SOW_Appendix_A_-_ARHO_Overoll_Phasing_0004.pdf
PDF 4 MB Posted
- Attached to
- NPS Bonded Aggregate Cleaning Resin Overcoat Federal contract opportunity
- Solicitation number
- 140D0424Q0944
About this file
This document appears to be a Statement of Work (SOW) Appendix that outlines the phasing and timing for a National Park Service (NPS) bonded aggregate cleaning and resin overcoat project. The project involves cleaning and overrolling (25,000 SF) with patching (1,000 SF) to be completed in three phases over a 4-day period, with a 24-hour curing time between each phase. The related federal contract opportunity is for the NPS Bonded Aggregate Cleaning Resin Overcoat, solicitation number 140D0424Q0944, issued by the Department of the Interior Departmental Offices Interior Business Center, a civilian agency. The document provides details on the sequencing and timing of the cleaning, overrolling, and patching activities to be performed under this contract.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Brand_Name_or_Equal_Justification_0005.pdf | ||
| Sol_140D0424Q0944_Amd_0005.pdf | ||
| Amend_05_Combined_Synopsis_Solicitation_140D0424Q0944_0005.pdf | ||
| Amend_04_Combined_Synopsis_Solicitation_140D0424Q0944_0004.pdf | ||
| SOW_Appendix_B_-_Bonded_Aggregate_Drawings_0004.pdf | ||
| Sol_140D0424Q0944_Amd_0004.pdf | ||
| SOW_Appendix_C_-_Bonded_Aggregate_Specifications_0004.pdf | ||
| Sol_140D0424Q0944_Amd_0003.pdf | ||
| SOW_Appendix_A_-_ARHO_Overoll_Phasing_-_Copy_0002.pdf | ||
| SOW_Appendix_C_-_Bonded_Aggregate_Specifications_0002.pdf | ||
| Combined_Synopsis_Solicitation_140D0424Q0944_-_Copy_0002.pdf | ||
| Sol_140D0424Q0944_Amd_0002.pdf | ||
| SOW_Appendix_B_-_Bonded_Aggregate_Drawings_0002.pdf | ||
| Sol_140D0424Q0944_Amd_0001.pdf | ||
| Sol_140D0424Q0944.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PHASE 3
PHASE 3
Clean & Over-Roll + patching: Day 4 Curing: 24 hours
PHASE 2
PHASE 2
Clean & Over-Roll + patching: Day 2-3
PHASE 1
Clean & Over-Roll + patching: Day 1