Sol_140FGA26R0008_Amd_0001.pdf
PDF 3 MB Posted
- Attached to
- MT RED ROCK LAKES NWR HQ OFC REHAB
- Solicitation number
- 140FGA26R0008
About this file
This is Amendment 0001 to Solicitation 140FGA26R0008, issued by the Fish and Wildlife Service (FWS) under the General Services Administration (GSA) on February 25, 2026. The amendment addresses clarifications regarding contractor questions about the solicitation and does not extend the original deadline. The period of performance runs from April 1, 2026, to April 1, 2027.
The amendment provides responses to four key contractor inquiries: (1) estimated linear footage of exterior logs requiring replacement due to rot is approximately 60 linear feet, though measurements are not exact due to snow drifts; (2) contractors should price log replacement as a lump sum with a breakout of cost per linear foot to account for unknown extent of rot until extraction; (3) snow guards specified in the plan set shall be Rocky Mountain Snow Guards or an approved equivalent; and (4) the amendment includes photographs of existing site conditions showing the exterior building damage, log rot damage, boiler room equipment, mechanical systems, and related infrastructure. The document contains multiple photographs documenting representative log siding damage, failure of existing coating systems, boiler identification plates, and current mechanical room configurations to support contractor bidding and planning.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Red_Rock_Question_0001.pdf | ||
| Sol_140FGA26R0008.pdf | ||
| B08_SOW_with_drawings.pdf | ||
| B03_WD_MT20260025.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: is not is required copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7.ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
PAGESOF
Contractor
The hour and date specified for receipt of Offers to sign this document and return
Thomas Ikner
See continuation page
FWS GAOA
FWS, GAOA
5275 Leesburg Pike Falls Church VA 22041
FGA
140FGA26R0008
02/25/2026
02/25/2026
1 13
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
140FGA26R0008/0001
This Amendment is to address questions that were being asked about the solicitation. See
Attached
Period of Performance: 04/01/2026 to
04/01/2027
1. Can the purchaser please provide an estimated LF (Linear Foot) measurement of exterior logs to be replaced due to log rot?
Approximately 60 linear feet – measurements not exact due to snow drifts.
2. The extent of log rot can be unknown until extraction is performed should contractors price as a LS as on the price schedule with an optional LF price?
Staff will attempt to provide an estimated LF of damaged logs that need to be replaced. Lump sum with a break out of cost per LF.
3. Can the purchaser provide the make and manufacturer of the snow guards listed in the plan set?
Rocky Mountain Snow Guards or approved Equivalent.
4. Can the purchaser furnish as existing site photos of the exterior of the building, boiler to include model and serial number and existing mechanical room?
| Amendment of solicitation/modification of contract |
| Contract ID code |
| Amendment/modification number |
| Effective date |
| Requisition/purchase requisition number |
| Project number |
| Issued by |
| Code |
| Administered by |
| Code |
| Name and address of contractor |
| Code |
| Facility code |
| Amendment of solicitation number |
| Dated |
| Modification of contract/order number |
| Dated |
| This item only applies to amendments of solicitations |
| Accounting and appropriation data |
| This item applies only to modifications of contracts/orders. |
| This change order is issued pursuant to: |
| The above numbered contract/order is modified to reflect the administrative changes |
| This supplemental agreement is entered into pursuant to authority of: |
| Other |
| Important: |
| Description of amendment/modification |
| Name and title of signer |
| Contractor/offeror |
| Date signed |
| Name and title of contracting officer |
| Signature of Contracting Officer |
| Date signed |
| Previous edition unusable |
| Standard form 30 (rev. 11/2016) |
| Continuation sheet |
| Reference Number |
| Name of Offeror or Contractor |
| OPTIONAL FORM 336 (4-86)) |
Sponsored by GSA FAR (48 CFR) 53.110
File details come from the government source that posted it. Updated .