A21_Bid_Schedule_0002.docx
DOCX document 38 KB Posted
- Solicitation number
- 140FC326Q0033
About this file
This is a bid schedule document for a solicitation to remove and replace above-ground fuel storage tanks, pumps, and related removal actions at a Department of the Interior Fish and Wildlife Service facility. The document serves as a pricing template for contractors to submit cost proposals for the project.
The bid schedule appears designed to capture line-item pricing for discrete work elements associated with the fuel storage system replacement, including costs for equipment removal, disposal, new tank and pump installation, and associated labor and materials. Contractors responding to Solicitation Number 140FC326Q0033 would complete this schedule to propose their pricing for the various components and tasks required to execute the removal and replacement of the above-ground fuel storage infrastructure. The schedule format allows for itemized cost breakdowns, enabling the government to evaluate competitive proposals on a detailed basis for this facility upgrade project.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Central Washington NWR Complex Installation of New Above Ground Storage Fuel Tanks, Pumps and Removal Actions Page 2
Install Above Ground Fuel Storage Fuel Tanks, Pumps, and Removal Actions at Central Washington NWR Complex
| Company Name: ________________________ | Primary Contact name: _______________________ |
| Phone Number: _________________________ | Email Address: ______________________________ |
Business Address: ______________________________________________________________________________
| DUNS/UEI Number: ____________________ | Date: _____________________ | |
| Item No. | ||
| Item Description | ||
| Estimated Quantity | ||
| Unit | ||
| Unit Price | ||
| Total Cost |
| Task 01 |
| Base Bid: Conboy NWR |
Pump, Clean, Recycle and Remove Old Fuel Tank (1) 1,000-gallon split 500/500
| 1 |
| Activity Unit |
| Task 02 |
| Base Bid: Conboy NWR |
Provide and Install New Fuel Tank and Pump Accessories (1) 1,000-gallon split 500/500
| 1 |
| EA |
| Task 03 |
| Base Bid: Columbia NWR |
Pump, Clean, Recycle and Remove Old Fuel Tanks (2) 1,000-gallon and (1) 500-gallon
| 1 |
| Activity Unit |
| Task 04 |
| Base Bid: Columbia NWR |
Provide and Install New Fuel Tanks and Pump Accessories (1) 1,000-gallon split 500/500
| 1 |
| EA |
| Task 05 |
| Base Bid: Hanford Reach ALE Unit |
Pump, Clean, Recycle and Remove Old Fuel Tanks (2) 1,000-gallon split 500/500
| 1 |
| Activity Unit |
| Task 06 |
| Base Bid: Columbia and Conboy Lake NWR Drain, store and transfer fuel to new tanks |
| 1 |
| Activity Unit |
FIRM FIXED PRICE TOTAL: $_____________
PRICE SCHEDULE
ALTERNATIVE QUOTATION – ADDITIVE AND/OR DEDUCTIVE ITEMS
| Item No. |
| Item Description |
| Estimated Quantity |
| Unit |
| Unit Price |
| Total Cost |
| 07 |
| Option 1: Columbia NWR |
Pump, Clean, Recycle and Remove Used Oil Tank
| 1 |
| Activity Unit |
| 08 |
| Option 2: Conboy NWR |
Provide and Install Pre-Engineered Metal Canopy Cover Over Fuel Tank
| 1 |
| Activity Unit |
FIRM FIXED PRICE TOTAL: $_____________
EA=Each *The Contracting Officer Representative (COR) must review invoices, bills of lading, and manifests prior to submission to the IPP system. Any modification (additions) to the contract must be approved by the Contracting Officer (CO) in advance of any work being completed. The COR does not have the authority to approve any modifications unless approved by the CO. Incomplete bids will be considered non-responsive and may not be evaluated for award.
(End of Price Schedule)
File details come from the government source that posted it. Updated .