Attachment 1-GU FY25 Drydock Rev (C).pdf
PDF 4 MB Posted
- Solicitation number
- 1305M224QNMAN0313
About this file
This document contains the specifications for the FY 25 intermediate drydocking and repairs to the NOAA Ship Gordon Gunter. The work includes routine annual inspections, maintenance, and repairs to the ship's systems and equipment, such as life rafts, survival suits, fire systems, navigation and communication systems, propulsion motors, and sanitation systems. The contractor is required to provide labor, materials, and technical services to perform the work. The document specifies inspection and testing requirements, quality assurance processes, and deliverables such as service reports and certifications. It references various NOAA standard specifications and drawings that will be provided to the contractor. The work is to be completed during a scheduled drydocking period to ensure the ship is able to safely perform its research and mapping missions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment IV - Price Schedule (Rev. 1).xlsx | XLSX spreadsheet | |
| Amendment 0001.pdf | ||
| Attachment VI - DOL Employee Rights Jobsite Poster.pdf | ||
| COMBINED SYNOPSIS-SOLN.pdf | ||
| Attachment IV - Price Schedule.xlsx | XLSX spreadsheet | |
| Attachment V - NOAA EAD AIRS PROCESS.pdf | ||
| Attachment II-Past Performance Information Form.pdf | ||
| Attachment III-Past Performance Questionnaire.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NOAA SHIP GORDON GUNTER
FY 25 DRYDOCK REPAIR SPECIFICATIONS
NOAA Ship Gordon Gunter FY25 Drydock Repair
Table of Contents
TABLE OF CONTENTS
1 SCOPE
2 GENERAL
REFERENCES
REQUIREMENTS
TEMPORARY SERVICES
3 BASE ITEMS
ANNUAL LIFE RAFT INSPECTION
SURVIVAL SUIT INSPECTION AND CERTIFICATION
ANNUAL MIRANDA INSPECTION AND MAINTENANCE
ANNUAL FAST RESCUE BOAT (FRB) INSPECTION AND MAINTENANCE
ANNUAL FIRE INSPECTION AND CERTIFICATIONS
ANNUAL WEIGHT TESTING OF LIFTING APPLIANCES
ANNUAL NAVIGATION & COMMUNICATION
ANNUAL MAIN PROPULSION MOTOR SERVICE
ANNUAL MARINE SANITATION DEVICE (MSD) SERVICE
ANNUAL OILY WATER SEPARATOR (OWS) SERVICE
SWITCHBOARD CLEANING AND GENERATOR INSPECTION (ANNUAL)
GREY AND BLACK WATER PIPING
BILGE CLEANING
OILY WASTE REMOVAL
STAND-ALONE AIR CONDITIONING UNITS SERVICING THE SERVER ROOM, PILOT HOUSE
A - FRAME MAINTENANCE
ANCHOR CHAIN MAINTENANCE
SHOWER DECK RE-SEALING
THERMOGRAPHIC SURVEY
STERN TUBE PUMPS
GAUGE CALIBRATION
GENERATOR ROOM VENTILATION WIRING
COATINGS REPAIR - FLYBRIDGE
SSDG SERVICING
DRYDOCK TEMPORARY SERVICES (ADDITIONAL)
DRYDOCKING AND ROUTINE DRYDOCK WORK
HULL VALVE MAINTENANCE
REFRIGERATION PLANTS TUNE UP/SERVICE/MAINTENANCE
OPERABILITY AND MAINTAINABILITY
STEERING HYDRAULICS
GALLEY HOOD DUCT CLEANING
MISCELLANEOUS STEEL REPLACEMENT
ANODE REPLACEMENT
MAIN PROPULSION MOTORS COMMUTATOR SERVICING
MAIN PROPULSION SHAFT SEAL REPLACEMENT
CHILL WATER VENTS
SSDG VALVES
BRIDGE SUNSHADES
WET LAB DECK COATING REPLACEMENT
COATINGS INSPECTIONS
FLOORING REPLACEMENT – CO STATEROOM
GYRO COMPASS
DOCK TRIALS AND SEA TRIALS
COATING SYSTEM REPAIR
PHOTOLUMINESCENT MARKINGS
AC PLANTS REPLACEMENT
BULWARK REPLACEMENT
PROFIBUS UPGRADE
ADDITIONAL WORK
5.0 Option Items
ACCESS AND EGRESS (HATCH INSTALLATION)
“A-FRAME” BEARING REPLACEMENT
COATING SYSTEM REPAIR - STACKS
TEMPORARY PLATFORM
COATINGS REPLACEMENT - AFT
COATINGS REPAIR - TOPSIDE
ADDITIONAL PIER SERVICES
HULL COATING
COATINGS REPAIR - FORWARD
1. SCOPE
This Specifications contain the requirements for routine intermediate drydock inspection, repairs and modifications to the NOAA Ship Gordon Gunter.
The National Oceanic and Atmospheric Administration (NOAA) operates a fleet of research vessels that support research and mapping for the National Fisheries Service, National Ocean Service, Office of Atmospheric Research and the National Weather Service, as well as provide support to other Federal agencies. These research missions are time sensitive and therefore the data must be collected at specific times during the sailing season to be meaningful. At the end of each sailing season the vessels enter a work availability (dry-dock or dockside) period to address known repairs & perform system upgrades. These availabilities support extending the life of the ship, maintain or enhance safety and habitability, provide new data collection capabilities and address emergent work that would otherwise adversely affect the ship’s ability to perform its mission. The work is completed such that all regulatory body (i.e. American Bureau of Shipping, United States Coast Guard) and habitability requirements are met. Order of work execution shall be efficient, and work is to be executed so as to not cause additional work or rework when such is avoidable.
The work items in the repair specification are identified well in advance of the performance period in order meet the contracting lead times. Additional work items (emergent work) may arise during the period between the work package submittal, contract award, or even prior to the start of or during the contract performance period. In accordance with Commerce Acquisition Regulation (CAR) clause 1352.271-72, the Contracting Officer may order additional changes during the contract period of performance to address any additional work items identified as necessary to ensure the intent of the dry-dock or dockside repair contract is met; that is, that the vessel shall be able to safely perform its mission, that it will meet all habitability requirements and regulatory body requirements, and that such repairs will be timely performed to ensure to the maximum extent practicable that the ship's schedule is not adversely impacted.
All work performed and materials to be first class in execution and cosmetic appearance, and suitable for intended purpose.
All joint and tightness tests and inspections shall be conducted in the presence of the COR.
All work is subject to COR acceptance.
2. GENERAL
References
NOAA Standard Specification No. MOC-000-1G, “General Requirements for Ship Repair Work on NOAA Ships.”
NOAA Standard Specification S1600, “Structural Access Cuts.”
NOAA Standard Specification, S2906, “Arc Welding on Waterborne Vessels.”
Dwg. No. 085-6233560, “General Arrangement Main Deck and Below.”
Dwg. No. 085-6233567, “General Arrangement Fcsle Dk & Above.”
NOAA Ship Gordon Gunter Drawing Index List
NOAA Weight Report Form, Microsoft XL Format, “Weight Report.xls”
NOAA Standard Specification MOC-631-2D, “Coating Systems for Steel Surfaces.”
ABS Rules for Building and Classing Steel Vessels
Commerce Acquisition Manual
Code of Federal Regulations
NOAA Ship Health Plan 1005-01
NOAA Drawing “Profile References, Modules, and Erection Sequence”
Dwg. No. GU-830-002, “Booklet of General Plans”
NOAA Ship Gordon Gunter Technical Publication Index List
Dwg. No. GU-801-001, “NOAA Ship Gordon Gunter Tank Sounding Tables.”
NOAA Weight Report Form, Microsoft XL Format, “Weight Report.xls”
NOAA Standard Specification AMC-000-2C, "Temporary Services at Contractor Facilities"
NOAA Standard Specification AMC-997-1A, "Drydocking and Routine Drydock Work"
GU-085-01 (Rev A), “Docking Plan”
Standard Specification S1205, “Zinc Protectors”
Drawing No. 243-6233870, “Main Propeller Shaft Installation Arrangement & Details”
Drawing No. 543-6233930, “Stern Tube & Shaft Bearing Lube Oil System Arrangement”
633-6233582, “Zincs Arr & Details” Drawing
AMC-631-2D Coating Systems for Steel Surfaces
Requirements
Reference 2.1.1 forms a part of these Detail Specifications. All provisions and requirements contained therein are applicable to all work items, including all additional work items that are authorized by the Contracting Officer. References, and drawings included herein or within references or attachments also remain applicable.
References 2.1.2 and 2.1.3 are amplifications of the requirements contained in reference
2.1.1 and other sections herein. Additional References are contained in individual items.
References 2.1.4 through 2.1.8 will be available for review during scheduled pre- bid inspection and during the performance period of the contract. The general arrangement drawings are the original Ocean Surveillance Ship T-AGOS 13 class drawings produced when the ship was built. Modifications to the ship after re-activation in 1998 for NOAA’s operations, and conversion in 1999 to meet National Marine Fisheries Service (NMFS) requirements, are not reflected in these arrangements. Some of the drawings and information provided in references 2.1.6 through 2.1.7 reflect some of the ship’s arrangements and construction changes since reactivation as a NOAA vessel. Contractor shall be responsible for verifying all current configuration, construction, and arrangement changes, as necessary, to comply with and perform the work requirements of these specifications. Contractors are encouraged to review ship’s drawings and to perform a field inspection of the ship and her equipment prior to submitting a bid proposal.
Ship’s drawings and technical publications may be borrowed during the performance period. All reference materials borrowed by the Contractor shall be signed for, and then returned to the COR after no further use of the reference materials is required.
Provide and maintain a status report of all American Bureau of Shipping (ABS) inspections and technical reviews required by ABS, during the course of this contract, to ensure the ship’s ABS certification requirements are in compliance. Submit weekly ABS status reports to the COR, along with the preliminary progress reports.
All visual examination, hydrostatic testing, and non-destructive testing shall be in accordance with ABS Rules for Building and Classing Steel Vessels, Survey After Construction, Part 7. All contractors performing NDT and hull gauging shall be certified under the ABS external specialists program.
Provide revised and updated copies of the production schedule to the COR as required to reflect actual work progress.All new equipment and furnishings purchased by the Contractor for installation on the vessel shall be provided with factory supplied technical manuals, or data sheets, complete with parts listings. Faxed copies of this information are not acceptable. This documentation shall be turned over to the COR after installation is completed. Equipment technical manuals shall provide detailed information necessary to operate, maintain, troubleshoot, and repair the equipment. The manuals shall include detailed procedures for disassembly of equipment, parts lists, drawings, inspection criteria, troubleshooting, and test procedures. Provide four paper copies of each manual, plus one electronic copy in Abode Acrobat .pdf format.
All inspection, test, and quality reports shall be submitted to the COR in Microsoft Word electronic software formats, in addition to providing hard paper copies.
Contractor to warrant all new or repaired coatings for a period of two (2) years from end of period of performance. Repair at ship convenience for any areas reported within 2 year period.
Weigh all materials and items removed, installed, or relocated on the ship. Provide by-weekly updates in the Contractors Performance and Progress Report. Provide a summary report to the COR indicating the total weight in pounds of items and a breakdown of their locations by space, deck, frame, distance from centerline, and height above the deck.
Reference 2.1.7 will be provided by the COR for the Contractor to identify, record, and document all weight changes for submitting the summary reports. Contractor may use their own weight report form for documenting weight changes. All the information required must be tracked and documented on any form provided.
Unless otherwise stated in the individual work items, prepare and coat all new steel, all existing steel surfaces identified to be cleaned and painted, and all paint systems disturbed while accomplishing work items, in accordance with reference 2.1.1. Finish coat colors shall match those of the surrounding, unmodified area. First coat shall be Sherwin Williams one part epoxy zinc, unless otherwise specified.
Ship’s force will maintain a minimal presence during accomplishment of work to these specifications. Their availability to operate ship’s equipment will be limited. Unless otherwise specified, provide a minimum of two working days’ prior notice for any equipment operations or lockout/tag out.
Ship’s Force standard workday is 8 hours (0700-1530), with lunch starting at 1100 hours.
The ship in conjunction with the above paragraph can support work on an extended 12 hour workday (0700-1900). The Contractor can request up to the extended workday from the COR, but NOAA cannot guarantee they have the work force to support.
All new and disturbed machinery and services shall be operated for a period sufficient to indicate satisfactory performance, but not less than one hour, after all adjustments and deficiency corrective actions have been made, without further adjustment.
Provide factory authorized technical representatives where required in the individual work items, to witness and to provide technical guidance during operational testing of equipment and systems, or as otherwise necessary. All tests and trials of equipment or systems shall be witnessed by the COR, ABS, and/or USCG as applicable, to ensure compliance with regulatory body requirements to maintain the ship’s ABS class certification, and to complete all requirements of these specifications
All new installed equipment, GFM and/or Contractor Furnished, whether stated or not in the individual work items shall be commissioned by a factory authorized technical agent in order to maintain equipment warranty.
The Contractor shall provide the services to the ship to dispose of hazardous waste. This is waste generated by the ship and is outside waste stored in ship’s tanks. Waste will consist of but not limited to; expended batteries from UPS and battery back-up systems, paint in containers up to 5 gallons, oily rags, etc.
These Detailed Specifications are a combination of “performance specifications” and “design specifications.” Whenever possible, the Government has provided performance specifications, giving the Contractor the opportunity to accomplish the work requirements as best as he or she sees fit, while providing a fully functional repair and/or equipment/system installation in accordance with all work requirements. When specific details are required, the Government will provide design/detail specifications; this will be more the exception, than the rule.
All installations shall comply with the references in section 2.1 and the contractor shall consult Reference 2.1.9 for proper material, installation standards, and connections to ship systems, where one installation method for one system is not authorized for another system. Such as treaded connections verses welded connections or any other safety driven ABS requirements (ex. spray shields).
Frame numbers and space names are derived from ship’s drawings. All equipment changes and space modifications over the ship’s life span may not all be reflected in the referenced drawings. Contractors are encouraged to review all referenced drawings and to perform a field inspection of the ship prior to submitting a bid. Copies of drawings and technical manuals not included herein may be made available for review during any scheduled pre-bid inspection and during the performance period. Contractors my review available drawings and technical manuals on board ship or at the Port Engineer’s office at NOAA’s Gulf Marine Support Facility, 151 Watts Ave., Pascagoula, MS.
Care and protection of the ship shall be strictly adhered to while work is being performed and properly secured/protected at the end of each shift which includes, but not limited to, providing proper protection for existing equipment, removed equipment (spares), new equipment being installed, wire-ways, piping, electronics, ductwork, passageways, decks, bulkheads, handrails, doorways and floorings. Items damaged shall be reported to the COR and documented via CFR within 24 hours, and they shall be replaced or repaired by the contractor.
Unless otherwise stated all work including growth (AIR) surface preparation and painting work shall be accomplished in accordance with Reference 2.1.1.8, except for the type of coating used. All paint preparations and application shall be completed in accordance with QP1 Standards. The Contractor may substitute QP1 by providing the services of a third party National Association of Corrosion Engineers (NACE) Level 2 or 3 qualified technical representative for the coatings products for supervision of surface preparation and coating system application. The technical representative shall be primarily used to observe the surface preparation, paint film thickness of coats, and to resolve technical difficulties such as allowable overcoat times, low ambient temperature or high relative humidity.
Contractor will follow/adhere to Government or NOAA policies, including ship/CO specific policies. Contractor should take note of safety related policies, working hour policies, OSHA rules, etc.
Reports and/or Deliverables
Contractor shall provide to the COR their Quality Assessment Plan (QAP), to include a Test Index Plan (TIP), or similar, in order to track deliverables throughout the project.
Provide an updated TIP report the COR at least every week.
Required reports Condition Reports (CR) and Condition Found Reports (CFR) are identified in the specifications. .
Deliverables are identified in the same manner as required reports and shall be submitted with the approved CR/CFR format cover sheet.
Other Technical Reports and Administrative Reports as required by the COR.
Kick-off/Pre-dockside Meeting
Unless previously completed after Contract award, on the first day of the Period of Performance and before commencing work on the ship, the Contractor shall host a kick-off meeting in the Ship’s Mess at 0800, or in Contractor’s conference room of adequate size. At a minimum, the meeting shall be attended by the COR, Contracting Officer (in- person or via phone), ship’s CO and CME, ABS surveyor, Dockmaster, and a Contractor's management official having authority to make binding commitments. Other interested parties may attend the meetings as appropriate.
The Contractor’s baseline Schedule, including start, checkpoint, milestone, and completion, dates for each work item, and all responsible parties by name and discipline/company. QA Test and Inspection Plan shall be submitted for approval by the COR no later than 30 days prior to, the Kick-off/Pre-availability Meeting. Any potential impacts to schedule, habitability, and material delivery delays, or complex work shall be identified. The TIP must be complete and approved prior to the meeting. Schedule will delineate critical path and milestones for the project, as well as measurable tracking methods to completion.
Contractor will provide organizational charts with contact information for each for all shipyard leadership as well as pertinent staff.
On the first day of the Period of Performance, the Contractor shall document existing ship conditions with a Ship’s Representative designated by the CO. Contractor shall document the pre- work as-found conditions of all spaces the contractor will work in or transit through.
Contractor shall complete and save a video recording of the existing ship conditions for documentation purposes. A copy of video shall be provided via CFR, to the COR, broken down by work item before work is started on the vessel. Included in the video effort the Contractor is responsible to accomplish the following as applicable.
Contractor shall also develop sketches with dimensions for individual work items to ensure interferences are replaced as originally found and in the same or better condition/matter.
Contractor shall ensure all equipment is in operating condition prior to disassembly or interference removal. Contractor shall coordinate equipment operation with the COR and/or Chief Engineer.
Document placards, labels and stencils in way of the work and interferences. All labels and placards shall be renewed if damaged or removed.4.21.
Notes: The following descriptive data of the ship is provided for information:
Length, Overall 224’ 0”
Length, BP 194’ 0” Beam, Molded 43’ 0”
Mean Draft, Load Line 15’ 1” Displacement, Load Line 2328 LT Displacement, Lightship 1557.2 LT
Cruising Speed 11 Knots Officers & Crew Size 19
Electric Service 450VAC, 60Hz, 3PH, 800A Service (2X400A) Propulsion Diesel electric, twin screw
NOAA Ship Gordon Gunter is identified with ABS ID Number 9000291, IMO Number 8835255, Official Number
023674, Hull Number 1128, and is classed +A1, E, +AMS, and +ACCU.
GOVERNMENT FURNISHED MATERIAL/EQUIPMENT: See Individual Items
Temporary Services
2.3.1. Scope
2.3.1.1. Provide temporary services for the ship for the entire time the ship is at the Contractor’s facility or until all work items are complete, and any time the Contractor disrupts ship’s services.
2.3.2. References
2.3.2.1. NOAA Standard Specification AMC-000-2D, “Temporary Services at Contractor
Facilities”
2.3.2.2. NOAA Standard Specification AMC-000-1H, “General Requirements for Contract Repair Work on NOAA Ships”
2.3.3. Government-Furnished Material (GFM)
2.3.3.1. None.
2.3.4. Requirements
2.3.4.1. Provide all temporary services required in accordance with Reference 2.3.2.1 with shore connection details and additional requirements as follows for the entire performance period:
2.3.4.2. Garbage- One dumpster located within 50-feet of the ship’s gangway. Dumpster shall be emptied within 24 hours of request. If dumpster is used by Contractor and ship, dumpster will be emptied by Contractor at approximately ¾ full point.
2.3.4.3. Crane Service- Provide crane service including operator and riggers for ship's force equipment and material lifts as needed during normal working hours. Provide crane lifts with a 5-ton minimum capacity. Provide COR with a procedure to request crane services with nominal four hours advance notice. For bidding purposes, assume 20 hours of crane service in total, in addition to any needed rigging, etc. support. If additional crane service is needed beyond estimated twenty hours, then the COR will provide an additional item request to the Contracting Officer for negotiated contract modification.
2.3.4.4. Disruption of Temporary Services: In the event temporary services are reduced due to the extent of contract work and disruption to services provided to the ship, rendering the ship uninhabitable, an equitable adjustment to the contract shall be negotiated.
The daily temporary service charge for all services as bid, but not provided shall be reduced and a credit provided to the government for the remainder of the contract period services are disrupted. Contractor shall make every effort to maintain all facilities and services required by this specification in a safe manner, so as not to render the ship uninhabitable.
2.3.4.5. Provide an on-site Quality Control Superintendent who shall be an onsite, full-time resource for this contract, for the duration of the Period of Performance. Quality Control Superintendent shall be a minimum of Level II certified and familiar with marine work. The Quality Control Superintendent shall be on-site and shall assist the Contractor’s Project Manager to ensure, maintain, and oversee Contractor quality.
Specific duties are included below:
2.3.4.5.1. Manage the Contractor’s quality for all work including material receipt, welding, piping, painting, electrical, testing, and retaining Material Test Reports (MTRs), etc.
2.3.4.5.2. Scheduling Contractor inspections with the Contractor, COR, Ship, and ABS.
QA Superintendent shall ensure accomplishment of Contractor pre-tests and that the Contractor is ready to present work to the COR and/or ABS at the scheduled time.
2.3.4.5.3. Scheduling ABS inspections and keeping survey reports
2.3.4.5.4. Maintaining ship cleanliness
2.3.4.5.5. Addressing any urgent cleaning and quality issues identified by COR.
2.3.4.5.6. Ensuring machinery and surrounding machinery components are covered and protected.
2.3.4.5.7. Attending production meetings
2.3.4.5.8. Providing a daily Inspection Schedule to the Contractor, COR, Chief Engineer, and CO no later than 1700 CDT on the day before the scheduled inspection.
Inspection schedule shall include all ABS call-outs, intermediate and final testing, and anything that will require the support of Ship’s Force (other than routine lock outs and tag outs) or the COR.
2.3.4.5.9. Compile and turnover to the COR a completed quality control package including all inspection reports, welding certifications, MTRs, test certificates, etc.
2.3.4.6. Provide an on-site full-time cleaning crew to maintain the ship and work area cleanliness for the duration of the Period of Performance. The cleaning crew shall be a minimum of one worker dedicated to maintaining ship cleanliness, decks/walkways, all vertical surfaces near work areas, horizontal surfaces near work areas, and all protective coverings. Cleaning crew shall report to the Quality Control Superintendent.
2.3.4.7. Five (QTY 5) days before scheduled Dock Trials, conduct a ship-wide cleaning to include but not limited to wiping down all surfaces and bulkheads on Main Deck and the Bridge, removal of all deck coverings, removal of all machinery coverings, cleaning of all ladderwells, cleaning the upper and lower engine room surfaces, and the final bilge cleaning.
2.3.4.8. Engine Room Bilge Cleaning – Remove all trash and debris from the engine room bilge and engine foundations and shall clean the engine room bilges by flushing with a fresh water and detergent solution (to remove all oil and other debris) and pump the bilges dry. Contractor shall dispose of all generated oily waste.
2.3.4.9. Paint all handrails on the ladderwells and touch-up all disturbed surfaces on bulkheads and decks that were the fault of the Contractor.
2.3.5. Quality Assurance
2.3.5.1. The contractor shall have documented plans for inspection, and documentation processes adequate for the scope of work being completed to ensure compliance with all requirements and references. Copies, Electronic and paper, to be provided.
2.3.5.2. Inspections in accordance with Reference 2.3.2.2.
2.3.5.3. Incremental in-process inspections are required by the contractor to ensure compliance by contractor and subcontractors.
2.3.6. Project Management
2.3.6.1. An on-site Project Manager, solely dedicated to completion of this contract, shall be provided by the contractor.
2.3.6.2. Project Manager will provide administrative support as needed for execution of the contract.
2.3.6.3. Project Manager will provide weekly status reports and tracking reports by time and date established by the COR, that reflect current statuses. Hardcopies and electronic copies to be provided.
2.3.6.4. Project Manager will support weekly status meets, and well as daily deckplate meetings to discuss plans of the day.
2.3.6.5. Project Manager will provide written Plan of the Day (POD) that clearly depicts expected efforts, start/stop times, Subs/vendor plans and status, material statuses, forecasted hot work for the following two days, impacted areas of the vessel due to work, specific areas where cleaning or other work will continue, etc. and other information deemed necessary by the COR. PAST dates for incomplete items with be updated using strikethrough and red test, leaving old dates in place. Hardcopies to be provides as well as electronic version sent evening prior to day.
2.3.6.6. Contractor to provide list of Long Lead Materials (anything greater than 7 calendar day in yard from ordering), by Work Item, Description, Population, Lead Time, shipyard need date, and expected arrival date. List to be updated weekly until arrival of vessel, at which time list to be incorporated into POD. Upon Arrival, list to be updated daily.
Contractor to update work execution plan for all items not anticipated to arrive by shipyard need date.
2.3.6.7. Contractor to provide digital Certs for items as CFRs, but also is to provide two copies of a Certification Binder for all items requiring certification or inspection certification or CFR. One Binder to be provided to COR and maintained shipboard as work progresses. Other binder to be delivered upon completion of work.
Additional Requirements:
Where coatings work is being performed, and unless specified otherwise:
All Bare steel (except internal to the fuel tank and underwater hull) to have Intershield 300HS or approved equivalent primer stripe coat on/near all edges and seams/joints, and a 300HS or approved equivalent primer full coat prior to application of other coatings. Inspection call-outs to the COR will occur for each step in the coatings process: measure chlorides and ensure they are not present, inspect coatings and prior to coatings, measure millage, etc. Each subsequent step will not occur until being approved by the COR. Intermediate coating will have stripe coat applied in manner described herein as well, prior to full coat. Contractor will propose minimum three coat system similar to AMC- 631-2d that is compatible with the existing coatings, and a system similar to STL-02 with added anti-fouling compatible with the existing ship’s antifouling for the underwater hull. PPG Pitthane Ultra Topcoat is the current topcoat in use by the crew in topside areas of structure, overheads, etc.
Contractor will provide containment, ventilation, and climate control to ensure expedient cure of coatings.
All surface preparation and painting work shall be accomplished in accordance with References and the specification herein, except for the type of coating used. All paint preparations and application shall be completed in accordance with QP1 Standards The Contractor may substitute QP1 by providing the services of a third party National Association of Corrosion Engineers (NACE) Level 2 or 3 qualified technical representative for the coatings products for supervision of surface preparation and coating system application. The technical representative shall be primarily used to observe the surface preparation, paint film thickness of coats, and to resolve technical difficulties such as allowable overcoat times, low ambient temperature or high relative humidity. All disturbed areas shall be prepared, primed and painted to match surrounding. NACE inspector if used will provide report of observations, data collection (millage, conditions, etc.), otherwise the contractor will provide report of same. All new and repaired coatings shall be warranted by the Contractor for a period of two years from the delivery of the ship, or two years from completion of Contract, whichever is later.
Paint with bright yellow paint markings suitable to the COR to indicate placement of all hull transducers, appendages, drains, some frame numbering, hull openings, etc. Provide proposed markings via drawing markup to the COR. Paint to be applied after all anti-fouling work is complete.
Each compartment will be subject to a “close out inspection” in the presence of the COR and ship representative, prior to the termination of work and the compartment being sealed by the contractor.
All work acceptance is subject to COR inspection.
COR will be present for all joint tightness tests and inspections. All new and disturbed joints are required to be hydrostatically tested, or alternative testing at the discretion of COR, and testing remains subject to acceptance of COR and ABS.
ACCIDENTS AND NEAR MISSES
The Contractor shall report to the COR and the vessel's designated Safety Officer any incidents of exposure or possible exposure to any hazardous substance and all accidents resulting in trauma, bodily injury, occupational disease, death, or environmental/equipment damage within one hour of occurrence. Near Misses are defined as incidents that did not result in injury but had the potential to result in injury if a person had been directly involved.
FORMAL DAMAGE REPORTS
The Contractor shall submit to the COR a full report of lost, damaged or destroyed items by Contractor employees to Government property, equipment, or the on-site environment. Formal reports shall be submitted to the COR and the vessel's designated Safety Officer within 24 hours of the occurrence.
CORRECTION PLAN
The Contractor shall submit to the COR a full correction plan, subject to approval by the COR when required by the COR, due to ACCIDENTS, NEAR MISSES, DAMAGE, SCHEDULE PERFORMANCE, CONTRACTOR PERFORMANCE, on site environment conditions, and/or similar. Formal reports/plans shall be submitted to the COR briefed by Contractor’s Project Manager.
End of section
3. BASE ITEMS
Annual Life Raft Inspection
References
NOAA Standard Specification AMC-583-1B, General Requirements for Life Raft Inspections
These specifications
Government Furnished Equipment: None additional
Requirements
Accomplish the annual inspection of the four (4) inflatable Mustang type life vest from the Fast Rescue Boat.
Accomplish annual inspection and certifications for six (6) total 20 and 25 person life rafts in accordance with all requirements. Provide CFR with findings/results of testing and inspection within 4 hours of findings.
Renew all expired life raft SOLAS Equipment Pack Items. For bidding purposes assume the cost of one complete 25-person life raft material will need replacing. Note this material will be used to replace any expired or defective material for found during the inspection and certification process.
Provide CFR with pricing for all items expired or defective.
Accomplish floor seam test and raft pressure tests as required by 46 CFR 160.151-57.
Replace the Hydrostatic Releases for the 6 life rafts with Contractor Furnished Equipment, equivalent to removed releases.
Contractor shall prepare, prime and paint the respective cradles at least 1 week prior to the life rafts being loaded back on the ship.
Quality Assurance
Certifications Required for: Each Life Vest, Life Raft, and Hydrostatic Release
The contractor shall provide CHECKPOINT Callouts for coatings surface preparations steps and coatings application steps.
The contractor shall take photos to documents the orientation of the life rafts in their cradles prior to removal. Provide labeled photos in a CFR to the COR.
Notes
5/6 Life Rafts were replaced 2023, one SOLAS pack was replaced 2023
End of Item
Survival Suit Inspection and Certification
NOAA Standard Specification AMC-583-1B, General Requirements for Life Raft Inspections
Government Furnished Equipment: None additional
Requirements
Accomplish the air testing on the 70 survival suits. Examination requirements and procedures for air testing can be found in USCG NVIC 01-08, or refer to manufacturer’s instructions.
Renew all expired SOLAS Equipment Pack Items. For bidding purposes assume the cost of 12 survival suits worth of expired or defective material. Note this material will be used to replace any expired or defective material found during the inspection and certification process, or other costs.
Provide CFR with pricing for all items expired or defective.
Quality Assurance
Provide inspection certificates for the 70 survival suits as CFR.
Notes - None Additional
Annual Miranda Inspection and Maintenance
MOC Standard Specification AMC-573-1C, “Testing of Davits and Weight Handling Gear.”
These Specifications
Government-Furnished Material (GFM): None
Requirements
Provide the services of a Factory Authorized Technical Agent (Palfinger Service Technician) to install parts, perform annual inspection, certify the installation, and test davit.
Remove all sheaves, pulleys, rollers, etc. from the arrangement for cleaning and servicing.
Thoroughly clean and degrease all components, and inspect for wear. Provide CFR of findings and recommendations. Wrap cables to prevent any contamination. Remove all items fastened to davit and appendages – repair all corroded areas by cleaning to bare white metal. Upon completion of all paint repairs, abrade and prep entire davit and recoat with primer and paint system (color to be black) to pe recommended by contractor and approved by COR. Remove cradle, and fully blast to clean white metal and paint cradle. Upon verification and rectification of any findings, and upon completion of paint, re-grease components and cable, and reassemble prior to continuing testing and certification. Sherwin Williams one-part marine zinc epoxy shall be the first coat. Mid-coats and top coats shall be dependent on location and match existing coatings. All repairs areas to be faired.
Contractor to propose coatings system to the COR.
Quality Assurance
Provide service report for the Davit with certification letter as CFR to the COR.
Certifications Required for: Replacement Components, and Boat Davit, Weight Test
The contractor shall take photos to documents the orientation of the FRB in the cradle and davit cables prior to removal. Provide labeled photos in a CFR to the COR.
Notes
Recommended sources for Palfinger certified inspectors:
3.3.8.1 Mike Resweber, Mike.Resweber@harding.no 1-337-256-9733 (phone)
Annual Fast Rescue Boat (FRB) Inspection and Maintenance
Code of Federal Regulations
These Specifications
Government-Furnished Material (GFM): Sponson ($45,000 value)
Requirements
Provide the services of a Factory Authorized Technical Agent to service, inspect, install parts, certify the installation and test FRB and ALL associated equipment. Replace FRB Sponson with GFE item. Have OEM provide and install additional anti-friction material to port and starboard areas where davit sling, etc. may make contact with the FRB. Provide marked up picture of current boat installed on davit in lowered position for approval for additional areas of material. Material to be same as other material on sponson. Provide a service report on the FRB motor maintenance as CFR to the COR. All Code of Federal Regulation and NOAA requirements for annual service and maintenance for the FRB and associate equipment shall be conducted and documented.
Remove the FRB and transport to a Factory Authorized Facility to perform the annual certifications and maintenance. Return the FRB to location of the ship (or alternate designated location) upon completion of service/inspections, and reinstall on the boat davit when all work on the vessel is complete.
Provide the services of a qualified firm to check and certify the Righting Bottle and corresponding mechanisms and perform inflation test. Provide separate hard and soft copy of certificate for the FRB self-righting bottle and the equipment to the COR.
Quality Assurance
Provide service report for the FRB with certification letter as CFR to the COR.
Certifications Required for: Replacement Components, and FRB inspection, Righting Bottle Inspection, Fire extinguisher(s) inspection, etc.
The contractor shall take photos to documents the orientation of the FRB in the cradle and davit cables prior to removal. Provide labeled photos in a CFR to the COR.
Notes
ZODIAC MILPRO certified inspectors and work performance is required. Contractor must provide bone-fide evidence that the servicer is certified by the OEM, and has OEM distributor relationship with OEM.
Annual Fire Inspection and Certifications
Drawing GU-555-001 Rev – “Fire Control Plan”
Drawing GU-555-6233815 Rev C “Fire Extinguishing System Diagrams
Drawing GU-436-6233675 Rev H “Fire & Smoke Detection System”
Diagrams Drawing GU-436-011 Fire Detection Installation (ABS)
Code of Federal Regulations
These Specifications
Technical Manuals
Government Furnished Material: None additional
Requirements
Portable Extinguishers: Inspect and weigh all portable extinguishers identified in references, including the discharge hose.
3.5.3.1.1 For bidding purposes assume 10% of each extinguisher type and size (weight/capacity) will require recharging and/or hydrostatic testing. Any quantities beyond that submit a condition found report on the number, type of action needed and costs.
3.5.3.1.2 Any extinguisher found to be rejected, for whatever reason shall be set aside. Submit a report to the COR identifying the extinguisher(s) found to be rejected and the reason(s) and cost to replace.
3.5.3.1.3 Upon completion, all portable extinguishers shall be returned to their designated stations or stowage locations in the case of spares. Certifications will indicate location of each extinguisher by serial number and item/identifier number, Fixed CO2 Systems: Main Motors and Paint Locker
3.5.3.2.1 Inspect and weigh fixed CO2 system cylinders coordinating with ship’s crew for availability to ensure that the crew can witness 100% of all bottle weighing and inspection.
3.5.3.2.2 Demonstrate all interlocks, shutdowns, time delays, automatic fire dampeners and controls operate correctly and verify intake and exhaust fans shutdown, and main motor breakers trip (Note: Main Motors must be online to verify breakers trip.
3.5.3.2.3 Submit a report to the COR identifying the size and number of cylinders requiring recharging or hydrostatic testing (If any), along with their location and serial numbers.
3.5.3.2.4 Inspect hoses between fixed cylinders and the distribution piping. Submit a report to the COR identifying any issues found and recommendations.
3.5.3.2.5 Inspect all fixed piping, nozzles and valves to ensure their satisfactory material condition. Connect an inert gas (nitrogen) to the system and blow-out the piping to prove it is clear.
3.5.3.2.6 Disconnect at the propulsion motor CO2 connection leading into each Propulsion Motor. Plug the connection at the motor to prevent foreign debris and moisture entering the motor.
3.5.3.2.7 Open and inspect check valves and corresponding filter screens just prior to the propulsion motor connection points, 2 check valves/screens on each motor. Clean the check valve and check for proper operation. Replace the screens/filters in each check valve.
3.5.3.2.7.1 Restore the check valves, screens and connections to the propulsion motors.
3.5.3.2.7.2 Demonstrate all interlocks, shutdowns, time delays, automatic fire dampeners and controls operate correctly.
3.5.3.2.7.3 After certifying the HALON 1301 system and placed in operation (see 3.5.6.4) the Contractor shall test the Main Motor operational shutdown. With the assistance of the CME the Main Motors will be placed online using the ship service diesel general to provide 20-30 RPM at the pier to verify proper shutdown of Main Motors with associated alarms when CO2 is activated.
Fixed Halon System: Ship’s Service Diesel Generator, Main Propulsion Room, Auxiliary Machinery Room/AC Flat, Emergency Diesel Generator and Bow Thruster.
3.5.3.3.1 Inspect and weigh fixed HALON system cylinders coordinating with ship’s crew for availability to ensure that the crew can witness 100% of all bottle weighing and inspection.
3.5.3.3.2 Demonstrate all interlocks, shutdowns, time delays, automatic fire dampeners and controls operate correctly and verify intake and exhaust fans shutdown. Coordinate with the ship’s crew to start the Ship Service Diesel Generators (SSDG’s) for testing (Note: SSDG’s must be running to test shutdowns).
3.5.3.3.3 Inspect hoses between fixed cylinders and the distribution piping, and ensure all hoses are marked with test dates that are within service life. Submit a report to the COR, identifying any issues found and recommendations. Submit a report to the COR, identifying any issues found and recommendations.
Accomplish inspection and testing of the GALLEY GAYLORD Hood system and associated heat sensing vent closure devices in the exhaust ducting, including over the oven, the fryer, and the griddle.
3.5.3.4.1 Prepare a Certificate of Servicing and report, listing the Gaylord Hood System and heat sensing vent closure devices, equipment, and components inspected and tested, and the results.
Submit the original and two (2) copies of the service report to the COR.
Fire/Heat/Smoke Detection System
3.5.3.5.1 Provide the service of an approved firm to provide the following services and certifications on this system.
3.5.3.5.2 Test all smoke and/or fire detection systems and demonstrate their proper functioning.
Upon completion of the tests and demonstrations, all systems shall be restored to normal operating configuration and left in a ready for use condition.
3.5.3.5.3 Testing shall include all smoke detectors using spray smoke and all heat detectors, and all pull stations.
3.5.3.5.4 Inspect all alarm bells for corrosion and verify proper operation.
3.5.3.5.5 Replace the two backup batteries in the detection panel, with new fully charged oem items and turnover old batteries to the ship’s CME.
3.5.3.5.6 Submit a condition report to the COR with test results and renewed annual certifications including the locally mount inspection stamp.
SCBA Respirators and Cylinders
3.5.3.6.1 Record serial numbers of each component per pack and the corresponding stowed location of equipment to ensure re-installation upon completion. Confirm with ship’s force all serial numbers. Packs not to be removed prior to confirmation.
3.5.3.6.2 Remove the SCBA equipment
3.5.3.6.3 Conduct a visual inspection of sixteen (16) SCBA Cylinders.
3.5.3.6.4 Conduct a flow test on eight (8) SCBA respirators and all regulators.
3.5.3.6.5 Conduct 3-year Hydrostatic test of the 16 SCBA Cylinders (AS REQUIRED) Last done in 2022.
3.5.3.6.6 3.4.6.7.3.1 Provide results of the Hydrostatic testing as a CFR.
3.5.3.6.7 Submit a condition report to the COR with findings and any recommendations. The report shall include the respective age of each bottle by location.
After completion of testing, all firefighting systems shall be reconnected, the cylinders properly secured in the bank, and the system left in a ready for use condition. Contractor will provide a callout to inspect systems being placed in service.
All extinguishers, hoses and fixed systems shall have tags attached indicating the date of service and the name of the firm, as well as the individual performing the servicing.
Quality Assurance:
Contractor will provide a detailed plan of action/schedule specific to this work item within 30 days of contract award and no later than 15 days prior to contract start.
Ship’s engineering personnel will witness testing/inspections, ABS attendance is required (funded by NOAA).
All extinguishers, hoses and fixed systems shall have tags attached indicating the date of service and the name of the firm performing the servicing. PROVIDE CFR WITHIN 24 HOURS IF HOSES
ARE FOUND WITHOUT TAGS OR NEED TO REPLACED/HYDROSTATIC TEST.
Test the fixed systems to the satisfaction of the attending ABS Surveyor, the COR, and to the requirements herein and in referenced documentation.
Prepare a Certificate of Servicing, listing all portable extinguishers and fixed systems examined and tested and the results of those tests and inspections. Deliver the original and two (2) copies of the report to the COR.
All fixed systems shall be inspected by the CME to ensure restoration to full operational capability.
Prepare a Certificate of Servicing and report, listing the Gaylord Hood System and heat sensing vent closure devices, equipment, and components inspected and tested, and the results. Submit the original and two (2) copies of the service report to the COR.
All personnel, shop or sub-contractors are to be trained at a manufacturer’s approved course and specialized in the inspection and repair of fixed and portable CO2, Halon, AFFF, dry chemical, fire main and sprinkling systems and equipment and be certified by the American Bureau of Shipping (ABS) to conduct these inspections. All inspections and testing shall comply with NFPA-10.
Adequate fire protection shall remain on the ship at all times during the performance of this item. No more than 10% of the portable extinguishers are to be removed from the vessel at any one time. The winning bidder may choose to remove greater than 10% of the portable extinguishers, so long as temporary (yard) extinguishers of the same type are provided in their place, at no additional cost to the government. Machinery spaces, vertical access and egress spaces, and spaces adjacent, shall not be removed without replacement. No fixed firefighting system shall be left in an inoperable condition overnight.
Annual Weight Testing of Lifting Appliances
References:
MOC Standard Specification AMC-573-1C, “Testing of Davits and Weight Handling Gear”
SFLC Standard Specification 6310 – Paint and Coatings
Steel Structures Painting Council Surface Preparation Specification No. 1 (SSPC-SP 1), "Solvent Cleaning”
Steel Structures Painting Council Surface Preparation Specification No. 3 (SSPC-SP 3), "Power Tool Cleaning
Steel Structures Paint Council Surface Preparation Specification No. 11 (SSPC-SP-11). “Power- Tool Cleaning to Bare Metal”
Government Furnished Equipment: None additional
Requirements
Provide the services of an OSHA certified test inspector, all necessary equipment (weights, load cell), and all ship’s weight handling gear and labor to weight test the following deck equipment in accordance with reference 3.2.2.1:
A-Frame – Rated 10000 lbs – Test 12500 lbs 10 min
J-Frame – Rated 2800 lbs – Test 3500 lbs 10 min
Main Deck Crane – Rated 7200 lbs – Test 9000 lbs 10 min
EFFER Crane (02 Level) – Rated 1340 lbs – Test 1675 lbs 10 min 3.6.7 General
Any welding, lifting gear overhauls and hydraulics work shall be completed before commencing weight testing.
Quality Assurance
Provide service report and certification letter as CFR to the COR.
Provide certified weight test certificates to the COR
Provide testing results in CFR as Register of Lifting Appliances in format as specified by COR.
Matrix of report vs equipment and/or gear vs stowed location, etc. to be provided for ease of validation of item vs reports.
Update lifting appliance placards with test data from CFR, including test date, test weight, and vendor witness of test.
All surface preparation and painting work shall be accomplished in accordance with References, except for the type of coating used. All paint preparations and application shall be completed in accordance with QP1 Standards The Contractor may substitute QP1 by providing the services of a third party National Association of Corrosion Engineers (NACE) Level 2 or 3 qualified technical representative for the coatings products for supervision of surface preparation and coating system application. The technical representative shall be primarily used to observe the surface preparation, paint film thickness of coats, and to resolve technical difficulties such as allowable overcoat times, low ambient temperature or high relative humidity. All disturbed areas shall be prepared, primed and painted to match surrounding.
Unless otherwise specified all surface preparation and coating systems shall follow References
Notes:
Recommended sources for OSHA certified inspectors: Crane Inspection Services, Inc.
Post Office Box 461 Fairhope, AL 36533 Ph: 251-928-6262 Fax: 251-990-6133 www.craneinspection.com Contact: James Pritchett Accredited For: FCD, SBMHD Area of Operation: National
Annual Navigation & Communication
NOAA Drawing 320-6629807 – Electrical One-Line Diagram for T-AGOS 18 AS-Built
Government Furnished Equipment: ABT/UPS components
Requirements
Provide the services of a Factory Authorized Technical Agent to service the following systems:
Furuno FAR 28X7 Series X-Band and S-Band Radars Transas Navi-Sailor ECDIS (2 systems)
GMDSS – Hybrid Sea-Area 3 system
AIS
SSAS
Sperry Autopilot NAVIPILOT 4000
Furuno DS-60 Speed Log
Fast Provide the annual service and system upgrades on the following systems:
• Furuno FAR 28X7 Series X-Band and S-Band…
This is the start of the file's text. The full file is on GovTribe.