The provided document appears to be an excerpt from a Statement of Work (SOW) Appendix A that outlines the phasing and timeline for a bonded aggregate cleaning and resin overcoat application project.

The key details are:

  • The project is divided into 3 phases, with each phase requiring clean and over-roll with patching, followed by a 24-hour curing period.
  • Phase 1 is scheduled for Day 1, Phase 2 is scheduled for Days 2-3, and Phase 3 is scheduled for Day 4.
  • The related federal contract opportunity is for the "NPS Bonded Aggregate Cleaning Resin Overcoat" project, with a Solicitation Number of 140D0424Q0944.
  • The project scope includes bonded aggregate cleaning, resin overcoat application (25,000 SF), and spot repair (1,000 SF).
  • The contracting agency is the Department of the Interior Departmental Offices Interior Business Center, a civilian agency.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PHASE 3

PHASE 3

Clean & Over-Roll + patching: Day 4 Curing: 24 hours

PHASE 2

PHASE 2

Clean & Over-Roll + patching: Day 2-3

PHASE 1

Clean & Over-Roll + patching: Day 1