Statement of Work Construction Veranda Receptacles.pdf
PDF 264 KB Posted
- Attached to
- Electrical Construction Federal contract opportunity
- Solicitation number
- 1333ND24RNB190010
About this file
This document is a Statement of Work (SOW) for the installation of new receptacles in the exterior veranda area of Building 101 at the National Institute of Standards and Technology (NIST) campus in Gaithersburg, Maryland.
The key objectives are to provide receptacles in the veranda area to allow patrons to charge their portable electronic devices. The contractor will be responsible for tasks such as tying into the existing electrical circuit, adding new receptacles, and ensuring compliance with applicable electrical codes. The SOW specifies the required deliverables, including a security plan, construction schedule, and material submittals. The period of performance is 70 days after notice to proceed. The contractor is required to obtain NIST security badges for all on-site personnel, which can take up to 82 days to process. This work is part of a larger Indefinite Delivery Indefinite Quantity (IDIQ) contract for Electrical Construction at NIST, with a total contract ceiling of $9,000,000 over 5 years and a guaranteed minimum of $4,000.
View the file
Other files for this federal contract opportunity
Show all 34
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
St at em en t o f W o rk
Statement of Work: B101 – New Receptacles at Veranda 1
Version 1.0 (2019) January 26, 2024
TITLE: B101 – New Receptacles at Veranda Requesting Lab/Division/Group: OFPM/FIG 195.02
General Statement of Need:
Installation of receptacles at veranda area of B101.
Background:
With the influx of technology there is a need for patrons to charge electronic devices. This project adds receptacles at the exterior veranda area to serve patrons using the library facility.
Objective(s):
To provide receptacles in the exterior veranda area so that patrons can charge their portable electronic devices.
Scope/General Requirements The contractor will provide all necessary labor, transportation, equipment, materials, expertise, tools, supervision, and management required to perform all activities within the scope of this contract. The contractor shall comply with applicable codes including NFPA 70 and NFPA 70E.
Activities may consist of, but not limited to:
• Tie into existing electrical circuit.
• Adding receptacles in the exterior veranda area. Existing circuit is not equipped with an equipment grounding conductor. Provide GFCI receptacles and additional receptacles supplied trough this GFCI per NFPA 70, 406.4 (D)(2).
Tasks/Specific Requirements Task 1 – Installation of receptacles Confirm existing conditions:
• Per preliminary survey: Three (3) ¾” conduits identified in existing junction identified as PB1-53-PP#19 located in existing column. Conduits include each: 2 #10 conductors (existing circuit PB1-53-PP#19), 4 #10 conductors (homerun for existing circuits PB1- 53-PP#19/21/23), 3#10 conductors (existing circuits PB1-53-PP#21/23).
• Use of shared neutral.
• No equipment grounding conductor.
• Identify and tag existing circuits.
• Refer to existing PDF file “Original Power Library Bldg 101” for additional information.
em en t o f W
Statement of Work: B101 – New Receptacles at Veranda 2
Task 2 – Installation of new receptacles Install new circuit with receptacles as follows:
• Intercept existing circuit PB1-53-PP#21 in column inside library. Assume replacement of existing junction box in column. Patch and paint drywall as needed.
• Route circuit from the inside column
• Install six (6) new weatherproof receptacles from intercepted circuit PB1-53-PP#21.
• New receptacles in circuit PB1-53-PP#21 to be routed in surface mounted conduit along existing granite base. Provide a ground-fault circuit-interrupter at the beginning of the circuit run. Comply with NFPA 70, 406.04(D)(2).
• Replace existing exterior at columns near stair entrances.
• Refer to attachments “Original Power Library Bldg 101” and “Circuit Routing Along
Granite Base” for additional information.
• Provide two price proposals: one based on aluminum rigid conduit system (to include fittings and supports) and one bid alternate based on professionally painted aluminum rigid conduit system (to include fittings and supports) to match existing granite base color. Product shall comply with NFPA 70, 344 (available conduit manufactures include but are not limited to Allied Tube and Conduit, and Wheatland
Tube).
Delivery Deliverable Schedule
Deliverable Description Quantity/Media Date Required
1 Completed Contractor Badge Application (NAIS) – OF 306 and NIST Site Badge Application for Green (for every onsite contract employee except delivery drivers)
Electronic submission Within 14 days of contract award
2 Contractor activity hazard analysis (job specific health and safety plan)
Electronic PDF submission
Within 14 days of contract award
3 AIA Bond and certificate of insurance
Electronic PDF submission
Within 21 days of contract award
4 Initial and updated Biweekly Construction Schedule
Electronic PDF submission
Every two weeks em en t o f W
Statement of Work: B101 – New Receptacles at Veranda 3
5 A quality control plan Electronic PDF submission
Within 21 days of contract award
6 Security Plan Electronic PDF submission
Within 21 days of contract award
7 Schedule of Contract Values Electronic PDF submission
Within 21 Days of NTP
8 Contract material submittals Electronic PDF submission
Within 21 Days of NTP
9 Warranty Master Schedule upon COR acceptance for each piece of equipment
Electronic PDF submission
Within 14 days of equipment acceptance
Government-Furnished Property, Material, Equipment, or Information (GFP, GFM, GFE, or GFI) N/A
Security Contractor to submit a security plan within 21 days of award. The following is to be addressed
• Access control for contractor personnel (background checks, clearances, alien status, etc.);
https://www.e-verify.gov/employers/federal-contractors
• Badging (construction worker ID badges and processing, escort/no escort required, lost badge procedures, access termination procedures);
• Vehicular access (construction worker parking, construction material deliveries);
• Internal security (key control, sensitive areas, internal theft of government or employee property);
• Construction worker movement to or through areas that are still occupied or operational;
• Security of construction plans (hard copy and electronic);
• Physical barriers; construction area warning signs; and
• Maintaining security during HAZMAT, law enforcement, fire, or medical emergency response.
Travel None Anticipated
Special Material Requirements None https://www.e-verify.gov/employers/federal-contractors em en t o f W
Statement of Work: B101 – New Receptacles at Veranda 4
Other Unique Requirements None
Place of Performance Gaithersburg, Maryland
Notice-To-Proceed
A Notice-To-Proceed (NTP) will be issued upon completion and government approval of Bonds, Safety Plan and validation of proper insurance. In accordance with the solicitation; Bonds, Insurance, and a Safety Plan are required to be submitted within 21 days after contract award.
Therefore, the NTP will be issued immediately upon review and approval of the Bonds, Safety Plan and validation of proper insurance. It is anticipated that NTP will be issued within 60 days of award.
In the event that the contractor does not provide the documents above, within 40 days of award, the contractor will be notified that they are delaying the project and a plan for corrective action will be required. The corrective action plan will shall be submitted within 7 days of the notification from the contracting officer.
Access to the campus will be restricted until the contract personnel are badged. Badging shall start at time of contract/task order award.
Period of Performance Period of Performance for this SOW shall be 70 days after notice to proceed.
Badging Requirements
Although a notice to proceed may be issued after acceptance of bonds and insurance, a NIST issued security badge is required for campus physical access. The contractor is responsible for ensuring that all badging requirements are adhered to in accordance with the Guidelines for OFPM Contractors and AE Firms. Further, the contractor is responsible for directly communicating with the assigned COR regarding any delay in the badging process.
Please note the timeline below to obtain a Green NIST site access/PIV badge. Reference
Guidelines for OFPM Contractors and AE Firms for (Yellow) Limited Access Cards. If a yellow badge is eligible for this contract/task order, please confer with COR.
Site Access/Site Card/PIV Timeline (Error free badge applications) em en t o f W
Statement of Work: B101 – New Receptacles at Veranda 5
COR submits badge application after award to contractor (NIST Action) Within 7 days
Contractor submits badge application and OF306 to COR for each and all contract employees *
Within 14 days
Application is entered into the security system (NIST Action) Within 8 days
Applicant is emailed E-QIP invitation (DoC/NIST Action) Within 8 days
Applicant completes E-QIP prior to email link expiration ** Within 14 days
E-QIP application is reviewed and approved for fingerprints at NIST (DoC/NIST Action)
Within 8 days
Applicant arranges with COR for visitor center access to obtain fingerprints Within 8 days
Applicant’s fingerprints are reviewed; Applicant is approved for NIST badge (NIST Action)
Within 8 days
Applicant schedules a badge appointment and arrives for badge Within 7 days
Total (Maximum) 82 days
* If contractor does not submit all badge applications at one time, the last badge application submission date will drive how long the badge process will take.
** If the applicant doesn’t complete E-QIP within the 14 days, contractor needs to notify COR to request another E-QIP invitation. Resent E-QIP invitation may take up to 4 days to be sent.