About this file

This document is an Attachment IV - Pricing Schedule for a federal contract opportunity. It outlines the base items, optional items, and additional government requirements (AIRs) related to the FY25 Intermediate Dry Docking of the NOAA Ship Reuben Lasker.

The base items include routine dry docking, underwater body inspections, ABS/USCG inspections, preservation, maintenance, and servicing of various ship systems. The optional items relate to additional government requirements (AIRs) and growth work, with unit prices for labor rates and material markup/handling fees. There is also an optional item for a post-industrial berthing period. The total price is broken down into base items, growth, and options. Additional schedule rates are provided for temporary services and lay days.

The related federal contract opportunity is for the FY25 Intermediate Dry Docking of the NOAA Ship Reuben Lasker, with a solicitation number of 1305M224Q0280A. The opportunity is being issued by the Department of Commerce National Oceanic and Atmospheric Administration.

View the file

Other files for this federal contract opportunity

Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Priging Sheet Attachment IV

Price Schedule
BASE ITEMS
CLINSPEC WORK ITEMSPECIFICATION WORK ITEM TITLEQTYUNITUNIT PRICEEXTENDED PRICE
100010101Routine Dry Docking1JB$ -
100010102Underwater Body Inspections1JB$ -
100010103ABS/USCG Inspections Assistance1JB$ -
100010104Preservation of Underwater Body1JB$ -
100010105Hull Anode Replacement1JB$ -
100010106Propeller Clean & Polish1JB$ -
100010107Service Sea Valves1JB$ -
100010108Service/Inspect Cathelco Anti-Fouling and Impress Current System1JB$ -
100010109Ground Tackle Maintenance & Preservation1JB$ -
100010110Bow Thurster Inspections, Servicing and Grooms1JB$ -
100010111Inspect/Service Thrust, Line Shaft & Propulsion Motor Carrier Bearings1JB$ -
100010112Freeboard Preservation1JB$ -
100010113Inspect/Service MSD Tank1JB$ -
100010114Tank Preservation1JB$ -
100010115Clean & Test SSDG Heat Exchangers1JB$ -
100010116Annual Liferaft Inspection and Servicing1JB$ -
100010117Fire Inspection and Hydrostatic Testing1JB$ -
100010118Dock & Sea Trials1JB$ -
100010119Protective Coverings1JB$ -
100010120Weight Control1JB$ -
100010121Utilities and Services, Daily Rates Mooring/Drydock1JB$ -
100010122Deck Coating Maintenance1JB$ -
100010123Main Generator Room and Trawl Winch Room Bilge Cleaning1JB$ -
100010125Miscellaneous Piping Repairs1JB$ -
100010126Miscellaneous Welding and Fabrication1JB$ -
200020201Replace Deck Coverings1JB$ -
200020202Tail Shaft and Rudder Removal, Inspections and Repair1JB$ -
200020203Anti Roll Tank Repairs1JB$ -

Total Base Items: $ -

OPTIONAL ITEM - ADDITIONAL GOVERNMENT REQUIREMENTS
ADDITIONAL ITEM REQUIREMENTS (AIRs) These items relate to Growth Work. The Unit Price Column will be used throughout the life of the contract if growth work is added to the scope of the contract. If Additional Item Requests (AIRs) are issued, these items will be awarded at the quantities needed via a contract modification. The quantity shown is an estimate only and may be exceeded at the unit prices offered.
CLINSPEC WORK ITEMSPECIFICATION WORK ITEM TITLEQTYUNITUNIT PRICEEXTENDED PRICE
300030000AIRS/Growth (estimated)

AIRs/Growth Labor Rate

Unit Price: $[ ] ; Quantity: 3,350 ; Unit of Issue: Hour; Extended Price: $____________ESTHRS
AIRs/Growth Material Markup/Handling Fee

Unit Price: $20,000; Quantity: 1; Unit of Issue: Percent [ ]%;

Extended Price: [ $ X percentage quoted]: $______________EST
%%
Total ORF Growth:$ -
OPTIONAL ITEM - ADDITIONAL GOVERNMENT REQUIREMENTS
ADDITIONAL ITEM REQUIREMENTS (AIRs) These items relate to Growth Work. The Unit Price Column will be used throughout the life of the contract if growth work is added to the scope of the contract. If Additional Item Requests (AIRs) are issued, these items will be awarded at the quantities needed via a contract modification. The quantity shown is an estimate only and may be exceeded at the unit prices offered.
CLINSPEC WORK ITEMSPECIFICATION WORK ITEM TITLEQTYUNITUNIT PRICEEXTENDED PRICE
400040000AIRS/Growth (estimated)

AIRs/Growth Labor Rate

Unit Price: $ [ ] ; Quantity: 3,350 ; Unit of Issue: Hour; Extended Price: $____________ESTHRS
AIRs/Growth Material Markup/Handling Fee

Unit Price: $20,000; Quantity: 1; Unit of Issue: Percent [ ]%;

Extended Price: [ $ X percentage quoted]: $______________EST
%%
Total PAC Growth:$ -
Total Growth:$ -
OPTIONAL ITEM
Note: ThIs may be exercised in accordance with FAR Clause 52.217-7 “OPTION FOR INCREASED QUANTITY-SEPARATELY PRICED LINE ITEMS”.
CLINSPEC WORK ITEMSPECIFICATION WORK ITEM TITLEQTYUNITUNIT PRICEEXTENDED PRICE
500050000Post-Industrial Berthing Period14Day$ -
Total Options:$ -
BASE + GROWTH:$ -
BASE + GROWTH + OPTIONS:$ -
ADDITIONAL SCHEDULE RATES
CLINSPEC WORK ITEMProduct DescriptionQTYUNITUNIT PRICEEXTENDED PRICE
N/AN/AAdditional Temporary Services (See CAR 1352.271-89)1Day
N/AN/ALay Day (See CAR 1352.271- 86)1Day