This document contains a schedule of items and specifications for bridge repair work on 13 bridges throughout the Modoc National Forest. The Forest Service is soliciting bids to perform maintenance and improvements on approaches, channels, substructures, superstructures, decks, wearing surfaces, and traffic safety features of the bridges. Work includes repairing embankments, pavement, concrete, drainage, railings, and other elements. Bidders shall provide all labor, materials, equipment and incidentals to complete the specified repairs and upgrades. Repair items are listed individually for each bridge and presented in priority order. The solicitation also includes optional upgrade items for bridge railings. Contractors should submit lump sum pricing for each repair item and optional item for all 13 bridges.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| R5 Modoc NF Wide Bridge Rpr Mntnce RFI Log 3-13-2024.xlsx | XLSX spreadsheet | |
| 12970224R0006 Amendment 2.pdf | ||
| 12970224R0006- Amendment 1.pdf | ||
| R5 Modoc NF Wide Bridge Rpr Mntnce RFI Log.xlsx | XLSX spreadsheet | |
| 10. WD CA20230007 20240209.pdf | ||
| 4. Drawings.pdf | ||
| 3. Specifications.pdf | ||
| 2. SOW.pdf | ||
| 8. 2850_Doublehead Mineral Material Sites.pdf | ||
| 9. 2850_WarnerMts_ Material_Sites.pdf | ||
| 7. 2850_Devils_Garden_MinMat_Sites.pdf | ||
| 6. 2850_All Mineral Material Sites.pdf | ||
| 5. 2850_All Big Valley Sites.pdf | ||
| 12970224R0006.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Forestwide Bridge Repair Modoc National Forest
Modoc & Lassen Counties
SCHEDULE OF ITEMS
ITEM
NO.
BRIDGE
NAME
DESCRIPTION
UNIT COST
573(01)-1 PARKER
CREEK,
SOUTH
FORK
Complete all repairs and improvements as described below and in specifications
Approaches Repair approach embankment fill (Shoulder near downstream side of abutment 2 has some erosion)
LS $
Approaches Pave bridge approaches 50’ on both approaches.
HMA: PG 64-28 binder w/ ½” minus aggregate;
minimum 2-inch depth.
LS $
Channel Clear hazard trees/snags LS $ Structure Replace and tighten hardware LS $ Wearing
Surface Repair running plates, replace in-kind as needed LS $
Parker Creek, South Fork Total $
573(01)-2 PARKER
CREEK,
UPPER
Complete all repairs and improvements as described below and in specifications
Approaches Pave bridge approaches 50’ on both approaches.
HMA: PG 64-28 binder w/ ½” minus aggregate;
minimum 2-inch depth.
LS $
Channel Remove hazard trees in channel upstream of bridge
LS $
Channel Restore channel to center of abutments (Creek flowing adjacent to Abutment 1)
LS $
Structure Place riprap (Class 4, est. 40 CY) around abutments LS $ Structure Clean wood-on-wood bearing locations to prevent moisture build up
LS $
Structure Replace and tighten hardware LS $ Wearing
Surface Repair running plates, replace in-kind as needed LS $
Parker Creek, Upper Total $
573(01)-3 HIGGINS
FLAT
Complete all repairs and improvements as described below and in specifications
Approaches Repair and extend bridge approach pavement to 50’ on both approaches.
LS $
HMA: PG 64-28 binder w/ ½” minus aggregate;
minimum 2-inch depth.
Channel Thin vegetation and trees in channel LS $ Structure Clean expansion joints LS $ Structure
Replace end deck beam on west edge at joint (6" x 8" x 15'8"), and first 3 damaged laminate deck boards
LS $
Structure Replace NE wing wall cap beam LS $ Structure Replace and tighten hardware (Some nuts missing) LS $ Wearing
Surface Repair running plates, replace in-kind as needed LS $
Higgins Flat Total $
573(01)-4 JUNIPER
CREEK
Complete all repairs and improvements as described below and in specifications
Approaches Repair approach embankment fill LS $ Approaches Repair and extend bridge approach pavement to
50’ on both approaches.
HMA: PG 64-28 binder w/ ½” minus aggregate;
minimum 2-inch depth.
LS $
Structure Replace and tighten hardware (Missing 1" nut and washer at Abutment 2 upstream wing wall, upstream column)
LS $
Wearing Surface
Repair running plates, replace in-kind as needed LS $
Juniper Creek Total $
573(01)-5
BARK
SPRING
Complete all repairs and improvements as described below and in specifications
Approaches Repair approach embankment fill LS $ Approaches Brush and clear approaches LS $ Approaches Pave bridge approaches 50’ on both approaches.
HMA: PG 64-28 binder w/ ½” minus aggregate;
minimum 2-inch depth.
LS $
Channel Armor (Class 5 riprap, est. 40 CY) south abutment to shift channel back to center of span and eliminate scour pool
LS $
Structure Clean expansion joints LS $ Structure Replace and tighten hardware LS $ Structure Clean structure of bird nests and other debris LS $ Wearing
Surface Repair running plates, replace in-kind as needed LS $
Bark Spring Total $
573(01)-6
LOST RIVER
Complete all repairs and improvements as described below and in specifications
Approaches Repair approach embankment fill and touch up approaches (Minor fill loss/erosion at NE abutment)
LS $
Structure Patch/repair concrete on abutments LS $ Structure Replace and tighten hardware (Some nuts missing on abutment, deck clamps to be tightened)
LS $
Structure Clean bridge LS $ Traffic
Safety Features
Replace load rating signs LS $
Wearing Surface
Repair running plates, replace in-kind as needed LS $
Lost River Total $
573(01)-7 LASSEN
CREEK
Complete all repairs and improvements as described below and in specifications
Approaches Brush and clear approaches LS $ Approaches Pave bridge approaches 50’ on both approaches
(bridge is at intersection, pave both road approaches on both sides of bridge). HMA: PG 64- 28 binder w/ ½” minus aggregate; minimum 2-inch depth.
LS $
Channel Brush channel to prevent obstruction LS $ Structure Clean Deck LS $ Structure Patch/repair concrete in all locations where scaling, spalling, delamination, or other damage has occurred
LS $
Structure Clean (Substructure is moist and growing algae) LS $ Lassen Creek Total $
573(01)-8 PIT RIVER,
SOUTH
FORK
Complete all repairs and improvements as described below and in specifications
Approaches Repair approach embankment fill (Minor erosion off roadway at end walls is narrowing the roadway and backfill settlement is contributing to potholes at edge of deck)
LS $
Approaches Brush along shoulders and in channel adjacent to abutments
LS $
Approaches Pave bridge approaches 50’ on both approaches.
HMA: PG 64-28 binder w/ ½” minus aggregate;
minimum 2-inch depth.
LS $
Structure Clean deck, expansion joints and bearing devices LS $ Structure Patch/repair concrete in all locations where scaling, spalling, delamination, or other damage has occurred (deck, wing walls and curbs)
Structure Clean bridge LS $ Pit River, South Fork Total $
573(01)-9 TURNER
CREEK
Complete all repairs and improvements as described below and in specifications
Approaches Repair and armor (Class 4 riprap, est. 50 CY) abutments/embankment
LS $
Approaches Pave bridge approaches 50’ on both approaches.
HMA: PG 64-28 binder w/ ½” minus aggregate;
minimum 2-inch depth.
LS $
Structure Patch/repair concrete in all locations where scaling, spalling, delamination, or other damage has occurred
LS $
Turner Creek Total $
573(01)-
ASH CREEK
- LOWER
Complete all repairs and improvements as described below and in specifications
Approaches Improve drainage on approaches, add rolling dip on south side
LS $
Approaches Repair asphalt and patch potholes at SW approach, Repair and extend bridge approach pavement to 50’ on both approaches.
HMA: PG 64-28 binder w/ ½” minus aggregate;
minimum 2-inch depth.
LS $
Channel Restore channel (Thalweg has shifted near abutment 1 and stream water is in contact with the abutment)
LS $
Structure Patch/repair concrete in all locations where scaling, spalling, delamination, or other damage has occurred
LS $
Structure Armor abutments with riprap (Class 5, est. 40 CY) LS $ Ash Creek – Lower Total $
573(01)-
ASH CREEK
- UPPER
Complete all repairs and improvements as described below and in specifications
Approaches Brush and clear approaches LS $ Approaches Pave bridge approaches 50’ on both approaches.
HMA: PG 64-28 binder w/ ½” minus aggregate;
minimum 2-inch depth.
LS $
Structure Patch/repair concrete in all locations where scaling, spalling, delamination, or other damage has occurred
LS $
Structure Armor piers with riprap (Class 5, est. 40 CY) LS $ Ash Creek – Upper Total $
573(01)-
12 EAST CREEK
Complete all repairs and improvements as described below and in specifications
Approaches Clean and brush culvert under entrance to 38N23, improve drainage to prevent ditches from draining to abutments
LS $
Approaches Pave bridge approaches 50’ on both approaches.
HMA: PG 64-28 binder w/ ½” minus aggregate;
minimum 2-inch depth.
LS $
Channel Brush and clear near abutments and piers, clear aspens from under bridge at back wall
LS $
Structure Eliminate gaps between gabions and abutment back walls (fill with additional material to mitigate erosion and water/animal intrusion)
LS $
Structure Patch/repair concrete in all locations where scaling, spalling, delamination, or other damage has occurred
LS $
East Creek Total $
573(01)-
13 FOUR MILE
Complete all repairs and improvements as described below and in specifications
Approaches Pave bridge approaches 50’ on both approaches.
HMA: PG 64-28 binder w/ ½” minus aggregate;
minimum 2-inch depth.
LS $
Structure Patch/repair concrete in all locations where scaling, spalling, delamination, or other damage has occurred
LS $
Structure Clean deck and steel members LS $ Four Mile Total $
Base Items Total $
Option Items:
556(01) PARKER
CREEK,
SOUTH
FORK
Upgrade/install railing end treatments to meet current code requirements
LS $
556(02) PARKER
CREEK,
UPPER
Upgrade/install railing end treatments to meet current code requirements
LS $
556(03)
HIGGINS
FLAT
Upgrade/install railing end treatments to meet current code requirements, repair missing/cracked spacers and delineators along railing
LS $
556(04) JUNIPER
CREEK
Upgrade/install railing end treatments to meet current code requirements
LS $
556(05) BARK
SPRING
Upgrade/install railing end treatments to meet current code requirements
LS $
556(06) LASSEN
CREEK
Upgrade/install railing end treatments to meet current code requirements, repair downstream vehicle damage on railing (downstream side of abutment 1 Install bridge approach rails to meet current code requirements
556(07) PIT RIVER,
SOUTH
FORK
Upgrade/install railing end treatments to meet current code requirements
LS $
556(08) TURNER
CREEK
Upgrade/install railing end treatments to meet current code requirements
LS $
556(09) ASH CREEK
- UPPER
Upgrade/install railing end treatments to meet current code requirements
LS $
556(10)
EAST CREEK
Upgrade/install railing end treatments to meet current code requirements
LS $
556(11)
FOUR MILE
Upgrade/install railing end treatments to meet current code requirements Repair damage at rail connection near NW abutment
Total Option Items $
Total with all options $
NOTE: ITEMS ARE IN ORDER OF PRIORITY AND WILL BE AWARDED SUBJECT
TO FUNDING AVAILABILITY