I.83, indicates that the project will be exempt from Alabama Sales Tax. Please confirm, the following:
a.a. Confirm that the project WILL NOT be exempt from Tuscaloosa County, AL

sales and use tax of 3%.

b. b. Confirm that the project WILL NOT be exempt from City of Tuscaloosa, AL sales and use tax of 3%.

c. c. Confirm that the project WILL be exempt from State of Alabama sales and use tax of 4%.

5Insurance ScheduleSol_140G0121R0015Solicication for bid, page 23 of 39, states regarding insurance, "The Contactor shall, at its own expense, provide and maintain during the entire performance of this contract, at least the kinds and minimum amounts of insurance required in the Schedule or elsewhere in the contract."
Please indicate where the schedule of required insurances is found in the bid documents.The kinds and amounts of insurance required is provided in clause 1452.228-70, Liability Insurance.
6Permits / Authorities having JurisdictionSol_140G0121R0015Please indicate if the project will be subject to building permits from the city and/or country of Tuscaloosa, AL.NO city building permit is required. USGS is obtaining a land development permit from the city.
7ElevatorA-402Floor plans indicate a single cab elevator near column F-2.0. No specification has been included for the elevator. Please confirm that the project includes an elevator and provide a specifiation for same.Elevator needs to comply with University of Alabama standards as indicated in "Division 14, Coneying Equipment. Will confirm if this document is available to include in the up coming update.
8Security ClearanceH6 in SF1442Please confirm Section (d) Background Investigation and (e) e-QIP as required for Federal Background Checks is only required for any personnel accessing IT or other network related systems. This is to confirm that no other security clearance is required for other personnel on the project.The background investigation and e-QIP for federal background checks is only required for contract personnel accessing Department of the Interior IT systems or DOI data.
9Unit Price Schedule00 43 22The unit price schedule in Specification 004322 is not listed as a deliverable in the proposal submission. Is this schedule to be submitted with the proposal? If so, please specify which Volume and Part.YES, please insert in Volume II, attached as the last page of Volume II Part I Section B – Supplies or Services and Prices.
10Bid PricesNAPlease confirm the bid prices from the unit price schedule are to be included in the Base Bid.Yes, bid prices in the unit price schedule are to be included in the base bid.
11Proposal SubmissionNAIs there a limitation for file size for electronic proposal submission? Do the Volumes need to be submitted separately?Each volume must be its own electronic file. The files (volumes) may be submitted in the same email.
12Quantity TakeoffNAIs a Civil CAD available to help bidders with quantity takeoff for earthwork?Signed and sealed drawings are contract documents. Contractor is responsible for quantity takeoffs.
13Project ScheduleNAWill the project schedule counts towards the 25 pages for the Management Plan?Yes
14Room 126 Finish MaterialNAThe material for the Room 126 is not listed as a finish on the legend/schedule. Please provide material selection for this room.126 removed from finish schedule. Will revise drawings accordingly.
15Fire Sprinkler Labor RateNAThere is not a labor rate listed for Fire Sprinkler Labor. Please provide a rate for this labor.
16Roof PlanA-107The Roof Plan A107 references Solar Panels on Standing Seam Metal Roof. Are these solar panels to be Contractor Furnished & Contractor Installed. If so, please provide specification section.A specification section will be provided in a future addendum
17Frame TypeNAPlease confirm that the frame type should be Hollow Metal (HM) for openings 104, 105, 106, 107All frames will be Hollow Metal (HM)
18Ceiling FinishA-701, A-800Drawing A701 calls out Ceiling C-1 at 9’-0” AFF in Rooms 122 & 123, which is a 2x2 Acoustical Ceiling. The finish schedule on A800 calls out the ceiling finish in these rooms to be PT12 which alludes to these ceiling being GYP Board. Please verify if the finish is to be ACT or Gyp Board.Vinyl ceiling tile to go in 122 and 123. Will revise finish schedule & legend accordingly.
19AP1 PanelsA-701B, A-800A800 calls out AP1 Panels in the Paint Booths (Room 150). However, on the RCP A701B AP1 Panels are not shown. Please confirm that AP1 panels should not be included in Room 150.AP1 panels should not be included in Room 150. Will revise finish plans.
20Ceiling FinishA701B, A-800A701B Calls out C-2 in Alcove 146A which is a 2x2 Metal Ceiling. However, A800 calls out AT-1 which is a 2x2 Acoustical Ceiling Tile. Please verify if the ceiling is to be a metal 2x2 tile or a ACT 2x2 tile.Ceiling to be metal 2x2. Interior Designer needs to confirm color. Will revise drawings accordingly.
21Ceiling Type AT409 51 00, Para 2.02DRefers to material as white. Finish Schedule and Color Legend A801 refers to AT4 as custom color to match PT6. Please confirm color for suspension, Axiom trim and Lyra PB panels for this ceiling type.AT4 ceiling to be painted PT6.
22Diamond Plate vs. Checker PlateS-200, Details 1, 2, 3, 4, 7, 9Details 1 & 2 on drawing S-200 indicate ¼” diamond plate. However, Details 3, 4, 7, and 9 on Drawing S-200 indicate 3/16” checker plate. Please confirm the correct size.The correct steel thickness is 1/4".
23PanelingRooms 119, 133, 137, 141, 148, 103, 202, 201, 110Please provide detailed elevation drawings for the paneling in the Break(119), QA Holding(133,137,141,148), Corridor(103), Sitting Area(202), Auditorium Seating(201), and Elevator(110) RoomsPlease see sheet A816 elevations of the paneling in break room 119, corridor 103, sitting area 202, auditorium 201
24PNL3 Metal Screen DoorA-801Under the Miscellaneous Finishes Color Legend references PNL3 metal screen door. Please provide specifications for PNL3.See sheet QL503 for description of sliding metal gate system. Finish described on A-801.
25Threshold Installation09 30 00, Para 3.03.C.3The series 800 Finish drawings indicate particular metal transition strips at each location that require porcelain floor tile. Please confirm that Method TR611 does not apply to this project.Use metal transition strips per series 800 finish drawings. Para 3.03.C.3 should read, “Thresholds: As indicated on drawings.”

Interior Paint is under 09 90 00 Painting and Coating instead of 09 91 23.

26Stair Treads09 30 00, Para 2.02.DThere are no “tile” stair treads located on the drawings. Drawing A801, Miscellaneous Finishes Color Legend indicates STRD1 (Central Stair only) and lists Dekton as the finish material. Please confirm that tile stair treads do not apply to this project.STRD1 is a custom sized tile product made for stair treads.
27Mosaic Trim Curb Bullnose09 30 00, Para 2.04.B.5There are no curbs located on the drawings. Please confirm that this does not apply to this project.There are no shower curbs in this project. Showers are fiberglass units.
28Mosaic Trim Cover Base09 30 00, Para 2.04.B.4The cove base identified on the Drawing A800 Finish Schedule and Drawing A801 Finish Schedule color legend is 6”x12” cove base, not mosaic. Please confirm that this does not apply to this project.6" x 12" cove base is used in the restrooms and at the water coolers alcoves. Cove base is not mosaic.
29Cleavage/Waterproofing Membrane09 30 00, Para 2.09.C and 3.03HThe TCNA tile installation techniques listed in Para 3.03.C lists a waterproofing membrane as “optional”. Please clarify if a waterproofing membrane is required behind ALL wall tile and UNDER all floor tile. If not, please provide the extents.
30Floor Covering Materials SV1, RS1 & RB 409 65 00, Para 2.02These items are not listed on Drawing A800 Finish Schedule, nor Drawing A801 Finish Schedule color legend. Please confirm that these items do not apply to this project.Rubber tile is referred to as static control rubber tile SD1 on the finish legend. RB4 is not in the project.
31Sealer & Wax09 65 00, Para 2.02.L
A-801Both product types listed on Drawing A801 Finish Schedule color legend (LVT 1 and 2, SD1) are not required to have a wax finish per the manufacturer. Please confirm this item can be omitted from the specs.These finishes do not require a wax finish for this type facility.
32FF&E ScheduleA-825Please confirm all these items are OFOI.Yes. All FF&E items are OFOI.
33Illustrative Surface Wallcovering09 72 16-23There is no indication of this item on the drawings. Please clarify.Correct. This is not in the project.
34Sign DetailsA-823, A-819, A-824Sheets A823 and A819 refer to room 101 having sign D1. D1 is not listed in the sign details on sheet A824 for size and or product information. Please clarify.Correct. The D1 sign type is not included in this project and will be removed from the schedule. See updated drawings.
35Hydraulic Lab Instrumentation11 53 63Are the following products Contractor Furnished and Contractor Installed or Owner Furnished and Owner Installed:

Acoustic Doppler Current Profiler(ADCP) tank and carriage Test basin, carriage and wave generator Tilting flume Tow tank carriage

If they are Contractor Furnished please provide the manufacturer and specific product (i.e. - model no., performances, etc.). Also please provide the manufacturer that was the basis of design for each product above.Contractor furnished and installed. Performance shall be per Section 11 53 63. Manufacturer model number and basis of design is not available. Equipment will be custom.
36Finish ScheduleA-800Finish Schedule Remark #5 in regards to Rooms 222-Conf and 223-Office. Both these rooms list this remark in the Remarks column, although neither room calls for hard tile. Please clarify.Remark 5 to be removed from 222 and 223 on the finish schedule. Will revise drawings accordingly.
37Finish ScheduleA-800, A-801Floor Color in Rooms 115-Comm and 116-Elec / A/V. Both these rooms list SCCS as the floor finish. SCCS is not listed on Drawing A801 Finish Legend. Please clarify.Listed on abbreviations legend below finish schedule on A800. Static Controled Concrete Sealer.
38Finish ScheduleA-800Room 110-Elev. Finish Schedule Remark #13 states to refer to Misc Int Finishes #9. Misc Int Finish #9 refers to Lab Casework. Should this state to refer to Misc Int Finish #8, and if so, please clarify the floor finish for the Elevator as the Finish Schedule lists this as Sealed Concrete, but Int Finish Note #8 states CT1.Yes. This should state to refer to misc int finish #8. Will revise drawings.
39Finish ScheduleA-800Finish Schedule Remark #6 in regards to Room 213-Admin. This rooms lists this remark in the Remarks column, although there are no hard tile finishes called for in this room. Please clarify.Remark 6 is not applicable to room 213-Admin. Will revise drawings accordingly.
40Finish ScheduleA-800, A-801AT11 Ceiling Finish. AT11 is not listed on Drawing A801 Finish Legend. Please clarify.AT3 to replace AT11 on finish schedule. Will revise drawings accordingly.
41Finish ScheduleA-800, A-101AFinish Schedule Remark #19 in regards to Room 113-Corridor Auditorium. Refer to Drawing A101A. This section appears on the north side of Room 119- Break Room. Please clarify if Remark #19 is correct as listed in the Remarks column on the Finish Schedule.Remark 19 not applicable to 113. Sheet revised accordingly.
42Time Line/Vinyl Mural in Lobby/Reception1/A-806

1&2/A-815

The elevations state to refer to FF&E package for this. Please advise if this is OFOI. If it is to be CFCI, please provide details regarding the material required here or provide an allowance for this product.Mural is OFOI.
43PNL75/A-815
A-801PNL7 is not listed on Drawing A801 Finish Legend. Please clarify.Elevation 5/815 revised to include finishes.
44Auditorium SeatingA-102A, A/A-311, D/A-311
A-801Detail D/A311 shows “Nosing with eased edge” and “Perforated metal riser”. Both these items state to See Room Finish Legend. There is no indication on Drawing A801 Finish Schedule Color Legend what these two materials are. Please provide a basis of design for both the nosing and the perforated metal riser.Auditorium nosings to match treads 3/4" solid white oak tread on 3/4" treated plywood sheathing.
45Wall Anchoring for Millwork/ Casework1/A-817

F1/A-542

This states to see Detail F1/A-542. Drawing A-542 is not in the documents. Please provide.
46Interior & Exterior Painting05 52 13, para 2.8.F.1This states to “Shop prime…with primers specified in Section 099113 ‘Exterior Painting’ and Section 099123 ‘Interior Painting’.” These specification sections were not provided in the documents. One of the specification sections is mentioned again in Para 2.8.G. Please clarify.
47Color & Pattern of Solid Core Doors08 14 00, Para 2.02.B.3This states “As identified in Structural Interior Design binder”. Further, Para 2.05-Finish lists Finished and Unfinished doors. Please provide the Structural Interior Design binder or clarify what wood doors are to be delivered pre-finished and what wood doors are to be delivered unfinished.All wood doors are to be prefinished. See finish legend for finishes. SID Interior Finishes Binder provided to Owner. The information can be found on the finish legend.
48Wall TypesG-005
09 21 16, Para 2.02.EPara 2.02.E lists Abuse-Resistant Gypsum Panels, but there is no indication on any wall type as shown on the wall type legend that requires abuse-resistant gypsum panels. Please clarify.Abuse resistant gypsum panels are required in this project.
49Seam Finishing09 72 13, Para 3.02.AThis states “Seam finishing…under Section 09 29 00 ‘Gypsum Board’. It also states “Painting…. Under Section 099123 ‘Interior Painting’.” These specification sections were not provided in the documents. Please clarify.Seam finishing should reference 09 21 16 Gypsum Board Assemblies instead of 09
50Transition Strip LegendA-802There are two items that are both listed as TS6. There is not one labeled TS4. As both TS4 and TS6 are shown on the Floor Finish Plans, please clarify which is which.Will revise drawings for clarification.
51Transition Strip TS4A-803, A-806Please provide a transition profile for these carpet to sealed concrete transitions.Added. See TS7 on A802.
52Marble Thresholds09 30 00, Para 2.05The series 800 Finish drawings indicate particular metal transition strips at each location that require porcelain floor tile. Please confirm that marble thresholds will not be required on this project.No marble thresholds in this project.
53Base for Wall Tile09 30 00, Para 2.03.B.5This paragraph states that there is no cove required. Drawing A800 Finish Schedule indicates CTB1 for wall base in the toilet rooms. Drawing A801 Finish Schedule Color Legend lists CTB1 as 6” x 12” porcelain cove base. Please clarify.Cove Base is required. Para 2.03.B.5 should read, “Cove where indicated on drawings” instead of “No cove required.”
54Shower StallsA-405, Elevations A, E, D, HThese elevations do not clearly illustrate what wall surfacing is required at the shower stalls. Drawing P-601 Plumbing Schedule lists SH-1 indicating it is only a terrazzo shower base and does not list a solid surround as the elevations suggest. Please clarify what is to be used on the wall locations at the shower stalls in Rooms 155 and 156.Provide fiber glass showers.
55Water Closet Paper Holder09 30 00, Para 2.03.C.2This states to provide a vitreous china paper holder at each water closet. Spec Section 10 28 00, Para 3.04 Accessory Schedule states the paper holder are stainless steel. Please clarify which is correct.Provide stanless steel.
56Shower Soap Holder09 30 00, Para 2.03.C.1This states to provide a vitreous china soap holder at each shower. Spec Section 10 28 00, Para 3.04 Accessory Schedule does not indicate a basis of design for this item. Please provide.Change accessories paragraph from 09 30 00 para. 2.03.C to read, “Refer to 10 28 00.” Add the following to the accessory schedule in 10 28 00 para. 3.04 Accessory – Soap Dish / Model – Bobrick B-680 and Bradley No. 900 / Quantity – As shown on drawings.
57NANASpecification Section on 011100 1.03B states “Work on Project will be executed after completion of Work of this Agreement, and which is excluded from the Agreement, as follows: Furnishing, Fixtures and Equipment.” There is a clear matrix on QL601 & QL602 showing what is CFCI, OFCI, OFOI, or VFVI for the Lab Equipment. However, there is some confusion with other items in Division 11 & 12.See items in next two rows.
a.Owner Furnished, Ownder Installed Equipment01 11 00, Para 1.03B
A-825Please confirm the following items are Owner Furnished, Owner Installed:

Div 11 Laboratory Fume Hoods Div 11 Hydraulic Lab Instrumentation Div 11 AV Systems

All Items shown on FFE & Schedule, Sheet A-825Div 11 Audio Video systems are contractor furnished, contractor installed as part of the construction contract. The fume hood in Water Prep Lab is specified under 11 53 13 and will be CFCI. There are other fume hoods listed on the equipment matrix which are mobile and will be OFCI.
b.Contractor Furnished, Constractor Installed Equipment01 11 00, Para 1.03B

A-819 A-820 A-821 A-822 A-823 A-824 Please confirm the following items are Contractor Furnished, Contractor Installed:

Div 10 Integrated Interior Assemblies (Demountable Partitions) Div 10 Mobile Storage Shelving Div 12 Roller Window Shades Div 12 Manufactured Casework Div 12 Laboratory Casework Div 12 Solid Surfacing Countertops Div 12 Quartz Agglomerate Countertops Div 12 Laboratory Accessories

All Signage Shown on Signage Drawings (A819, A820, A821, A822, A823, A824)Div 11 Audio Video systems are contractor furnished, contractor installed as part of the construction contract. Div 12 Laboratory Casework and Div 12 Laboratory Accessories Yes, CFCI.
58Sales Tax ExemptionSection I.83 of SF1442The Sales Tax exemption in section I.83 of the SF1442 and Attachment E states that it is the Owner’s Intent to make the contractor a Purchasing Agent. In this scenario, the contractor can order and receive materials for the Owner, but cannot pay for the material since the contractor is typically not a tax exempt entity. Therefore, the contractor transmits material invoices to the Owner who then pays the material invoices directly.

In our experience, sales tax is included in our proposals and then the owner realizes sales tax savings when they pay the material invoices. Please confirm that this is the intent and sales tax should be included in the proposals.

59Audio Visual Equipment01 23 00Specification Section 012300 Alternates states that Alternate No. 1 is to include the scope of work for audio-visual equipment. However, this Alternate is not listed on the SF1442. Is Alternate to be included in the Proposal?Solicitation for bid is correct. Section 01 23 00 will be removed from specifications manual per future addendum
60Natural Limestone/Cast Stone01 23 00
SF1442The SF1442 lists Alternate 0011 for Natural Limestone in lieu of Cast Stone. However, this alternate is not listed in Specification Section 012300 Alternate section. Can this Alternate be listed in the specification section?Solicitation for bid is correct. Section 01 23 00 will be removed from specifications manual per future addendum
61Wall Tile ElevationsA-803, A-404, A-405A803 calls out for CT2 & CT3 on the wall behind the water fountain outside rooms 122 & 123. However, wall tile elevations on A404 & A405 do not include this area. How tall should the wall tile be on that wall?CT2 to go to 54"H. CT3 not used behind water fountain anymore. Will revise drawings accordingly.
62Stump Removal01 11 00.01, Para 1.03ASpecification Section on 011100 1.03A states “Work on Project will be executed after completion of Work of this Agreement, and which is excluded from the Agreement, as follows: Removal of Trees on Site By Separate Contract.” Does this include removal of stumps as well?Refer to Specification 31 10 00, 3.01.
63Hardware08 71 00EX04, EX16, 102C, 135A and 159B don't have a hardware set assigned. Advise hardware required.
64HardwareThere are a few exterior hollow metal openings indicated to be “FEMA” openings per the hardware set description and hardware indicated.

EX06 – hw set 39 EX11 – hw set 38 125A – hw set 40 125B – hw set 40 154 – hw set 37

Are these the only exterior openings to be “FEMA” rated? If not, advise all openings required and the correct hardware sets required for them.

File details come from the government source that posted it. Updated .