This document is an Attachment IV - Pricing Schedule for a federal contract opportunity. It outlines the base items, optional items, and additional government requirements (AIRs) related to the FY25 Intermediate Dry Docking of the NOAA Ship Reuben Lasker.
The base items include routine dry docking, underwater body inspections, ABS/USCG inspections, preservation, maintenance, and servicing of various ship systems. The optional items relate to additional government requirements (AIRs) and growth work, with unit prices for labor rates and material markup/handling fees. There is also an optional item for a post-industrial berthing period. The total price is broken down into base items, growth, and options. Additional schedule rates are provided for temporary services and lay days.
The related federal contract opportunity is for the FY25 Intermediate Dry Docking of the NOAA Ship Reuben Lasker, with a solicitation number of 1305M224Q0280A. The opportunity is being issued by the Department of Commerce National Oceanic and Atmospheric Administration.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 1305M224Q0280 amd 0003.pdf | ||
| Sol_1305M224Q0280_Amd_0002.pdf | ||
| Attachment I - Reuben Lasker FY 25 Dry Dock SOW Rev-1.6.pdf | ||
| Attachment IX - Reference - TECHNICAL MEMORANDUM - REUBEN LASKER Stern Tube Leak Long Term Repair Plan REV A.pdf | ||
| Attachment VIII - GEK 91694C Vertical Drilling Motor Type GEB20.pdf | ||
| Attachment VII - Reference - 256-01-00003-010 Rev_-_ Heat Exchanger.pdf | ||
| Lasker Bow Thruster Motor Rev 3.pdf | ||
| 1305M224Q0280 Amendment 0001 SF 30 (11_2016).pdf | ||
| Attachment II Past Performance Information Form.pdf | ||
| 1305M224Q0280.pdf | ||
| Attachment VI - Deliverables List.docx | DOCX document | |
| Attachment III Past Performance Questionnaire.docx | DOCX document | |
| Attachment I Reuben Lasker FY25 Dry Dock SOW Rev-1.5.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Priging Sheet Attachment IV
| Price Schedule | ||||||
| BASE ITEMS | ||||||
| CLIN | SPEC WORK ITEM | SPECIFICATION WORK ITEM TITLE | QTY | UNIT | UNIT PRICE | EXTENDED PRICE |
| 1000 | 10101 | Routine Dry Docking | 1 | JB | $ - | |
| 1000 | 10102 | Underwater Body Inspections | 1 | JB | $ - | |
| 1000 | 10103 | ABS/USCG Inspections Assistance | 1 | JB | $ - | |
| 1000 | 10104 | Preservation of Underwater Body | 1 | JB | $ - | |
| 1000 | 10105 | Hull Anode Replacement | 1 | JB | $ - | |
| 1000 | 10106 | Propeller Clean & Polish | 1 | JB | $ - | |
| 1000 | 10107 | Service Sea Valves | 1 | JB | $ - | |
| 1000 | 10108 | Service/Inspect Cathelco Anti-Fouling and Impress Current System | 1 | JB | $ - | |
| 1000 | 10109 | Ground Tackle Maintenance & Preservation | 1 | JB | $ - | |
| 1000 | 10110 | Bow Thurster Inspections, Servicing and Grooms | 1 | JB | $ - | |
| 1000 | 10111 | Inspect/Service Thrust, Line Shaft & Propulsion Motor Carrier Bearings | 1 | JB | $ - | |
| 1000 | 10112 | Freeboard Preservation | 1 | JB | $ - | |
| 1000 | 10113 | Inspect/Service MSD Tank | 1 | JB | $ - | |
| 1000 | 10114 | Tank Preservation | 1 | JB | $ - | |
| 1000 | 10115 | Clean & Test SSDG Heat Exchangers | 1 | JB | $ - | |
| 1000 | 10116 | Annual Liferaft Inspection and Servicing | 1 | JB | $ - | |
| 1000 | 10117 | Fire Inspection and Hydrostatic Testing | 1 | JB | $ - | |
| 1000 | 10118 | Dock & Sea Trials | 1 | JB | $ - | |
| 1000 | 10119 | Protective Coverings | 1 | JB | $ - | |
| 1000 | 10120 | Weight Control | 1 | JB | $ - | |
| 1000 | 10121 | Utilities and Services, Daily Rates Mooring/Drydock | 1 | JB | $ - | |
| 1000 | 10122 | Deck Coating Maintenance | 1 | JB | $ - | |
| 1000 | 10123 | Main Generator Room and Trawl Winch Room Bilge Cleaning | 1 | JB | $ - | |
| 1000 | 10125 | Miscellaneous Piping Repairs | 1 | JB | $ - | |
| 1000 | 10126 | Miscellaneous Welding and Fabrication | 1 | JB | $ - |
| 2000 | 20201 | Replace Deck Coverings | 1 | JB | $ - |
| 2000 | 20202 | Tail Shaft and Rudder Removal, Inspections and Repair | 1 | JB | $ - |
| 2000 | 20203 | Anti Roll Tank Repairs | 1 | JB | $ - |
Total Base Items: $ -
| OPTIONAL ITEM - ADDITIONAL GOVERNMENT REQUIREMENTS | ||||||
| ADDITIONAL ITEM REQUIREMENTS (AIRs) These items relate to Growth Work. The Unit Price Column will be used throughout the life of the contract if growth work is added to the scope of the contract. If Additional Item Requests (AIRs) are issued, these items will be awarded at the quantities needed via a contract modification. The quantity shown is an estimate only and may be exceeded at the unit prices offered. | ||||||
| CLIN | SPEC WORK ITEM | SPECIFICATION WORK ITEM TITLE | QTY | UNIT | UNIT PRICE | EXTENDED PRICE |
| 3000 | 30000 | AIRS/Growth (estimated) |
AIRs/Growth Labor Rate
| Unit Price: $[ ] ; Quantity: 3,350 ; Unit of Issue: Hour; Extended Price: $____________ | EST | HRS | |
| AIRs/Growth Material Markup/Handling Fee |
Unit Price: $20,000; Quantity: 1; Unit of Issue: Percent [ ]%;
| Extended Price: [ $ X percentage quoted]: $______________ | EST | ||
| % | % | ||
| Total ORF Growth: | $ - |
| OPTIONAL ITEM - ADDITIONAL GOVERNMENT REQUIREMENTS | ||||||
| ADDITIONAL ITEM REQUIREMENTS (AIRs) These items relate to Growth Work. The Unit Price Column will be used throughout the life of the contract if growth work is added to the scope of the contract. If Additional Item Requests (AIRs) are issued, these items will be awarded at the quantities needed via a contract modification. The quantity shown is an estimate only and may be exceeded at the unit prices offered. | ||||||
| CLIN | SPEC WORK ITEM | SPECIFICATION WORK ITEM TITLE | QTY | UNIT | UNIT PRICE | EXTENDED PRICE |
| 4000 | 40000 | AIRS/Growth (estimated) |
AIRs/Growth Labor Rate
| Unit Price: $ [ ] ; Quantity: 3,350 ; Unit of Issue: Hour; Extended Price: $____________ | EST | HRS | |
| AIRs/Growth Material Markup/Handling Fee |
Unit Price: $20,000; Quantity: 1; Unit of Issue: Percent [ ]%;
| Extended Price: [ $ X percentage quoted]: $______________ | EST | |||
| % | % | |||
| Total PAC Growth: | $ - | |||
| Total Growth: | $ - |
| OPTIONAL ITEM | ||||||
| Note: ThIs may be exercised in accordance with FAR Clause 52.217-7 “OPTION FOR INCREASED QUANTITY-SEPARATELY PRICED LINE ITEMS”. | ||||||
| CLIN | SPEC WORK ITEM | SPECIFICATION WORK ITEM TITLE | QTY | UNIT | UNIT PRICE | EXTENDED PRICE |
| 5000 | 50000 | Post-Industrial Berthing Period | 14 | Day | $ - | |
| Total Options: | $ - |
| BASE + GROWTH: | $ - | |
| BASE + GROWTH + OPTIONS: | $ - |
| ADDITIONAL SCHEDULE RATES | ||||||
| CLIN | SPEC WORK ITEM | Product Description | QTY | UNIT | UNIT PRICE | EXTENDED PRICE |
| N/A | N/A | Additional Temporary Services (See CAR 1352.271-89) | 1 | Day | ||
| N/A | N/A | Lay Day (See CAR 1352.271- 86) | 1 | Day |
&"Arial,Bold"&11LAKE UNION DRYDOCK
File details come from the government source that posted it. Updated .