This statement of work outlines requirements for a water treatment rehabilitation project at the Saratoga National Fish Hatchery in Wyoming. The contractor shall provide all materials, equipment, and labor to complete the work using government-provided specifications and drawings. Changes to the project include replacing a sealed column end with a Water Spike device and maintaining the existing UV system. The contractor must submit as-built drawings for approval. Points of contact include the Hatchery Manager and Contracting Officer Representative. The related federal contract opportunity is solicitation number 140FC124R0001 for the Saratoga NFH Water Treatment Rehabilitation project through the Department of the Interior Fish and Wildlife Service.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION C
STATEMENT OF WORK
TO
20-027 WATER TREATMENT REHAB
AT
SARATOGA NATIONAL FISH HATCHERY
I. GENERAL CONDITIONS
A. The Contractor shall provide all material, equipment, and labor required to complete the work as described in all the attached Government provided documents and changes mentioned in Section II.
II. CHANGES IN REQUIREMENTS
A. Changes to Government Furnished Documents. The referenced items have drawings numbers listed for association.
1. The A/E shall utilize all Government furnished documents to complete the project. The baseline project shall be considered the specifications package and drawing number 6R-WY-75-17-041. The items listed below are non-inclusive and the Contractor shall consider all minor changes based on this list.
2. Changes
a. Lower sealed column end replacement with Water Spike
i. https://warrenwaterbroom.com/water-spike/
ii. P03
b. The existing UV system shall remain unchanged.
B. Complete final as-builts as constructed. USFWS can approve red lines if the deviation is minimal.
III. POINTS OF CONTACT
A. Hatchery Manager
1. Lee Bender (307-326-5662)
B. Contracting Officer Representative / Technical Representative
1. Michael Wandersee (303-236-4479)
END OF STATEMENT OF WORK