Amend_0001_Atch_2_Redacted_Bone_Hill_Dam_Removal_0001.pdf
PDF 13 MB Posted
- Attached to
- BONE HILL NWR-DAM BREACH CONSTRUCTION Federal contract opportunity
- Solicitation number
- 140F0121R0055
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140F0121R0055_Amd_0002.pdf | ||
| Amend_0002_Atch_1_Bid_Schedule_Rev_1_20_Aug_0002.xlsx | XLSX spreadsheet | |
| Sol_140F0121R0055_Amd_0001.pdf | ||
| Amend_0001_Atch_1_Geotech_Rpt_Bone_Hill_0001.pdf | ||
| Atch_5_Bone_Hill_Dam_Breach_Bid_Schedule_Bone.xlsx | XLSX spreadsheet | |
| Atch_4_Bone_Hill_Dam_Breach_DBA_Wage_Rate.pdf | ||
| Atch_3_Bone_Hill_Dam_Breach_Submittals_21-046.pdf | ||
| Atch_1_Bone_Hill_Dam_Breach_21-046_Specifications.pdf | ||
| Atch_2_Bone_Hill_Dam_Breach_21-046_Drawings.pdf | ||
| Sol_140F0121R0055.pdf | ||
| Atch_6_Bone_Hill_Dam_Breach_Past_Perf_Quest.doc | DOC document |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bone Hill Dam Removal Design Report January 22, 2021
Page ii
BONE HILL NATIONAL WILDLIFE REFUGE
BONE HILL DAM REMOVAL
DESIGN SUMMARY REPORT
DESIGN SUBMITTAL
TABLE OF CONTENTS
TABLE OF CONTENTS ................................................................................................. ii
LIST OF TABLES ..........................................................................................................iii
LIST OF FIGURES .........................................................................................................iii
LIST OF APPENDICES .................................................................................................iii
1.0 BACKGROUND
2.0 PROJECT FEATURES
3.0 DATA COLLECTION
3.1 Geotechnical and Subsurface Evaluations
3.2 Survey
4.0 HYDRAULIC DESIGN
4.1 Inflow Hydrology
4.1.1 Drainage Basin Characteristics
4.1.2 Basin Soils and Infiltration
4.1.3 Precipitation
4.1.4 Unit Hydrograph
4.1.5 Reservoir Capacity Curve
4.1.6 Inflow Hydrology Summary
4.2 Reservoir Routing and Breach Sizing Analysis
4.3 Downstream Inundation Evaluation
4.4 Sedimentation Analysis
5.0 OTHER DESIGN CONSIDERATIONS
5.1 Permitting
5.2 Remove Existing Combined Service Spillway and Outlet Works
5.2 Riprap Sizing
5.3 Low Flow Concrete Structure
5.4 Soil Bearing and Settlement
6.0 CONSTRUCTION CONSIDERATIONS
6.1 Reservoir Control
6.2 Site Dewatering
6.3 Demolition and disposal
Page iii
6.4 Opinion of Construction Cost
7.0 REFERENCES
LIST OF TABLES
Table 1 Summary of Key Drainage Basin Parameters
Table 2 Summary of Soil and Infiltration Parameters
Table 3 100-Year Point Rainfall Depths
Table 4 Summary of Unit Hydrograph Characteristics
Table 5 Summary of Inflow Hydrology
Table 6 Summary of Reservoir Routing
Table 7 Construction Cost Opinion Bid Tab
LIST OF FIGURES
Figure 1 Basin Characteristics
Figure 2 Soil Map
Figure 3 Inundation Limits
LIST OF APPENDICES
Appendix A Design Drawings
Appendix B Specifications
Appendix C Geotechnical Investigation Report
Appendix D HEC-HMS Inputs and Results
D.1 – Basin Soils and Infiltration Rates
D.2 – Precipitation
D.3 – Unit Hydrograph Development
D.4 – Reservoir Capacity Curves
D.5 – Existing Spillway Curves
D.6 – Breach Opening Curve and Results
Appendix E Field Photos
Appendix F Environmental Review
Appendix G Riprap Sizing Calculation
Appendix H Soil Bearing and Settlement Calculation
Appendix I Construction Cost Opinion
\\Ww-Rs1\CLIENT\1700\1772\1772.38_Bonehill_Removal\7_Documents\100_Pct\Bonehilldesignreport_100pct_Jan2020.Docx
1.0 BACKGROUND
Bone Hill Dam was originally designed and constructed by the U.S. Department of
Agriculture, Biological Survey (currently U.S. Fish and Wildlife Services). The dam is owned and operated by the U.S. Fish and Wildlife Service (FWS). The dam is located in the southern part of North Dakota FWS Region 6 northeast of Jud, ND. The general vicinity of the site is shown on the Project Drawings.
The dam is a low hazard-potential earthen embankment located on a small tributary of
Bone Hill Creek that flows into the James River. The stored water is primarily used as habitat and breeding areas for migratory birds and other wildlife as part of the Bone Hill
Creek National Wildlife Refuge (NWR), which is an easement Refuge established by
Executive Order Number 8112 dated May 10, 1939. The dam has a structural height of approximately 14.3 feet and a crest length of approximately 1,750 feet with an active storage of approximately 77.5 acre-feet. At the reservoir’s normal high-water line, the reservoir has a surface area of about 11 acres.
Major repairs and improvements to Bone Hill Dam were completed in 1994 and included enlarging the reservoir pool, widening the dam crest, and installing a combined service spillway and low-level outlet works. The updated design also included a clay core and downstream toe drain system. Shortly after construction, the dam breached due to piping along the CMP pipe because of poor compaction of the embankment material around the
CMP. The structure was again reconstructed with a clay core keyed into the foundation and extended the length of the embankment.
An Intermediate SEED Inspection was completed on August 12, 2010 by URS. The dam was given an overall safety classification as “POOR” due to the erosion of the dam crest, severe headcutting of the auxiliary spillway, and backcutting of the upstream embankment around the outlet works conduit and headwall. Immediate actions to resolve these deficiencies were recommended.
Due to recent wet seasons and significant flooding in the James River basin, Bone Hill
Dam has experienced overtopping and erosion. Based on our initial site assessment completed on July 15, 2020, several dam safety issues were identified:
1. Inadequate spillway capacity;
2. Erosion of the auxiliary spillway channel;
3. Evidence of significant corrosion of the CMP outlet works conduit;
4. Evidence of significant piping and undermining around the outlet works conduit;
5. Evidence of significant erosion of the upstream embankment around the combined service spillway and outlet works; and
6. Inoperable service spillway due to bent stoplog channels.
In addition to the dam safety concerns, the property owner and FWS Refuge Manager both expressed concerns related to the downstream auxiliary spillway erosion creating a hazardous area for the cattle that graze on the property.
Due to the current condition of the dam, the FWS Region 6 Division of Engineering Office has decided to decommission the dam and construct a permanent breach within the embankment. W.W. Wheeler & Associates (Wheeler) was contracted to complete the preliminary design and engineering required by FWS to decommission the dam (FWS, 2015). This report documents the design criteria, assumptions, and calculations used to decommission the FWS Dam.
2.0 PROJECT FEATURES
The decommissioning of Bone Hill Dam will remove the dam from the FWS dam inventory, discontinue the water easement right to the dam, and abandon the existing water right.
The key project features of the removal of the dam include:
1. Excavate a trapezoidal breach along the existing dam embankment to have a bottom with of 50-feet, side slopes of 5 Horizontal (H) : 1 Vertical (V).
2. Remove the existing combined service spillway and outlet works structure.
3. The downstream breach opening and discharge channel will have a longitudinal slope of approximately 1-percent.
4. The upstream breach section will be sloped at a 3H: 1V.
5. A concrete low-water crossing will be installed in the breach to allow the property owner access across the breached section.
6. Armor the downstream breach opening with median rock size (D50) of 1-foot to protect the embankment from long-term erosion and head cutting of the embankment soils.
7. Place the excavated embankment fill into the auxiliary spillway to flatten the steep slopes and eliminate the hazard for the cattle.
8. Place the excavated embankment fill to backfill the foundation of the proposed breach where the outlet works CMP was removed.
3.0 DATA COLLECTION
3.1 GEOTECHNICAL AND SUBSURFACE EVALUATIONS
Four test borings 20 feet deep were located along the existing dam embankment near the low-level outlet works. The borings were performed by Terracon Consultants (Terracon) in July 2020 as part of a subsurface exploration and laboratory testing program. The location of the borings and a summary of the testing results are provided in Appendix C.
The embankment material identified in the borings generally consists of a clayey sand
(SC) and sandy clay (CL). A buried layer of topsoil was observed in the first two borings which probably represents the old dam crest prior to the enlargement in 1994. The material observed in general has the following characteristics:
Description Clayey Sand (SC) and Lean Clay (CL) Liquid Limit 38 – 40% Plastic Limit 17% Plasticity Index 21 – 23%
% Passing -200 Sieve 15 - 62%
3.2 SURVEY
Topographic data of the project site and downstream hazards was obtained from two different sources:
• Holly Beck Surveying & Engineering completed a land survey of the dam crest
(Holly Beck, 2020), combined service spillway and outlet works inverts and dimensions, cross-sections of the auxiliary spillway extending from the dam crest to the downstream culvert at 75th Avenue and the invert and dimensions of the culvert at 75th Avenue. The survey data was provided in North Dakota State
Plane North American Datum of 83 (NAD83) Coordinates using North American
Vertical Datum of 88 (NAVD88).
• 1.4-meter Statewide LiDAR derived elevation data obtained from the North
Dakota GIS Hub acquired by USACE St. Louis District (USACE, 2010). The
LiDAR elevation uses NAVD88 and was flown in 2010.
4.0 HYDRAULIC DESIGN
4.1 INFLOW HYDROLOGY
A comprehensive hydrologic rainfall-runoff computer simulation model of the contributing basin to Bone Hill Dam was developed with U.S. Army Corps of Engineers (USACE)
Hydrologic Modeling System (HEC-HMS) Version 4.2.1 software (USACE, 2017) to estimate runoff from a 100-year recurrence interval precipitation event during a 24-hour duration storm occurring over the basin. Discharges from the Bone Hill Dam basin were routed through the existing Bone Hill Reservoir and designed breach. Pertinent HEC HMS input and output data is provided in Appendix D. Key steps in the development of this inflow included:
1. Determine drainage characteristics for the basin;
2. Develop the 100-year recurrence interval precipitation data, including the depth vs. duration relationship and temporal distribution;
3. Create a reservoir capacity curve; and
4. Develop a synthetic unit hydrograph to simulate the transformation of rainfall to runoff in the drainage basin.
4.1.1 Drainage Basin Characteristics
The boundary for the drainage basin contributing runoff to Bone Hill Dam was developed using the North Dakota Statewide LiDAR data (USACE, 2010). Figure
No. 1 shows the basin and basin parameters used to model the hydrologic response. Table No. 1 summarizes the key drainage basin parameters including area, calculated longest flow path, longest flow path from centroid, change in elevation from the basin maximum elevation to sub-basin minimum elevation and average basin slope that was calculated in ArcGIS (ESRI, 2018).
Table No. 1 – Summary of Key Drainage Basin Parameters
Dam Name Bone Hill Dam
Drainage Area (sq. miles) 7.02
Longest Flowpath, L (miles) 5.634
Longest Flowpath to Centroid, Lca (miles) 2.880
Slope of Longest Flowpath, S (feet / mile) 32.83
Basin Maximum Elevation, (feet) 1841
Sub-Basin Minimum Elevation, (feet) 1639
4.1.2 Basin Soils and Infiltration
The soil characteristics for the basin were obtained from the United States
Department Agriculture (USDA) National Resources Conservation Service
(NRCS). The NRCS soils data indicated that on-site soils consist of a mixture of sands, silts and clays (NRCS, 2020). The NRCS soils data also indicated the dominant hydrologic soil group for each soil type identified. Within the basin, soil types B, C and D were present. These soil groupings were used to determine recommended infiltration rate for each soil type following U.S. Bureau of
Reclamation guidelines (USBR, 1989). Once infiltration rates were determined, a weighted average infiltration rate was calculated for the basin. The average infiltration rate and percent imperviousness of the basin are summarized in Table
No. 2. A soil map for the basin is provided on Figure 2, and infiltration calculations are provided in Appendix D1.
Table No. 2 – Summary of Soil and Infiltration Parameters
Weighted Average Infiltration (inch/hour) 0.21
Percent Impervious (%) 0.80
4.1.3 Precipitation
The 100-year, 24-hour precipitation for the basin was estimated following procedures documented in National Oceanic and Atmospheric Administration
(NOAA) Atlas 14, Volume 8, Version 2.0 (DOC, 2013). The 100-year, 24-hour precipitation depth versus duration values for Bone Hill basin are provided in Table
No. 3. Detailed calculations for the areal reduction and temporal distribution of the
100-year precipitation depth-duration values are documented in Appendix D2.
Table No. 3 – 100-Year Point Rainfall Depths
5-min 15-min 1-Hr 2-Hr 3-Hr 6-Hr 12-Hr 24-Hr
(inches) (inches) (inches) (inches) (inches) (inches) (inches) (inches)
0.997 1.78 3.12 3.79 4.16 4.74 5.24 5.67 Runoff model used 100-yr rainfall applied using 1st Quartile, 50% Probability of Occurrence temporal distribution.
4.1.4 Unit Hydrograph
The unit hydrograph was developed for the basin using the dimensionless unit hydrograph technique as documented in Chapter 4 of the USBR Flood Hydrology
Manual (USBR, 1989). Detailed unit hydrograph calculations are provided in
Appendix D3. The USBR unit hydrograph procedure is based on the observation that unit hydrograph lag time is a function of measurable basin parameters. For the dimensionless unit hydrograph, the lag time is defined as the time from the center of unit rainfall excess to the time at which 50 percent of the runoff has passed the concentration point. The following equation was used to determine the lag time for each basin:
Lg= Ct (L Lca / S0.5)0.33 where:
Lg = Lag time (hours);
Ct = a constant equal to (26 * Kn);
L = length of the longest watercourse (miles);
Lca = length along the longest watercourse from the point of interest to a point opposite the centroid of the basin, (miles); and
S = overall slope of the longest watercourse from the point of concentration to the drainage basin divide, (feet / mile).
Ct values are approximated as 26 times Kn, where Kn is estimated as the average
Manning’s roughness value for the principal watercourse in the drainage basin.
The Kn value was selected based on review of similar drainage basins in the region as documented in Table No. 4.3 of the USBR Flood Hydrology Manual (USBR, 1989). Kn values for the Great Plains area (Type 4) range between 0.03 and
0.076; the value selected, 0.036, was considered appropriate for the development of reasonable lag times in the basin. Kn along with associated Ct and lag time (Lg) values used for the basin are summarized in Table No. 5.
Table No. 4 – Summary of Unit Hydrograph Characteristics
Kn 0.036
Ct 0.936
Lag Time, Lg (hours) 1.3
4.1.5 Reservoir Capacity Curve
Documentation of the development of the reservoir storage versus capacity relationship used in the HEC-HMS hydrologic reservoir routing model is provided in Appendix D4. The reservoir capacity was calculated based on the best available topographic information including the LiDAR data and survey data.
4.1.6 Inflow Hydrology Summary
Wheeler used the HEC-HMS model to simulate the runoff associated with the 100-year precipitation event and route the inflow through Bone Hill Dam and breach to determine if the proposed breach dimensions met the criteria for decommissioning low hazard FWS dams. The HEC HMS model was developed using the basin, reservoir and rainfall characteristics described in Sections 4.1.1 through 4.1.5.
Peak runoff results of the 100-year storm from the HEC-HMS model are summarized in Table No. 6.
Table No. 5 – Summary of Inflow Hydrology
Parameter 100-year, 24-hour Frequency Storm
Peak Inflow (cfs) 2,763
Inflow Volume (acre-feet) 1,173
4.2 RESERVOIR ROUTING AND BREACH SIZING ANALYSIS
The HEC-HMS model and inflows described in Section 4.0 were used to design the proposed breach dimensions at Bone Hill Dam. The breach dimensions were evaluated in accordance with FWS’s guidance for decommissioning low hazard dams (FWS, 2015).
According to the FWS guidance, the size of the breach should be sufficient to pass the
100-year flood peak discharge (assuming no initial reservoir storage) with a maximum reservoir depth of six feet and the breach width should not be less than the bottom width of the original natural channel at the dam site.
Observations made during the 2020 site visit indicated a smaller meandering low-flow channel downstream of the existing low-level outlet works. The elevation at the downstream toe of the dam is approximately 5-feet higher than the invert of the outlet works and has a longitudinal slope of approximately 1-percent. A large group of woody vegetation is located approximately 10 feet downstream of the outlet works where the low-flow channel meanders to the right around the vegetation before it continues downstream.
Pictures of the downstream channel, dam embankment and downstream toe are provided in Appendix E.
Aerial imagery, survey elevations and LiDAR data were used to estimate the natural channel width and slope. The downstream natural ground is both wide and flat, forming a slough feature that drains water from the reservoir into a downstream network of braided channels. The design drawings provided in Appendix A provides an illustration of the existing dam and proposed breach location, a profile and a cross-section of the breach.
Three scenarios were developed to route the 100-year storm as described below:
1. Basin Model ‘100yr’ = Estimated the 100-year inflow design storm only (no reservoir routing).
2. Basin Model ‘100yr w Res’ = Estimated the 100-year inflow design storm with existing reservoir routing. Assumed an initial reservoir elevation as the maximum normal pool El. 1639 as documented in the Pertinent Data and modeled two spillway curves as documented in Appendix D5.
3. Basin Model ‘100yr Breach’ = Estimated the 100-year inflow design storm with the breached reservoir routing. Assumed an initial reservoir elevation as the proposed breach invert El at 1635.15 and a breach opening curve documented in
Appendix D6.
The 100-year reservoir routing results through Bone Hill Lake are summarized in Table 6.
The proposed 50-foot breach resulted in a depth of 4.95 feet, which is less than 6 feet;
therefore, this breach was used for the final design.
Table No. 6 – Summary of Reservoir Routing
Parameter Existing
Basin Model ‘100yr w Res’
Proposed Basin Model
‘100yr Breach’
Peak Discharge (cfs) 2,762 2,754
Maximum Water Surface Elevation
1642.5 1640.1
Reservoir Depth above proposed breach invert of 1635.15 (ft)
7.35 4.95
4.3 DOWNSTREAM INUNDATION EVALUATION
As part of the FWS decommissioning guidance, Wheeler developed a downstream inundation model of Bone Hill Lake to demonstrate that no downstream structures are adversely impacted during the 100-year inflow design flood of Bone Hill Dam. To assess the downstream structures, Wheeler developed a two-dimensional (2D) HEC-RAS unsteady flow model for channel and overland routing downstream of Bone Hill Dam. The model was setup with 50- by 50-foot grids that extend from Bone Hill Dam to downstream of Nortonville, ND. The 2D grids extract elevations from a 1-meter digital elevation model that was derived from LiDAR data and survey data described in Section 3. Three different scenarios were modeled as described below:
1. Existing Conditions – routing the 100-year design storm through the existing dam features;
2. Existing Conditions pre dam – routing the 100-year design storm as if no dam existed at that location; and
3. Proposed Conditions – routing the 100-year design storm through the proposed breach.
Two modified terrains were developed for the project using features available through
HEC-RAS. The first terrain was modified to match the proposed breach and this terrain was used for the Proposed Conditions model. The second terrain was modified to interpolate the terrain between the natural ground upstream of the dam and downstream of the dam to simulate natural conditions without the dam. This terrain was used for the existing conditions pre-dam model. The original terrain developed from the LiDAR data was used for the Existing Conditions model.
Inflow hydrographs for the three scenarios were optioned from the HEC-HMS model described in Section 4.1 and 4.2. The model was terminated downstream of the Town of
Nortonville because no more structures were identified as potentially impacted. The
“Diffusion Wave” set of simplified Saint Venant equations were used to run the 2D water surface profile model with a computational timestep of five seconds. These equations were judged appropriate because no dramatic increases and decreases in the flow hydrographs are expected and the terrain is flat.
Two-dimensional surface roughness was added to the 2D HEC-RAS model based on manning’s roughness of the National Land Cover Database (USGS, 2016). The manning’s values applied to the land use were obtained from Colorado Rules and Regulations (DWR, 2020). The following 2D roughness values were incorporated in the model as follows:
• Main channel, vegetation – 0.05
• Emergent wetlands – 0.075
• Woody wetlands – 0.095
• Cultivated crops – 0.047
• Pasture – 0.04
• Grasslands – 0.037
• Shrubs – 0.082
• Deciduous forest – 0.115
• Developed area, high intensity – 0.147
• Developed area, medium intensity – 0.104
• Developed area, low intensity – 0.095
• Developed – 0.046
• Open water – 0.032
A bridge structure was added to the 2D flow area at the closest downstream crossing, 75th
Avenue Southeast. A breakline was added along the center of the road for the other crossings as a conservative approach; however, this did not result in any of the structures within the Town being adversely impacted by the proposed breach during the 100-year design storm. The culvert dimensions were measured by Wheeler with a hand-level and tape during the July 2020 site visit to Bone Hill Dam. The results of the downstream inundation evaluation for the three different scenarios are shown on Figure No. 3. Based on the inundation limits, no adverse impacts are expected at Bone Hill Dam after the dam is decommissioned.
4.4 SEDIMENTATION ANALYSIS
The breach of Bone Hill Dam has been designed with a small permanent dead reservoir pool that will simultaneously act as a sedimentation trap. This sedimentation trap is designed to reduce sedimentation moving downstream during smaller, more frequent storms. The approximate 3-foot-deep reservoir pool was included in the design to maintain a historical water source for the landowner’s cattle as well as function as a sediment basin.
5.0 OTHER DESIGN CONSIDERATIONS
5.1 PERMITTING
ERO resources completed an environmental review of the permitting requirements and process required for the removal of Bone Hill Dam. The complete report is provided in
Appendix F. Based on their assessment, Bone Hill Dam would need to be permitted under the following regulations:
• National Environmental Policy Act (NEPA);
• U.S. Army Corps of Engineers’ (USACE) Section 404 of the Clean Water Act
(CWA);
• U.S. Fish and Wildlife Service (USFWS) Section 7 of Endangered Species Act
(ESA) and Biological Assessment;
• State Historic Preservation Officer (SHPO); and
• Migratory Bird Treaty Act (MBTA).
USFWS and ERO are working together to determine the level and types of permits required for Bone Hill Dam. Preliminary determinations and conclusions regarding the permits listed above are summarized below:
1. NEPA – A categorical exclusion was selected because the anticipated environmental effects are not expected to be significant.
2. USACE 404 – A Nationwide 27 permit is required and has been obtained for this project.
3. USFWS Section 7 – Based on ERO site visit and USFWS Refuge Manager, the project would likely have no effect on any threatened or endangered species;
however, no official determination has been provided.
4. SHPO - USFWS Refuge Manager has started the process to obtain the SHPO permit required for the project.
5. MBTA – This permit is triggered if an active nest is present during construction, but this permit can be avoided if construction occurs outside of active breeding season between March and August.
5.2 REMOVE EXISTING COMBINED SERVICE SPILLWAY AND OUTLET WORKS
The removal of the existing combined service spillway and outlet works is shown on the design drawings provided in Appendix A. As discussed in Section 1, during the field visit in July 2020, significant piping and erosion was observed in the upstream and downstream embankment near the outlet works 36-inch CMP. Additionally, the CMP was completely corroded in several locations. Pictures of the erosion and corroded CMP are provided in
Appendix E. Wheeler designed the breach to encompass the existing combined service spillway and outlet works. Wheeler also designed for an additional 2-feet of excavation below the breach crest to remove any loose sand or gravel that was placed and contributed to the existing seepage.
5.2 RIPRAP SIZING
Two different types of armoring are used in the decommissioning design of Bone Hill
Dam. As noted in the field visit, existing gabion erosion nets were previously used in the auxiliary spillway to prevent channel erosion. The gabion rocks have an approximate D50 of about 6-inches. The current gabion baskets are no longer effective after several larger storm events have displaced them within the downstream auxiliary channel. Wheeler’s design will use these gabion rocks as additional erosion protection downstream of the breach. The gabion rocks will be spread along the downstream breach over some geotextile matting to prevent scour and backcutting during larger storm events. Riprap will be installed upstream and downstream of the low water crossing. Appendix G provides detailed riprap sizing calculations using depths and velocities obtained from the
HEC-RAS model described in Section 4.3. Based on those calculations, Wheeler designed a Grade I riprap with a D50 equals 12-inches.
5.3 LOW FLOW CONCRETE STRUCTURE
A concrete low-water crossing will be installed through the breach to allow for vehicle access across the property. Concrete designs conform to the applicable requirements of
ACI 318-11 and ACI 350. Key parameters used in the design are:
1. Design compressive strength of concrete: 3,500 psi @ 28 days
2. Design yield strength of reinforcing bars: 60,000 psi
3. Minimum concrete cover over reinforcing bars: 3 inches
4. Unit weight of soil: 130 pcf
5. Soil friction angle (Φ): 30°
6. Soil pressure coefficient (Ko, “at-rest” pressure): 0.50
7. Unit weight of water: 62.4 pcf
The reinforcing steel design for the low water crossing was based on providing minimum temperature and shrinkage reinforcing steel in the structures to minimize cracking.
5.4 SOIL BEARING AND SETTLEMENT
Wheeler analyzed the low water crossing structure for the bearing capacity and settlement using a recommended traffic surcharge of 250 pound per square feet (psf). The factor of safety against bearing capacity was calculated to be greater than 3. Total settlement was calculated to be less than 0.3 inches. Bearing capacity and settlement analyses for the planned low water crossing are provided in Appendix H. Based on these analyses the planned structure meets the bearing capacity and settlement requirements.
6.0 CONSTRUCTION CONSIDERATIONS
6.1 RESERVOIR CONTROL
The level of reservoir control for this project will be decided by the selected Contractor.
The dam is located on an off-line channel and due to the dam deficiencies, the dam can no longer store water. The water surface elevation at the time of construction is expected to be around El. 1633 or lower, similar to the elevation at the time of the July 2020 site visit. The timing of the construction is anticipated to be late fall after the rainy season and before winter. The contractor can choose to either submit a reservoir control plan or watch the daily weather and plan construction activities accordingly.
6.2 SITE DEWATERING
Bone Hill Dam is expected to be drained naturally prior to construction because of the current erosion issues along the outlet works, the dam can no longer hold water. However, localized groundwater conditions and natural springs could cause localized groundwater issues during construction. Groundwater during construction is expected to be controlled by isolated sumps and pumps.
6.3 DEMOLITION AND DISPOSAL
The existing CMP headwall and outlet conduit, as well as unsuitable embankment material will be excavated and disposed off-site. Suitable excavated material from the dam embankment will be placed in the auxiliary spillway erosion areas as shown on the drawings.
7.0 REFERENCES
1. American Concrete Institute (ACI, 2006) ACI 350-06, Code Requirements for
Environmental Engineering Concrete Structures, 2006.
2. American Society of Civil Engineers (ASCE, 2007) Minimum Design Loads for
Buildings and Other Structures, 2007.
3. Geographic Information System Company (ESRI, 2018) ArcGIS Desktop Version
10.7.
4. Holly Beck Surveying & Engineering (Holly Survey, 2020), Land Survey, July 2020.
5. Natural Resources Conservation Services (NRCS, 2020), Web Soil Survey LaMoure
County, North Dakota, July 7, 2020, website:
https://websoilsurvey.sc.egov.usda.gov/App/HomePage.htm
6. U.S. Army Corps of Engineers (USACE, 2017) HEC-HMS Hydrology Modeling
System Version 4.2.1, March 2017.
7. U.S. Army Corps of Engineers St. Louis District (USACE, 2010), 1.4-meter Statewide
LiDAR North Dakota GIS Hub, Flown 2010 and 2011, website: https://lidar.swc.nd.gov/
8. U.S. Fish and Wildlife Service, (FWS, 2015), Guidance for Decommissioning U.S. Fish and Wildlife Service Low Hazard Dams, October 2015.
9. U.S. Fish and Wildlife Service, (FWS, 2010), Intermediate SEED Inspection Report
Bone Hill Dam, Prepared by URS Group, Inc., January 28, 2011.
10. U.S. Geological Survey (USGS, 2020), StreamStats Version 4.4.0, website:
https://streamstats.usgs.gov/ss/
11. U.S. Geological Survey (USGS, 2016), National Land Cover Database 2016, website: https://www.usgs.gov/centers/eros/science/national-land-cover-database?qt-science_center_objects=0#qt-science_center_objects
12. U.S. Bureau of Reclamation (USBR, 1989) Flood Hydrology Manual, First Edition
1989, Prepared by Arthur Cudworth Jr.
13. Terracon Consultants (Terracon, 2020), Geotechnical Exploration Report, July 2020.
https://websoilsurvey.sc.egov.usda.gov/App/HomePage.htm https://lidar.swc.nd.gov/ https://streamstats.usgs.gov/ss/ https://www.usgs.gov/centers/eros/science/national-land-cover-database?qt-science_center_objects=0#qt-science_center_objects https://www.usgs.gov/centers/eros/science/national-land-cover-database?qt-science_center_objects=0#qt-science_center_objects
Centroid
Bone Hill Dam
Longest Flow Path / Longest Flow Path from Centroid
Watershed (7.02 sq miles)
0 4,000 8,000 Feet Job No. 1772.38
Bone Hill National Wildlife Refuge Bone Hill Dam Removal
Basin CharacteristicsSE
PT
EM
BE
R
20BONE HILL
NATIONAL
WILDLIFE
REFUGE
FIGURE 1
Bone Hill Dam
0 4,000 8,000 Feet
Soil Group B B/D C C/D D Water
Job No. 1772.38
Bone Hill National Wildlife Refuge Bone Hill Dam Removal
Soil MapSE
PT
EM
BE
R
20BONE HILL
NATIONAL
WILDLIFE
REFUGE
FIGURE 2
Bone Hill Dam th Av e S E
2nd St th
Av e S
E
60th St SE th
Av e S
E th
Av e S
E
58th St SE th
Av e S
E
60th St SE
6th Ave th
Av e S
E th
Av e S
E th
Av e S
E
59th St SE
76th Ave SE th
Av e S
E th
Av e S
E
58th St SE st
Av e S
E
57th St SE
0 2,400 4,800
Feet
FWS Boundary Inundation Limits w/Existing Dam Inundation Limits w/50ft Breach Inundation Limits w/o a Dam
Job No. 1772.38
Bone Hill National Wildlife Refuge Bone Hill Dam Removal
Inundation LimitsJA
NU
AR
Y 2
BONE HILL NATIONAL
WILDLIFE REFUGE
FIGURE 3
2nd St
3rd Av e
59th St SE
5th Av e79 th
Av e S
E th
Av e S
E
0 1,500 3,000Feet
Appendix A Design Drawings
© 2020 Microsoft Corporation © 2020 Maxar ©CNES (2020) Distribution Airbus DS
BONE HILL CREEK NATIONAL
WILDLIFE REFUGE
BONE HILL CREEK NATIONAL
WILDLIFE REFUGE
REFUGE BOUNDARY
BONE HILL DAM
BISMARK
EDGLEY
BONE HILL
CREEK LAKE
0 200 500 1000 1500 Scale in Feet
LOCATION MAP
STATE MAP
(N.T.S.)
FISH AND WILDLIFE SERVICE
UNITED STATES DEPARTMENT OF THE INTERIOR
REGION 6 ENGINEERING - DENVER, COLORADO
DESIGNED:
DATE:
DRAWN:
DRAWING NO. SHEET 1 OF
CHECKED:
VICINITY MAP
NO SCALE
APPROVAL SIGNATURES
ANY PRINT ACCOMPANYING THIS INVITATION TO BID MAY BE A REDUCED
REPRODUCTION OF THE WORKING DRAWINGS. IF LINE BELOW DOES NOT
MEASURE SIX INCHES IN LENGTH, THE INDICATED SCALES ARE TO BE
ADJUSTED ACCORDINGLY.
NOTE TO BIDDERS:
REGIONAL ENGINEER
ASS'T. REGIONAL DIR.
DATE
PROGRAM SUPERVISOR
FACILITIES
SAFETY/IND HYGIENIST
CULTURAL RESOURCES
DATE
DATE
DATE
DATE
DATE
BONE HILL CREEK
NATIONAL WILDLIFE REFUGE
LAMORE COUNTY NORTH DAKOTA
BONE HILL DAM REMOVAL
LOCATION MAPS AND
DRAWING INDEX
CBM SAA JJT
01/22/2021 5
BONE HILL CREEK
BONE HILL DAM REMOVAL
REFUGE BOUNDARY
R:
\1
0\
\1
2.
_B on eH ill_
Re m ov al
\9 _D ra w in gs
\C
AD
F ile s\
IF
C\ Sh ee tF ile s\
-0
-0
8-
3:
pm
S co tt X
RE
FS
: J
JT
_s ta m p
JJ
T_ sig
DRAWING INDEX
SHEET
NUMBER SHEET TITLE
1 LOCATION MAPS AND DRAWING INDEX
2 ABBREVIATIONS, LEGEND, AND SITE ACCESS
3 EXISTING PLAN AND SECTION
4 GENERAL PLAN OF MODIFICATIONS
5 BREACH PLAN, PROFILE, AND CROSS-SECTION
FARGO
JO
HN
JO
SEPH TREACY
III
CO
LO
RADO L CENSED
I
PROFESSIONAL ENGINE
ER
47781
2/8/2021
AutoCAD SHX Text
OR
AutoCAD SHX Text
RI
AutoCAD SHX Text
ME
AutoCAD SHX Text
RT
AutoCAD SHX Text
PA
AutoCAD SHX Text
DE
AutoCAD SHX Text F
AutoCAD SHX Text O
AutoCAD SHX Text
NT
AutoCAD SHX Text
TE
AutoCAD SHX Text
IN
AutoCAD SHX Text E
AutoCAD SHX Text
TH
AutoCAD SHX Text
FISH AND WILDLIFE
AutoCAD SHX Text
SERVICE
AutoCAD SHX Text U.S.
AutoCAD SHX Text
U.S. FISH & WILDLIFE SERVICE
AutoCAD SHX Text
SERVICE
AutoCAD SHX Text
FISH AND WILDLIFE
AutoCAD SHX Text
TH
AutoCAD SHX Text
ME
AutoCAD SHX Text
RT
AutoCAD SHX Text
PA
AutoCAD SHX Text
DE
AutoCAD SHX Text
NT
AutoCAD SHX Text F
AutoCAD SHX Text O
AutoCAD SHX Text
OR
AutoCAD SHX Text
RI
AutoCAD SHX Text
TE
AutoCAD SHX Text
IN
AutoCAD SHX Text E
AutoCAD SHX Text U.S.
-13+33
-13+00
-12+00
-1 1+
-1 0+
00-9+00
-8+00
-7+00
-6+ 00-5
+0 0-4
+0
-3+00
-2+00
-1+000+
1+00
2+00
3+00
4+00
5+00
0 100 200 400 600 Scale in Feet
BONE HILL DAM
BONE HILL
CREEK LAKE
ACCESS ROAD
59TH STREET SE
LOCKED GATE
LOCKED GATE
TH
A
VE
NU
E
SE
S2
A S2
INDICATES CROSS SECTION LOCATION. "A"
REFERS TO CROSS SECTION DESIGNATION. THE
NUMBER "S2" REFERS TO THE SHEET NUMBER
WHERE THE SECTION IS SHOWN.
INDICATES DETAIL LOCATION. THE NUMBER 6
REFERS TO THE DETAIL DESIGNATION. THE
NUMBER S2 REFERS TO THE SHEET NUMBER
WHERE THE DETAIL IS SHOWN.
CENTERLINE
MAJOR 5 FT CONTOUR INTERVAL
WITH ELEVATION IN FEET
MINOR 1 FT CONTOUR INTERVAL
NEW CONCRETE
EXISTING
CONCRETE
NATURAL GROUND
FILTER SAND
STEEL
EMBANKMENT
BACKFILL
SELECT FILL
NORTH ARROW
CONTROL
POINT/MONUMENT
BEDROCK
CUT SLOPE
FILL SLOPE
STRUCTURAL
SLOPE
LEGEND
PROPERTY BOUNDARY
APPROX. WATER OR WETLANDS LIMITS
DRAIN GRAVEL
RIPRAP
BACKFILL
CONCRETE
GROUT
BASECOURSE
A.B. = ANCHOR BOLT
ACB = ARTICULATED CONCRETE BLOCKS
ADDL = ADDITIONAL
APPROX. = APPROXIMATELY
B.O.H. = BOTTOM OF HOLE
BF = BOTTOM FACE
BL = BOTTOM LAYER
BM = BENCHMARK
BR = BOTTOM ROW
BTWN = BETWEEN
CFS = CUBIC FEET PER SECOND
CI - CAST IRON
CJ = CONSTRUCTION JOINT
CLR. = CLEAR
CMP = CORRUGATED METAL PIPE
CMU = CONCRETE MASONRY UNIT
CONC. = CONCRETE
CP = CONTROL POINT
CRJ = CONTROL JOINT
CTJ = CONTRACTION JOINT
CTR. = CENTER OR CENTERS
℄ = CENTERLINE
D = NORMAL DIAMETER OF
DI = DUCTILE IRON
DIPS = DUCTILE IRON PIPE SIZE
DR = DIMENSION RATIO
D/S = DOWNSTREAM
db = NOMINAL DIAMETER
DIA. = DIAMETER
DEMO = DEMOLISH
DET. = DETAIL
DIAG. = DIAGONAL
DWG. = DRAWING
DWL. = DOWEL
E. = EASTING
EA. = EACH
EC = EACH CORNER LENGTHS OF BARS
EF = EACH FACE
EJ = EXPANSION JOINT
EL = ELEVATION (IN FEET)
ELL = HDPE ELBOW
EMBED = EMBEDDED/EMBEDMENT
EQ. SPC. = EQUALLY SPACED OR EQUAL
SPACES
ER = EACH ROW
ES = EACH SIDE
EW = EACH WAY
EXIST = EXISTING
F.G. = FINAL GRADE
FF = FAR FACE
EL. = FINISH
FLG = FLANGE
FR = FAR ROW
FS = FAR SIDE REINFORCING BAR
FTG. = FOOTING
GA = GAUGE
GALV. = GALVANIZED
GR. = GRADE
GRP = GLASSFIBER REINFORCED PLASTICS
H = HORIZONTAL
HDPE = HIGH DENSITY POLYETHYLENE
H.R. = HAND RAIL
HK. = HOOK
HSS = HOLLOW STRUCTURAL SECTION
I.D. = INSIDE DIAMETER
IF = INSIDE FACE
INV. = INVERT
IR = INSIDE ROW
Ld = DEVELOPMENT LENGTH
LCD = LEFT CHIMNEY DRAIN
LLV = LONG LEG VERTICAL
LOD = LEFT OUTLET DRAIN
LTD = LEFT TOE DRAIN
MAX. = MAXIMUM
MFR. = MANUFACTURER
MIN. = MINIMUM
MJ = MECHANICAL JOINT
ML = MIDDLE LAYER
MP = MONITORING POINT
MR = MIDDLE ROW
N. = NORTHING OR NORTH
NO. = NUMBER
NAVD = NORTH AMERICAN VERTICAL DATUM
NGVD = NATIONAL GEODETIC VERTICAL
DATUM
NHWL = NORMAL HIGH WATER LINE
N.T.S. = NOT TO SCALE
NF = NEAR FACE
NR = NEAR ROW EQ.
NS = NEAR SIDE
O.C. = ON CENTER
O.D. = OUTSIDE DIAMETER
O.H.P. = OVER HEAD POWER
OF = OUTSIDE FACE
OPP = OPPOSITE
OR = OUTSIDE ROW
PC = POINT OF CURVATURE
P.D. = PLAIN DOWELS
P.I. = POINT OF INTERSECTION
P.R.C. = POINT OF REVERSE CURVATURE
PT = POINT OF TANGENCY
PE = PLAIN END
⅊ = PLATE
PLCS = PLACES
PROJ = PROJECTION
PVC = POLY VINYL CHLORIDE
R = RADIUS
RCD = RIGHT CHIMNEY DRAIN
REQD = REQUIRED
REINF. = REINFORCEMENT
ROD = RIGHT OUTLET DRAIN
RSP = RIVETED STEEL PIPE
RTD = RIGHT TOE DRAIN
S = SLOPE
SCH. = SCHEDULE
SDR = STANDARD DIMENSION RATIO
SECT. = SECTION
SEO = COLORADO DIVISION OF WATER
RESOURCES, OFFICE OF THE STATE
ENGINEER
SIM. = SIMILAR
SPC. = SPACE OR SPACES
SPY. = SPILLWAY
SQ. = SQUARE
SS = STAINLESS STEEL
STA. = STATION
STD = STANDARD
STL. = STEEL
SYM. = SYMMETRICAL
T.&B. = TOP AND BOTTOM
T.O. = TOP OF
T.O.W. = TOP OF WALL
TF = TOP FACE
THK = THICK
THRD = THREADED
TL = TOP LAYER
TR = TOP ROW OF REINFORCING BAR
TYP. = TYPICAL
U.N.O. = UNLESS NOTED OTHERWISE
U/S = UPSTREAM
UV = UNIFORMLY VARYING
V = VERTICAL
VCP = VITRIFIED CLAY PIPE
W = WIDE FLANGE STRUCTURAL BEAM
W/ = WITH
W/O = WITHOUT
WP = WORK POINT
W.S. = WATER SURFACE
W.S.A. = WATER STOP TYPE A
WSP = WELDED STEEL PIPE
WTP = WATER TREATMENT PLANT
SURVEY NOTES:
1. TOPOGRAPHIC SURVEY DATA WAS COLLECTED BY HOLLYBECK
SURVEYING AND ENGINEERING, INC. ON JULY 14, 2020
2. HORIZONTAL PROJECT COORDINATES ARE NORTH DAKOTA STATE
PLANE SOUTH, NORTH AMERICAN DATUM 1983 (NAD 83). PROJECT
VERTICAL CONTROL IS BASED ON NORTH AMERICAN VERTICAL DATUM
1988 (NAVD 88)
DESIGNED DRAWN CHECKED DATE DRAWING NO. SHEET
OF
SUB-SHEETBONE HILL CREEK
BONE HILL DAM REMOVAL
CBM SAA JJT 01/22/2021 2 5
ABBREVIATIONS, LEGEND, AND SITE ACCESS G2
R:
\1
0\
\1
2.
_B on eH ill_
Re m ov al
\9 _D ra w in gs
\C
AD
F ile s\
IF
C\ Sh ee tF ile s\
-0
-0
8-
3:
pm
S co tt X
RE
FS
: 2
3_
Al lP oi nt s;
J
JT
_s ta m p
JJ
T_ sig
ABBREVIATIONS PRIVATE PROPERTY
AND ACCESS ROAD
NOTES:
1. ACCESS ROAD IS ON PRIVATE PROPERTY. GATES MUST BE CLOSED UPON ENTRY
AND EXIT DUE TO CATTLE.
STAGING AND
STOCKPILE AREA
JO
HN
JO
SEPH TREACY
III
CO
LO
RADO L CENSED
I
PROFESSIONAL ENGINE
ER
47781
2/8/2021
AutoCAD SHX Text
2+00
3+00
4+00
5+00
BH
B1
BH
B2
BH
B3
BH
B4
BORING LOCATION TABLE
Point #
B1
B2
B3
B4
Northing
326807.11
326880.56
326917.02
326990.46
Easting
2380937.57
2380961.20
2380960.44
2380984.07
Elevation
1644.97
1645.17
1645.56
1645.58
0 20 50 100 150 Scale in Feet
SPILLWAY
TRAINING DIKE
AUXILIARY
SPILLWAY
BONE HILL
DAM
CMP SERVICE
SPILLWAY OUTLET
BONE HILL
CREEK LAKE
DESIGNED DRAWN CHECKED DATE DRAWING NO. SHEET
OF
SUB-SHEETBONE HILL CREEK
BONE HILL DAM REMOVAL
CBM SAA JJT 01/22/2021 3 5
EXISTING PLAN AND SECTION C1
R:
\1
0\
\1
2.
_B on eH ill_
Re m ov al
\9 _D ra w in gs
\C
AD
F ile s\
IF
C\ Sh ee tF ile s\
-0
-0
8-
3:
pm
S co tt X
RE
FS
: 2
3_
Al lP oi nt s;
J
JT
_s ta m p
JJ
T_ sig
EROSION/
HEADCUTTING
IN SPILLWAY
OUTLET DISCHARGE
CHANNEL
DOWNSTREAM
CHANNEL
A C1
SECTION
OUTLET STRUCTURE
C1 A
0 5 10 15 Scale in Feet
10.0'
10.0'
36" DIA. CMP
APPROX. 65'
12" D50 RIPRAP
ON 6" BEDDING
48" - 12 SECTION
CMP RISER
12" D50 RIPRAP
ON 6" BEDDING
2.0'
RIPRAP
DRAIN
COMPACTED
BACKFILL
6" DIA. TOE DRAIN
STA. 1+88 TO 4+88±
NOTES:
1. CONTOURS UPSTREAM OF CMP HEADWALL WERE INTERPOLATED BASED ON
GROUND CONDITIONS.
2. GABION ROCK BASKETS ARE SPREAD OUT ALONG AUXILIARY SPILLWAY CHANNEL.
3. REMOVE AND DISPOSE OF EXISTING CMP RISER AND OUTLET PIPE.
4. SALVAGE AND REUSE UPSTREAM SLOPE RIPRAP FOR BREACH TO THE EXTENT
POSSIBLE.
5. EXCAVATE AND REMOVE TOE DRAIN WITHIN THE EXCAVATION LIMITS. ABANDON
AND GROUT TO FILL REMAINING TOE DRAIN WITH 3,000 PSI GROUT.
6. EXCAVATED RANDOM FILL TO BE PLACED AND GRADED IN THE AUXILIARY SPILLWAY
CHANNEL. SLOPE 3H:1V OR FLATTER.
INV. EL. 1634.14
OUTLET INV. EL. 1628.63
JO
HN
JO
SEPH TREACY
III
CO
LO
RADO L CENSED
I
PROFESSIONAL ENGINE
ER
47781
2/8/2021
1+00
2+00
3+00
4+00
5+00
EL
EV
AT
IO
N (F
EE
T)
EL
EV
AT
IO
N (F
EE
T)
0+00 0+40
DESIGNED DRAWN CHECKED DATE DRAWING NO. SHEET
OF
SUB-SHEETBONE HILL CREEK
BONE HILL DAM REMOVAL
CBM SAA JJT 01/22/2021 4 5
GENERAL PLAN OF MODIFICATIONS C2
R:
\1
0\
\1
2.
_B on eH ill_
Re m ov al
\9 _D ra w in gs
\C
AD
F ile s\
IF
C\ Sh ee tF ile s\
-0
-0
8-
3:
pm
S co tt X
RE
FS
: 2
3_
Al lP oi nt s;
J
JT
_s ta m p
JJ
T_ sig
0 20 50 100 150 Scale in Feet
36" DIA. CMP
(TO BE REMOVED)
EROSION AREA TO BE
FILLED W/ EMBANKMENT
MATERIAL
ACCESS ROAD
LOW WATER
CROSSING
NOTES:
1. EXCAVATED EMBANKMENT FILL WILL BE PLACED AND
GRADED IN THE EROSION HEADCUTTING AREAS
WITHIN THE AUXILIARY SPILLWAY.
2. SLOPE HEADCUTTING AREAS 3H:1V FOR CATTLE.
140.0'
260.0'
210.0'
160.0'LIMITS OF SITE
DISTURBANCE
LIMITS OF SITE
DISTURBANCE
STAGING AND
STOCKPILE AREA
200.0'
100.0'
LIMITS OF
WETLANDS
LIMITS OF
WETLANDS
LIMITS OF
WETLANDS
MIN. 6"
STRIPPING
MIN. 4.0'
EROSION SCARP
RANDOM FILL
A C2
TYPICAL SECTION
EROSION SCARP
C2 A
JO
HN
JO
SEPH TREACY
III
CO
LO
RADO L CENSED
I
PROFESSIONAL ENGINE
ER
2+
3+ 004+
5+
2+
.2
-5.0H:1V -5.0H:1V
-5 .0
-1
.0
CP
CP
CP
CP
EL
EV
AT
IO
N (F
EE
T)
EL
EV
AT
IO
N (F
EE
T)
PROFILE VIEW OF EMBANKMENT BREACH
1+00 2+00 3+00 4+00 4+50
EL
EV
AT
IO
N (F
EE
T)
EL
EV
AT
IO
N (F
EE
T)
2+54
0.0 20.0 40.00.0-20.0-40.0
TEMPORARY CONTROL POINT TABLE
Point #
CP1
CP2
CP3
CP4
Northing
326926.06
326923.89
326876.88
326874.71
Easting
2380963.00
2380974.80
2380953.98
2380965.79
Elevation
1635.15
1635.14
1635.15
1635.14
0 10 20 40 60 Scale in Feet
DESIGNED DRAWN CHECKED DATE DRAWING NO. SHEET
OF
SUB-SHEETBONE HILL CREEK
BONE HILL DAM REMOVAL
CBM SAA JJT 01/22/2021 5 5
BREACH PLAN, PROFILE, AND CROSS-SECTION C3
R:
\1
0\
\1
2.
_B on eH ill_
Re m ov al
\9 _D ra w in gs
\C
AD
F ile s\
IF
C\ Sh ee tF ile s\
-0
-0
8-
3:
pm
S co tt X
RE
FS
: 2
3_
Al lP oi nt s;
J
JT
_s ta m p
JJ
T_ sig
PRECONSTRUCTION
GROUND SURFACE
50.0'
ST
A.
.1
" D
IA
. C M
P
FLATTER
FLATTER
LOW WATER
CONCRETE CROSSING
PLAN VIEW OF
EMBANKMENT BREACH
PRECONSTRUCTION
GROUND SURFACE
EL. 1635.15
12.0'
-0.1% -1.0%
36" DIA. CMP
4.0'
2.0'
BREACH INV.
EXCAVATE 2' BELOW PIPE AND
BACKFILL AND COMPACT W/
SUITABLE EMBANKMENT FILL
C3
DETAIL
OUTLET REMOVAL
C3
0 5 10 15 Scale in Feet
10.0'
C3
-0.1% -1.0% -5.0%
GABION ROCK ON
FILTER FABRIC6" BEDDING
CONTROL SILL
EL. 1635.15
12.0' 5.0'
DETAIL
LOW WATER CROSSING
C3
0 5 10 15 Scale in Feet
5.0'
24" THICK TYPE I RIPRAP
OVER 6" BEDDING
5.0'
24" THICK TYPE I RIPRAP
OVER 6" BEDDING
1.0'
2.5'
1.0'
DETAIL
LOW WATER CROSSING
C3
0 1 2 4 6 Scale in Feet
#5@12 EW
C3
4.0'
6" ROADBASE FROM
CROSING TO GRADE
6" ROADBASE 3,500 PSI
CONCRETE
NOTES:
1. LOW WATER CROSSING CONCRETE WILL TRANSITION TO ROADBASE ON SIDE
SLOPES TO GRADE.
2. CUT SLOPES TO BE MATTED AND SEEDED BOTH UPSTREAM AND DOWNSTREAM.
3. TEMPORARY CONTROL POINTS ARE FOR CONSTRUCTION ONLY AND REPRESENT
THE EXTENT OF THE BREACH LOCATION AND ELEVATION.
4. SIDE SLOPES TO BE CONSTRUCTED AT 5H:1V MINIMUM. SLOPES MAY BE
FLATTENED AT THE DISCRETION OF THE LAND OWNER AND FWS.
6" ROADBASE
(TYP.)
CUT SLOPES TO
BE SEEDED
NATIVE UPLAND
SEED MIX
LIMITS OF SITE
DISTURBANCE
TYPE I RIPRAP
AND GABION ROCK
1.5
1.5
-5.0%
TYPE I RIPRAP
5 OR5 OR
JO
HN
JO
SEPH TREACY
III
CO
LO
RADO L CENSED
I
PROFESSIONAL ENGINE
ER
Appendix C Geotechnical Report
REPORT C OVER PAGE
Geotechnical Exploration Report
Dam Exploration
Lamoure County, North Dakota
August 5, 2020
Terracon Project No. M1205033
Prepared for:
W. W. Wheeler & Associates, Inc.
Englewood, CO
Prepared by:
Terracon Consultants, Inc.
West Fargo, ND
Terracon Consultants, Inc. 860 9 th Street NE, Unit K West Fargo, ND 58078
P (701) 282 9633 F (701) 282 9635 terracon.com
REPORT C OVER LETTER TO SIGN
August 5, 2020
W. W. Wheeler & Associates, Inc.
3700 S. Inca Street
Englewood, CO 80110
Attn: Mr. John Treacy, III P.E.
P: (303) 761 4130
E: john.treacy@wwwheeler.com
Re: Geotechnical Exploration Report
Dam Exploration
Bone Hill Creek National Wildlife Refuge
Lamoure County, North Dakota
Terracon Project No. M1205033
Dear Mr. Treacy:
We have completed the Geotechnical Exploration services for the above referenced project. This study was performed in general accordance with Terracon Proposal No. PM1205033 dated July
1, 2020. This report presents the findings of the subsurface exploration for the proposed project.
We appreciate the opportunity to be of service to you on this project. If you have any questions concerning this report or if we may be of further service, please contact us.
Sincerely, Terracon Consultants, Inc.
Alex L. Sprunk, P.E. Chad A. Cowley, P.E.
Geotechnical Group Manager Senior Engineer
Responsive ■ Resourceful ■ Reliable 1
REPORT TOPICS
INTRODUCTION
SITE CONDITIONS
PROJECT DESCRIPTION
GEOTECHNICAL CHARACTERIZATION
GENERAL COMMENTS
FIGURES
Note: This report was originally delivered in a web-based format. Orange Bold text in the report indicates a referenced section heading. The PDF version also includes hyperlinks which direct the reader to that section and clicking on the
GeoReport logo will bring you back to this page. For more interactive features, please view your project online at client.terracon.com.
ATTACHMENTS
EXPLORATION AND TESTING PROCEDURES
SITE LOCATION AND EXPLORATION PLANS
EXPLORATION RESULTS
SUPPORTING INFORMATION
Note: Refer to each individual Attachment for a listing of contents.
http://client.terracon.com/
Responsive ■ Resourceful ■ Reliable 1
INTRODUCTION
Geotechnical Exploration Report
Dam Exploration
Bone Hill Creek National Wildlife Refuge
Lamoure County, North Dakota Terracon Project No. M1205033
August 5, 2020
INTRODUCTION
This report presents the results of our subsurface exploration and laboratory testing services performed for the proposed dam removal project at Bone Hill Creek National Wildlife
Refuge in Lamoure County, North Dakota. The purpose of these services is to provide information relative to:
■ Subsurface soil conditions ■ Groundwater conditions
The geotechnical exploration Scope of Services for this project originally included the advancement of four test borings to depths of 15 feet below existing site grades. While on site, W. W. Wheeler amended the fieldwork scope and requested we advance all four borings to a depth of approximately 20 feet below existing grade.
Maps showing the site and boring locations are shown in the Site Location and Exploration
Plan sections, respectively. The results of the laboratory testing performed on soil samples obtained from the site during the field exploration are included on the boring logs and/or as separate graphs in the Exploration Results section.
SITE CONDITIONS
The following description of site conditions is derived from our site visit in association with the field exploration and our review of publicly available geologic and topographic maps.
Item Description
Parcel Information
The project is located at Bone Hill Creek National Wildlife Refuge in
Lamoure County, North Dakota.
Latitude: 46.5512° N, Longitude: 98.8605° W (approximate)
See Site Location
Existing
Improvements
Existing wildlife refuge
We understand there is an existing dam on the east side of Bone Hill Creek
Lake. Detailed information regarding the dam (height, width, etc.) were not provided.
Dam Exploration ■ Lamoure County, North Dakota
August 5, 2020 ■ Terracon Project No. M1205033
Responsive ■ Resourceful ■ Reliable 2
Item Description
Current Ground Cover Moderately vegetated earthen cover
Existing Topography
Rolling terrain; from the top of the dam, the ground surface slopes downward to the east and west. Top of the dam is at approximate elevation 1645.
PROJECT DESCRIPTION
We understand the dam at Bone Hill Creek National Wildlife Refuge will be removed and the site restored to near original conditions. It is our understanding some of the existing embankment fill will be used to repair eroded areas adjacent to the dam. W. W. Wheeler requested us to provide geotechnical exploration (drilling and sampling) services at four points along the existing dam on the east side of Bone Hill Creek Lake which is located on the Bone Creek National Wildlife Refuge.
W. W. Wheeler also requested Terracon to provide laboratory testing on select samples.
GEOTECHNICAL CHARACTERIZATION
We have developed a general characterization of the subsurface conditions based upon our review of the subsurface exploration, laboratory data, geologic setting and our understanding of the project. This characterization is termed GeoModel. Conditions encountered at each exploration point are indicated on the individual logs. The individual logs can be found in the
Exploration Results section and the GeoModel can be found in the Figures section of this report.
As part of our analyses, we identified the following model layers within the subsurface profile. For a more detailed view of the model layer depths at each boring location, refer to the GeoModel.
Model Layer Layer Name General Description
1 Fill 1 Sandy lean clay mixture - grayish brown and gray, trace gravel, occasional cobbles
2 Fill 2 Sandy lean clay mixture - dark/light gray and black, trace gravel, occasional cobbles, some decayed plant vegetation
3 Fill 3 Buried topsoil - organic clay or sandy silt, dark gray to black, some decayed plant vegetation
4 Fill 4 Silty sand or clayey sand - trace gravel, gray to black, medium to fine grained, waterbearing
5 Sand
Silty or clayey sand - grayish brown to gray, variable contents of gravel, occasional cobbles, fine to coarse grained, medium dense, waterbearing
Responsive ■ Resourceful ■ Reliable 3
Model Layer Layer Name General Description
6 Gravel Poorly graded gravel with silt and sand – grayish brown, fine to coarse grained, waterbearing, occasional cobbles
7 Clay Sandy lean clay - grayish brown to gray, variable contents of gravel, occasional cobbles, medium stiff to very stiff
Due to the variability of soils encountered in the upper 15 feet of the soil borings, it was difficult to identify an accurate transition between fill and native soils. It is possible some of the soils we identified in the boring logs as “fill”, between depths of 10 and 15 feet below grade, are instead disturbed native soils.
Groundwater
The boreholes were observed while drilling for the presence and level of groundwater. The water levels observed in the boreholes can be found on the boring logs in Exploration Results and are summarized below.
Boring Number Approximate Depth to Groundwater while Drilling and Sampling (feet)
B-1 10
B-2 10
B-3 10
1. Below ground surface.
Groundwater was not observed in the remaining boring while drilling, or for the short duration the borings could remain open. However, this does not necessarily mean the boring terminated above groundwater, or the water levels summarized above are stable groundwater levels. Due to the low permeability of some of the soils encountered in the borings, a relatively long period may be necessary for a groundwater level to develop and stabilize in a borehole. Long term observations in piezometers or observation wells sealed from the influence of surface water are often required to define groundwater levels in materials of this type.
Groundwater level fluctuations occur due to seasonal variations in the amount of rainfall, runoff and other factors not evident at the time the…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .