2A04_-_SOW_V5_20-027_Saratoga_NFH_Water_Treatment_Rehab_0008.pdf
PDF 128 KB Posted
- Attached to
- Saratoga NFH Water Treatment Rehabilitation - WY
- Solicitation number
- 140FC124R0001
About this file
This statement of work outlines requirements for the Saratoga NFH Water Treatment Rehabilitation project. The contractor shall provide all materials, equipment, and labor to complete the work using government-provided specifications and drawings. Key scope items include repairing CMU damage, installing monitoring sensors, replacing all piping, rehabilitating the drum filter and degassing columns by replacing the lower sealed end with a Water Spike device, maintaining the existing UV system, demolishing relevant components, general construction, and developing as-built drawings. The contracting officer representative is Michael Wandersee, and the hatchery manager is Lee Bender. This work is solicited under opportunity number 140FC124R0001 from the Department of the Interior Fish and Wildlife Service.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION C
STATEMENT OF WORK
TO
20-027 WATER TREATMENT REHAB
AT
SARATOGA NATIONAL FISH HATCHERY
I. GENERAL CONDITIONS
A. The Contractor shall provide all material, equipment, and labor required to complete the work as described in all the attached Government provided documents and changes mentioned in Section II.
II. CHANGES IN REQUIREMENTS
A. Changes to Government Furnished Documents. The referenced items have drawings numbers listed for association.
1. The A/E shall utilize all Government furnished documents to complete the project. The baseline project shall be considered the specifications package and drawing number 6R-WY-75-17-041. The items listed below are non-inclusive and the Contractor shall consider all minor changes based on this list.
2. Only work to be included in Contract (excluding Changes IIA3 below): See Specifications (1A04 – Specification Saratoga Rehab of Water Trtmt) Page number references have been removed as some were not accurate.
a. Repair CMU damage in two locations (outside corner and near degassing)
b. Monitoring, sensors, or any other mechanisms to assist in maintenance/monitoring
c. All piping replacements
d. Drum filter
e. Degassing Columns = SEE Changes in bullet 3 below.
f. Generator
g. All Relevant Demolition
h. General Construction
3. Changes
a. Lower sealed column end replacement with Water Spike
i. https://warrenwaterbroom.com/water-spike/
ii. P03
b. The existing UV system shall remain unchanged.
B. Complete final as-builts as constructed. USFWS can approve red lines if the deviation is minimal.
III. POINTS OF CONTACT
A. Hatchery Manager
1. Lee Bender (307-326-5662)
B. Contracting Officer Representative / Technical Representative
1. Michael Wandersee (303-236-4479)
END OF STATEMENT OF WORK
https://warrenwaterbroom.com/water-spike/
| A. Changes to Government Furnished Documents. The referenced items have drawings numbers listed for association. |
| 1. The A/E shall utilize all Government furnished documents to complete the project. The baseline project shall be considered the specifications package and drawing number 6R-WY-75-17-041. The items listed below are non-inclusive and the Contractor sh... |
| 2. Only work to be included in Contract (excluding Changes IIA3 below): See Specifications (1A04 – Specification Saratoga Rehab of Water Trtmt) Page number references have been removed as some were not accurate. |
| a. Repair CMU damage in two locations (outside corner and near degassing) |
| b. Monitoring, sensors, or any other mechanisms to assist in maintenance/monitoring |
| c. All piping replacements |
| d. Drum filter |
| e. Degassing Columns = SEE Changes in bullet 3 below. |
| f. Generator |
| g. All Relevant Demolition |
| h. General Construction |
| 3. Changes |
| a. Lower sealed column end replacement with Water Spike |
| i. https://warrenwaterbroom.com/water-spike/ |
| ii. P03 |
| b. The existing UV system shall remain unchanged. |
| B. Complete final as-builts as constructed. USFWS can approve red lines if the deviation is minimal. |
| A. Hatchery Manager |
| 1. Lee Bender (307-326-5662) |
| B. Contracting Officer Representative / Technical Representative |
| 1. Michael Wandersee (303-236-4479) |
| END OF STATEMENT OF WORK |
File details come from the government source that posted it. Updated .