About this file

This document is a set of questions and answers related to an electrical construction project at the National Institute of Standards and Technology (NIST). The key details are:

The NIST is issuing an Indefinite Delivery Indefinite Quantity (IDIQ) task order contract for electrical construction, with a 5-year ordering period and a total contract ceiling of $9,000,000. This is a 100% set-aside for small business firms. The questions and answers address details such as the use of GFCI outlets, the drilling of historic granite, the replacement of exterior receptacles, and the provision of grounding conductors. The solicitation will be updated to include a bid alternate for a professionally painted aluminum rigid conduit system. The electrical contractor will be required to provide marked-up drawings rather than CAD as-builts for this initial task order.

View the file

Other files for this federal contract opportunity

Other files attached to Electrical Construction, newest first.
File Type Posted
Veranda Ext Arch Struct Detail Bldg 101_Amend 0001.pdf PDF
Original Power Library Bldg 101_Amend 0001.pdf PDF
Statement of Work Construction Veranda Receptacles 07 23 2024_amend 0001.pdf PDF
Panelboard Pictures_Amend 0001.pdf PDF
Site Visit 1333ND24RNB190010_KTR attendance.pdf PDF
1333ND24RNB190010 _Amend 001.pdf PDF
Circuit Routing Along Granite Base_Amend 0001.pdf PDF
Statement of Work Construction Veranda Receptacles.pdf PDF
List of Attachments.pdf PDF
NIST S 7101-58_Respiratory Protection_01072021.pdf PDF
NIST O 7401-00_Fire and Life Safety Order_051721.pdf PDF
NIST 7101-65_Machines Power Tools Associated Equipment Safety_040419a.pdf PDF
Attachment 2- Project Data Sheet.pdf PDF
WD_MD20240053.pdf PDF
NIST S 7401-02_ITM of Fire Protection and Life Safety Systems_042221.pdf PDF
NIST S 7401-01_Fire Protection Life Safety for Design and Construction _01122021.pdf PDF
NIST S 7101-55_Hearing Protection_01072021.pdf PDF
NIST S 7101-56_Control of Hazardous Energy_LOTO_01072021.pdf PDF
NIST S 7101-67_Fall Protection_09072021a.pdf PDF
Guidelines for Contractors and A-E firms - May 25 2022.pdf PDF
Attachment 3 - Past Performance Questionnaire.pdf PDF
REVISED---NIST S 7401-03_Impairment of Fire Protection and Life Safety Systems_020622a.pdf PDF
NIST P 7400.00 - Fire and Life Safety_021017.pdf PDF
NIST S 7101-24_Incident Reporting and Investigation_01042021.pdf PDF
Attachment 1- Key Personnel Resume Form.pdf PDF
FormSF1442_solicitation.pdf PDF
final_pr_2103_06 Utility Outages.pdf PDF
NIST N 7101-64_Electrical Safety Notice_102615 (5).pdf PDF
NIST S 7101-57_Permit-Required Confined Space_01072021.pdf PDF
NIST S 7101-20_Work and Worker Authorization Based on Hazard Reviews_12172020.pdf PDF
NIST S 7401-04_Fire Prevention During Welding Cutting and Other Hot Work_01122021.pdf PDF
NIST S 7101-66_Ladder Safety_090523.pdf PDF
NIST S 7101-74_Powered Industrial Trucks_10292021.pdf PDF
FINAL---NIST S 7101-21_Personal Protective Equipment_062023.pdf PDF
Show all 34

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Could you please provide the photos of the electric room and panel?

Photos will be provided and added to the scope as attachment “Panelboard Pictures”.

2. Is the existing conduit run overhead or in the slab?

In the slab per record drawings. There is not guarantee that record drawings match field conditions.

3. Would GFI outlets with USB ports be a better fit for this application?

Yes, scope will be updated to reflect this.

4. Is the use of IMC conduit acceptable for this project?

It is for the painted option. Will update scope to reflect this. Still want the aluminum finish as stated in the scope (e.g., both painted and aluminum finish options are required).

5. It is our understanding the existing granite base is listed as historic and has historical value. Will we be allowed to drill thru the granite to support our conduit and boxes? Or will we be required to drill only thru the outer joint seam?

Drill thru granite is allowed with diamond core bit. The offeror can consult with a granite expert consultant. If applicable, the offeror must reference this consultation in the technical narrative.

6. Dry or core drilling thru the existing historical granite does not seem to be an option.

This will most likely crack the granite. Will a diamond core bit be allowed to be used when penetrating the granite to bring electric from the interior column out to the exterior?

Drill thru granite is allowed with diamond core bit. The offeror must use means and method needed to ensure not cracking of the granite. The offeror can consult with a granite expert consultant. If applicable, the offeror must reference this consultation in the technical narrative.

7. Please verify that all (6) new receptacles will be GFCI type and that no pig tailing from

(1) GFCI will be accepted? The statement of work shows provide a ground-fault circuit-interrupter at the beginning of the circuit run.

One GFCI protecting the whole circuit is acceptable.

8. The statement of work shows to “Replace existing exterior at Columns near stair entrances”. Please confirm this means to replace existing receptacles at columns near stair entrances.

Yes, statement should have referred to existing receptacles at columns. Scope have been updated to reflect this.

9. In the statement of work, it shows that no grounding conductors exist for panel “PB1- 53” Circuits 19, 21 and 23. Please advise that the intent is to provide a new grounding conductor from the electrical panel for these circuits.

No. NFPA 70, 406.4 (D)(2) shall be followed.

10. Attachments “Original Power Library Bldg. 101” and “Circuit Routing Along Granite Base” for additional information. I believe we viewed these drawings at the project walk but they do not appear to be available on the Sam.gov website. Can these drawings be provided prior to the due date?

Attachments “Original Power Library Bldg. 101” and “Circuit Routing Along Granite Base” will be provided.

11. In the provided bid Solicitation, there is only Item No. 0001 $_________ shown for pricing. Since two price proposals are being requested, one based on aluminum rigid conduit system (to include fittings and supports) and one bid alternate based on professionally painted aluminum rigid conduit system (to include fittings and supports) to match existing granite base color. Will this solicitation be updated for the painted option identified as Item No. 0002?

Yes. Solicitation will be updated.

12. Will the B101, “New receptacles at Veranda” project require the assistance of a design engineer for cad /construction drawings or will the electrical contractor be able to provide as-builts that are marked up from the Government supplied drawings?

Electrical contractor to provide mark up drawings. CAD as-builts not required for this initial task order.