R5 Modoc NF Wide Bridge Rpr Mntnce RFI Log 3-13-2024.xlsx

XLSX spreadsheet 47 KB Posted

Attached to
MODOC NF Wide Bridge Repair Maintenance Solicitation
Solicitation number
12970224R0006
Issued by

About this file

This document contains a log of questions and responses related to a solicitation for bridge repair and maintenance work on 13 bridges throughout Modoc National Forest. The work includes approaches, channels, substructures, superstructures, decks, wearing surfaces, and traffic safety features. Bidders must furnish all labor, materials, equipment, and incidentals to complete the specified work. The required bid guarantee is 20% of the bid price or $200,000, whichever is less. RFIs are due 5 calendar days prior to the close of the solicitation in Mountain Time. Approved material sources have suitable aggregate base and riprap available. Replacement running plates must match existing galvanized steel dimensions of approximately 24 inches wide by Gauge 10 or 12.

View the file

Other files

File Type Posted
12970224R0006 Amendment 2.pdf PDF
12970224R0006- Amendment 1.pdf PDF
R5 Modoc NF Wide Bridge Rpr Mntnce RFI Log.xlsx XLSX spreadsheet
10. WD CA20230007 20240209.pdf PDF
4. Drawings.pdf PDF
3. Specifications.pdf PDF
2. SOW.pdf PDF
1. SOI.pdf PDF
8. 2850_Doublehead Mineral Material Sites.pdf PDF
9. 2850_WarnerMts_ Material_Sites.pdf PDF
7. 2850_Devils_Garden_MinMat_Sites.pdf PDF
6. 2850_All Mineral Material Sites.pdf PDF
5. 2850_All Big Valley Sites.pdf PDF
12970224R0006.pdf PDF
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

R5-Modoc NF Wide Bridge Rpr & Mntnce RFI Log
Updated3/13/24 8:23
RFI NumberRFI QuestionGovernment RFI ResponseNotes
1The bid bond amount says 100%, should this be 10% which is typical.The amount of the bid guarantee shall be 20% percent of the bid price or $200,000.00, whichever is less.
2Regarding the rail end treatments, there are 2 or 3 different types that can be used, do you have a specific one that is called out. Sorry I could not find it in the specs.We’re seeking a rounded, bull-nose style end section with breakaway assembly. The approach rail should flare out from the bridge rail and the end section should be offset from the edge of travelled way at least 3 feet.
3Could you please provide the sign-in sheet from the site visit?A sign-in sheet was not collected. There were 2 representatives in attendance, one from Larranaga Trucking, Inc. and one from Judd Buick Construction, Inc.
4
Please confirm if RFIs are due 5 calendar days or 10 calendar day prior to the close of the solicitation.RFI's will close 5 calendar days prior to the close of the solicitation.
5
Please confirm if RFIs are due 5 calendar days or 10 calendar day prior to the close of the solicitation.All times for submissions of offers and RFI's are in Mountain Time.
6Does the 50’ of AC also need new AB under it?Per drawing sheet 3, USFS requires a minimum AB depth of 6 inches. USFS-provided material sources have been identified to supply this when needed.
7Under wildlife conservation measures it states all previously painted members shall be repainted. Does this include every and all surfaces? Does this include the galvanized guard rail?Girders and guardrails are the members that need painting. Some of the galvanized rails were previously painted and USFS wishes to restore these to new condition and appearance. Members that were not previously painted do not require new paint.
8Botany mitigation measures. Can we clean the equipment at each site before moving to next or does in need to be hauled off to be washed?Equipment may be washed on site before moving on to the next location. Wash locations must be approved by the Forest Service in advance. Equipment should be loaded onto the transport trailer and then washed to ensure the site remains tidy and no contaminated mud is tracked off site.
9Do any of the provided Rock Sources have material suitable for use as the aggregate base course for the AC paved approaches? The included information seems to indicate that the only material available is cinders and/or crushed rock.Cottonwood, Deer Springs, Little Baldy, Telephone Flat, and West Warner have suitable aggregate base.
10Do any of the Rock Sources have the Class 4 or Class 5 Rip-Rap?Cottonwood, Deep Creek, Del Prat, Judge Pit, Little Baldy, West Warner have riprap available for mining though no stockpiles are available.
11Can you please provide the geographic coordinates for each bridge?BRIDGE NAMELATITUDELONGITUDE
--PARKER CREEK, SOUTH FORK41.44670555-120.2950583
--PARKER CREEK, UPPER41.42530278-120.2787361
--HIGGINS FLAT41.30502222-120.9056722
--JUNIPER CREEK41.06224-120.994189
--BARK SPRING41.46626667-121.0691195
--LOST RIVER41.98213056-121.1643667
--LASSEN CREEK41.82980834-120.2985639
--PIT RIVER, SOUTH FORK41.23186389-120.3966028
--TURNER CREEK41.418427-120.997337
--ASH CREEK - LOWER41.16048056-120.8300028
--ASH CREEK - UPPER41.12961389-120.7908944
--EAST CREEK41.17913334-120.2086556
--FOUR MILE41.91747778-120.8796139
12The description of work for the East Creek Bridge says to eliminate gaps between the gabions and abutment wall using fill materials. What is the material to be used for fill. The gabion is not clearly shown in the photo. Can you provide more details the gap to be filled?Due to the difficult-to-reach location between the structure and fill + gabion baskets, hand-placed rock and pumped grout is recommended.
13On the schedule of items, several of the bridges are requiring repairs to the running plates or replace in kind as necessary. What type of repairs need to be made to the running plates? Do you anticipate any running plates needing to be replaces? If running plates are to be replaced can you please provide details on the material and dimensions to be used?Several sections of running plate are loose, bent, and/or lacking fastening hardware. If running plates cannot be repaired and secured, they must be replaced. The material is standard diamond-plated steel approximately 24-inch width. Replacement material must be in-kind to match what remains. We believe existing material is mostly galvanized Gauge 10 or 12.

image1.jpeg image2.jpeg

File details come from the government source that posted it. Updated .