Attachment_1_SOW.pdf

PDF 161 KB Posted

Attached to
Dixie National Forest SO Construction Federal contract opportunity
Solicitation number
1284N819R0002
Issued by
Department of Agriculture Forest Service R4-Intermountain Region

View the file

Other files for this federal contract opportunity

Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GENERAL SPECIFICATIONS/ STATEMENT OF WORK

DIXIE NF SUPERVISOR’S and CEDAR CITY RANGER DISTRICT OFFICE

1.1 SCOPE OF CONTRACT

This Project consists of constructing a new Supervisor’s and Ranger District Office. The work will include construction of utilities, parking lots, sidewalks, plaza, storm drainage structures, landscaping, signage, lighting, irrigation and site furniture. The new Supervisor’s Office is located on Forest Service owned property.

1. Demolition Work is shown in plans and noted in specifications and includes the following:

a. Pulverizing and stockpiling the existing unreinforced concrete road and parking areas on site. The material may be reused as road base on the project. Concrete with rebar will not be used as fill

b. Reuse of existing fencing and new fencing (if needed) to secure the contractor’s work area and isolation of the work site. Demo portion of the fencing at work conclusion as shown on the plans.

c. Removal of some existing trees and vegetation and recycling and disposal of materials.

d. Removal, capping and abandonment of exiting utilities, including water, sewer, communications and electrical.

e. Removal and/ or relocation of existing utility poles (Contract shall coordinate with the appropriate utility provider.)

f. Abatement and disposal of asbestos containing materials in the existing Oil and Gas House and WCF Maintenance Garage.

g. Removal and safe disposal of hazardous materials in the existing buildings including:

mercury containing items, CFC containment, and any other items noted in plans in the Sign Shop, Oil and Gas House and WCF Maintenance Garage.

h. Demolition, recycling, salvage and disposal of the “WCF Garage” facility as shown on the plans.

i. Demolition, recycling, salvage and disposal of the Sign Shop facility as shown on the plans.

j. Demolition, recycling and salvage of the Oil and Gas House Facility as shown on the plans.

2. The BLM has maintenance operations and other facilities at the east of the Forest Service site that shall remain in place and operational during construction. Access to these areas must be maintained during construction.

3. New construction work is shown in the plans and noted in the specifications and includes the following:

a. Coordination, documentation, supervision and assistance to meet the requirements for achieving two Green Globes as defined by the Green Building Initiative and as shown in the contract documents.

b. Personnel, documentation and assistance to implement Whole Building Commissioning process for the project. The contract package includes a commissioning plan and checklists

c. Disposal, recycling and salvage operations.

d. Erosion and sedimentation control.

e. Site grading, fill and material disposal as shown in the drawings and specs and noted in the

Geotechnical Report.

f. All staging, earthwork, trenching and site prep shall be in accordance with drawings, specifications and the Geotechnical Report.

g. Fencing: salvage and new (as needed) of the contractor’s work area and isolation of the work site.

h. Trenching, bedding and installation of new site utilities including, impact fees, connections, water, sewer, storm water and services for a new building. Include water lines/laterals, fire hydrants, water meter, curb valve and boxes, concrete vault, concrete manhole, and modifications to the existing systems.

i. Installation and construction of deep wells for ground source heating systems for the facility as shown in the documents.

j. Construction of an on-site detention basins, with outlet control structures.

k. Installation of concrete flatwork, decorative elements, sidewalks, dumpster pads, and curbs.

l. Construction of new asphalt parking lots, reuse of pulverized site material, access to 100 E, with site lighting, striping and signage as shown in the drawings and noted in the specifications.

m. Installation of irrigation systems, seeding, plantings, mulch, weed control, trees, curbing, landscape boulders, retaining walls and other landscaping items shown in the plans and noted in the specifications.

n. Installation of exterior flagpoles, kiosks, signage, site identification sign, picnic tables, and bike racks.

o. Trenching bedding and installation of electrical and communications service, transformers, temporary power, impact fees, and site lighting.

p. Construction of a 15,800 SF, wood framed Supervisor’s and Ranger District Office for the Dixie National Forest. Work for the building will include, but is not limited to: concrete footings and foundations, excavation of poor soils, structural fill, concrete slabs, wood framed walls, and roof joists, insulation, drainage structures, pipe composite siding, cast stone masonry siding glulam framing members, structural steel columns, beams and connections, wood decking, fire sprinkler system, drywall, painting, ceramic tile, resilient flooring and accessories, fire stopping, carpet, acoustical dropped ceilings, wood casework, solid surface counters, plastic laminate, and finish carpentry, cabinetry, aluminum clad wood windows, roller shades, light shelves, shade structures, hollow metal and wood doors, door hardware, painting, staining and transparent finishes, showers, faucets, drinking fountains, toilets, urinals, toilet partitions, sinks, appliances, fan coil units, variant refrigerant flow heating and cooling systems, heat pumps, HVAC controls, ductwork, dampers, louvers, fans, pumps, valves, piping, sump pumps, electrical lines, occupancy detectors, outlets, lighting, communications, public address and white noise systems, projectors, and other items noted in the specifications and shown in the drawings.

1.2 PROJECT LOCATION

The project site is located within the city of Cedar City, UT at 820 N Main Street on Forest Service Property. The site is located in Iron County.

1.3 SITE INFORMATION AND LIMITATIONS

The following site conditions are considered incidental to the contract and the contractor will not be paid directly for any of the following items:

1. The contractor shall have full use of the premises for construction operations, including the use of the Project site during the construction period. The Contractor’s use of the premises is limited only by the Government’s right to perform work or to retain other contractor’s on portions of the Project.

2. Except as noted herein, the construction site for the new building will be closed to the public during construction. The Contractor will be responsible for fencing, signing and limiting public access.

Access shall be maintained to the facilities at the east of the Forest Service property through construction except as approved by the Contracting Officer for the purpose of reconstructing the access roads and parking areas. At least one access road shall be maintained at all times.

3. The Contractor shall not disrupt existing utility service (water, power, telecom, sewer, etc.) to and within the compound without coordination and approval in writing from the Contracting Officer’s Representative. Provide 48 hours’ notice prior to disrupting utilities to the other occupied areas of the site.

4. Water is available at the site for construction purposes. The contractor is responsible for any temporary connection hardware.

5. Electricity is available at the site for construction purposes. The Contractor will be responsible for coordinating the installation of temporary power for the site and the cost for the service.

6. Telephone service is not available, and shall be the contractor’s responsibility.

7. Sewer lines are available to the contractor, if desired.

8. The Contractor shall provide temporary toilet facilities (porta-potties) at the site during all construction work. Toilet facilities shall be provided at a rate of one stool for every 10 workers assigned or working on site with a minimum of one required.

9. All construction equipment shall be pressure washed before entering the Site. The removal of mud and debris from treads, tracks and undercarriage, with emphasis on axles, frame, cross-members, motor mounts, and underneath steps, running boards, and front bumper/brushguard assemblies will be required. The purpose is to reduce or eliminate the transportation of noxious weeds, which is required by Federal and State regulations.

10. The contractor shall inform and enforce an “Anti-Idling” policy for vehicles on the site that requires vehicles will not idle for more than 2 minutes on the site. The contractor shall inform subcontractors and deliveries of this policy.

11. Work hours allowed shall be Monday-Friday 7AM-7PM. The contractor may work weekends if needed, 8AM-7PM.

1.4 GENERAL SITE CONDITIONS AND WEATHER

1. The elevation of the site is approximately 6300 feet above sea level. The construction site experiences very cold temperatures with snow on the ground from October to April. Summer temperatures are moderate and rarely exceed 90 degrees.

2. In depth soil surveys have been performed and are available as an attachment to the specifications.

See Geotechnical Report, prepared by GSH Engineering, SLC, UT, October 2018.

3. The contractor shall review the water table information included in the geotechnical study.

1.5 TRAFFIC CONTROL AND CONSTRUCTION SIGNING

A. No work that endangers, interferes, or conflicts with traffic or access to work sites shall be performed until a plan for satisfactory warning and handling of traffic has been submitted by the contractor and approved by the CO and Local Transportation Authority. Construction signing for traffic control shall conform to the Manual of Uniform Traffic Control Devices (MUTCD). All traffic control signs will be placed in areas adequate for a truck pulling a fifth wheel trailer to be turned around. Contractor shall not be paid directly for this item, rather it will be considered incidental to other items of work listed in the Schedule of Items.

B. Signing and barricades shall be adequate enough to protect Forest Service employees and public. The contractor shall take special care to adequately sign and protect areas of work and construction from persons using these areas.

1.6 WORK CAMPS, STAGING AND STORAGE AREAS

A. Areas for staging operations and storage of materials shall be approved by the CO. The Contractor must request in writing for approval from the CO to stage work trailers on site. Overnight camping on site will not be allowed.

B. Confine storage of materials and equipment as approved by the Contracting Officer. The Contractor is responsible for the security of all personal equipment and materials.

C. Contractor shall maintain access to the facilities for Forest Service contracting personnel.

D. No fuel storage is permitted on the site. Fuel trucks must be equipped with spill containment kits and portable berms that meet State and Federal regulations

1.7 INSPECTION OF WORKSITE

The contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work, and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.

1.8 CONTRACT TIME: 450 Calendar Days from Issuance of Notice to Proceed and ready for occupancy by March 31, 2021. Project is anticipated to start August 2019

1.9 COORDINATION:

Coordinate installation with the utility division for the Town of Cedar City, Public Works Department.

716 N. Airport Rd., Cedar City, UT 84720 ,Phone: (435) 586-2912

1.10 MEASUREMENT AND PAYMENT/ DESCRIPTION OF BID ITEMS:

A. BASE BID A: See specification Section 001900, Mobilization for Bid Item description of mobilization and bonding.

B. BASE BID B: See specification Section 024117, Section 024230 and the drawings for a description of the Bid Item to remove and dispose of hazardous and asbestos materials for the existing structures.

C. BASE BID C: See specification Sections 024100, Section 024116 and the drawings D101 and D102 for a description of the Bid Item to demolish the facilities including the WCF Maintenance facility, 2 sheds, the Oil and Gas House, and Sign Shop. Include roofs, walls, interior build out, foundations, slabs, windows, doors, and other components to completely remove the facilities. Include salvage, removal and disposal, of the materials.

D. BASE BID D: See specifications and drawing C-01 for a description of the Bid Item for site demolition.

Include all site demolition including removal / pulverizing of pavements, sidewalks, concrete pads, retaining walls, landscaping, gates, fencing, storm drains and lines, hydrants, waterline, oil and water separator line, curb and gutter, and salvage of the antique grader.

E. BASE BID E: See specifications and civil drawing sheets for requirements for the Bid Item for earthwork including: sedimentation control, surveying, staking, clearing, grubbing, excavation, hauling, fill, grading, compaction, testing, etc.

F. BASE BID F: See specifications and civil drawing sheets for the requirements for the Bid Item for civil utility installation: Include concrete vaults, thrust blocks, inlet boxes, manholes, water system (valves, piping, sanitary sewer system, fire hydrants and the storm sewer system.

G. BASE BID G: See specification Section 012500: Utility Company Coordination for line item description of connection fees and work for utility connection. Utility connections include water, sewer, storm drain and electrical. This item includes fees and hours only, materials costs are in other line items below.

H. BASE BID H: See specifications and Site electrical drawings sheets ES001 and ES002 for the description of the Bid Item electrical site work. Include all electrical site demolition and construction including exterior lighting, transformer, poles, vaults, radio tower, conductor, grounding, sensors, etc.

I. BASE BID I: See specifications and civil drawing sheets for the Bid Item for all asphaltic pavements, striping, concrete curb and gutter, vehicle approach, dumpster pad (trash enclosure), sidewalk, concrete pads, concrete retaining walls, signs, wheel stops. Do not include the work shown on the drawings for optional bid item 1, the east secured parking area.

J. BASE BID J: See specification Section 000501 and the drawings for the description for bidding and pricing the complete Office Building.

K. BASE BID K: See Specification Sections 232113, 23213.33 and 232113.34 and the geothermal drawings MS-01, MS-02 and MS-03 for a description of the bid item to construct geothermal wells, piping, earthwork and materials to provide complete geothermal well system 10’ beyond the building perimeter.

L. BASE BID ITEM L: Provide and Install a Forest Service Site ID sign as described Section 101420 and shown in the drawings.

1.11 OPTIONAL BID ITEMS:

A. OPTIONAL BID ITEM 1: See the specification and the Civil Engineering Drawings for the work for the Bid Item to construct the east Secured Government parking lot. Include all work shown in the dashed line on sheet C-02. Include all electrical work, conduit, site lighting as shown in the site lighting plans

B. OPTIONAL BID ITEM #2: Site furnishings: Provide and install the bulletin board, flag pole, 3 bicycle racks, and 4 wood picnic tables as described in spec sections 101425, 107516, and 129300 and shown in the drawings.

C. OPTIONAL BID ITEM #3: Landscaping: Provide and install irrigation system, Perimeter drainage structure, Plants, boulders, Planting media, drystack retaining walls, landscape stone, wood mulch, weed barrier and steel edging. Review Sections 328000, 329220, 329310 and 329400.

1.12 DRAWINGS:

A. The complete list of drawings includes the following:

1. G1: Cover Sheet

2. G2: Drawing Index

3. D101: Site Demolition Plan, Sign Shop Building/ Oil and Gas Building Demolition

4. D102: Maintenance Building Demolition

5. C-01: Existing Site Conditions & Demolition Plan

6. C-02: Site construction and Utility Plan

7. C-03 Site Grading Plan

8. CD-01: Detail Sheet 1

9. CD-02: Detail Sheet 2

10. CD-03: Detail Sheet 3

11. CD-04: Detail Sheet 4

12. CD-05: Detail Sheet 5

13. CD-06: Detail Sheet 6

14. L-01: Landscape Plan

15. L-02: Landscape Berm Layout Plan

16. IR-01: Irrigation Plan

17. IR-02: Irrigation Details

18. D-01: Site ID Sign, Dry Stack Retaining Wall, Berm Construction Details

19. D-02: Bulletin Board, Flag Pole, Bike Rack Details

20. D-03: Picnic Table, Edging, Planting Details

21. G101: Code Analysis

22. GA101: Accessibility Standards

23. A101A: Footing and Foundation Plan A

24. A101B: Footing and Foundation Plan B

25. A102A: Office Floor Plan A

26. A102B: Office Floor Plan B

27. A103A: Framing Floor Plan A

28. A103B: Framing Floor Plan B

29. A104A: Finish Floor Plan A

30. A104B: Finish Floor Plan B

31. A105A: Reflected Ceiling Plan A

32. A105B: Reflected Ceiling Plan B

33. A106A: Roof Plan A

34. A106B: Roof Plan B

35. A201: Office Elevations

36. A202: Office Elevations

37. A301: Building Sections

38. A302: Building Sections

39. A303: Building Sections

40. A304: Building Sections

41. A305: Building Sections

42. A306: Building Sections

43. A401: Enlarged Floor Plans

44. A402: Enlarged Floor Plans

45. A403: Interior Elevations

46. A404: Interior Elevations

47. A405: Interior Elevations

48. A501: Architectural Details

49. A502: Architectural Details

50. A503: Roof Details

51. A504: Roof Details

52. A505: Floor and Ceiling Details

53. A506: Door and Window Details

54. A507: Millwork and Cabinet

55. A508: Millwork and Signage Details

56. A701: Wall Types

57. A801: Door/ Frame Schedules and Types

58. A802: Hardware Schedule

59. A803: Window Elevations

60. A901: Finish Schedule and Legend

61. A902: Accessory Schedule and Signage

62. S001: Structural Notes

63. S002: Structural Notes (Cont)

64. S003: Schedules

65. S004: Schedules

66. S005: Schedules

67. S006: Schedules

68. S101: Footing and Foundation Plan, Grid M to E

69. S102: Footing and Foundation Plan, Grid E to A

70. S103: Roof Framing Plan Grid M to E

71. S104: Roof Framing Plan Grid E to A

72. S105: Entrance Framing Plan

73. S201: Typical Details

74. S202: Typical Details

75. S203: Details

76. S204: Details

77. S205: Details

78. S206: Details

79. S207: Details

80. MS-01: Geothermal Site Plan

81. MS-02: Geothermal Details

82. MS-03 Geothermal Details

83. MS-04: Geothermal Drilling Log

84. P001: Plumbing Legend, Schedules and Notes

85. P101: Plumbing Plan

86. P102: Waste and Vent Plan

87. P401: Enlarged Plumbing Plan

88. P402: Enlarged Waste and Vent Plan

89. P501: Plumbing Details

90. M001: Mechanical Legend, Schedules and Notes

91. M002: Mechanical Legend, Schedules and Notes

92. M101: Mechanical Plan

93. M102: Mechanical Refrigerant Piping Plan

94. M401: Enlarged Mechanical Plans

95. M501: Mechanical Details

96. E001: Electrical Legend, Notes, and Panel Schedules

97. E002: Service Block Diagram and Lighting Controls

98. E003: Lighting Controls, Continued and Main Conference Room AV Details

99. E101: Receptacle Floor Plan

100. E201: Telecommunications Floor Plan

101. E301 : Lighting Floor Plan

102. E401: Mechanical Power

103. E501: Security and Intercom Systems

104. ES001 Electrical Exterior Demolition

105. ES101 Electrical Exterior Site Plan

1.13 SPECIFICATIONS

A. The following specifications are attached. Some sections in the schedule of items refer to other sections not listed and are subsidiary to, or are included in payment for other pay items in this contract. These items are considered incidental and no additional compensation will be made.

Section 000501 - Office Building Section 010250 - Construction Staking Section 011250 - Measurement And Payment With Asphalt Section 011900 - Mobilization Section 012500 - Utility Company Coordination Section 013100 - Project Management And Coordination Section 013300 - Submittal Procedures Section 014130 - Contractor’s Quality Control Section 015000 - Temporary Facilities And Controls Section 017419 - Construction Waste Management And Disposal Section 017700 - Closeout Procedures Section 018109 - Testing For Indoor Air Quality Section 018113.53 - Sustainable Design Requirements - Green Globes Section 019113 - General Commissioning Requirements Section 023701 - Sediment And Erosion Control Measures Section 024100 - Waste Material Disposal

Section 024116 - Structure Demolition Section 024117 - Hazardous Waste Disposal Section 024230 - Asbestos Abatement Section 033000 - Cast-In-Place Concrete Section 033510 - Polished Concrete Finishing Section 033545 - Concrete Sidewalks And Curb & Gutters Section 047200 - Cast Stone Masonry Section 051200 - Structural Steel Framing Section 055000 - Metal Fabrications Section 061000 - Rough Carpentry Section 061500 - Wood Tongue And Groove Decking Section 061600 - Sheathing Section 061753 - Shop-Fabricated Wood Trusses Section 061800 - Glued-Laminated Construction Section 062013 - Exterior Finish Carpentry Section 062023 - Interior Finish Carpentry Section 064116 - Plastic-Laminate-Faced Architectural Cabinets Section 071113 - Dampproofing Systems Section 072100 - Thermal Insulation Section 073216 - Concrete Roof Tile Section 074646 - Fiber-Cement Siding And Soffit Section 076200 - Sheet Metal Flashing And Trim Section 078413 - Penetration Firestopping Section 079200 - Joint Sealants Section 081113 - Hollow Metal Doors And Frames Section 081416 - Flush Wood Doors Section 082143 - Out-Swing Entry Doors Section 083113 - Access Doors And Frames Section 084113 - Aluminum-Framed Storefront Section 085200 - Aluminum Clad Wood Windows Section 087100 - Door Hardware Section 088000 - Glazing Section 088700 - Window Security Film Section 092900 - Gypsum Board Section 093000 - Tiling Section 095113 - Acoustical Panel Ceilings Section 096513 - Resilient Base And Accessories Section 096519 - Resilient Tile Flooring Section 096813 - Tile Carpeting Section 097700 - Special Wall Finishes Section 099123 - Interior Painting Section 099300 - Staining And Transparent Finishing Section 099600 - High-Performance Coatings Section 099735 - Dry-Erase Coating Section 101400 - Exterior Signs Section 101419 - Dimensional Letter Signage Section 101420 - Administrative Identification Sign – As (Hdpe) Section 101423 - Panel Signage Section 101425 - Panel Bulletin Board / Log Stanchion Section 101550 - Toilet Compartments Section 102116 - Shower Surrounds Section 102800 - Toilet And Bath Accessories

Section 105113 - Metal Lockers Section 105201 - Fire-Protection Specialties Section 107516 - Ground-Set Flagpoles Section 113100 - Residential Appliances Section 115213 - Projection Screens Section 122413 - Roller Window Shades Section 122600 - Interior Daylighting Devices Section 124813 - Entrance Floor Mats, Grilles, And Frames Section 129300 - Site Furnishings Section 211313 - Fire Sprinkler System Section 220518 - Escutcheons For Plumbing Piping Section 220529 - Hangers And Supports For Plumbing Piping And Equipment Section 220553 - Identification For Plumbing Piping And Equipment Section 220719 - Plumbing Piping Insulation Section 221100 - Water Distribution Systems Section 221102 - Curb Valves And Boxes Section 221116 - Domestic Water Piping Section 221300 - Onsite Wastewater Treatment Systems Section 221316 - Sanitary Waste And Vent Piping Section 223300 - Electric, Domestic-Water Heaters Section 224100 - Plumbing Fixtures Section 230517 - Sleeves And Sleeve Seals For Hvac Piping Section 230529 - Hangers And Supports For Hvac Piping And Equipment Section 230548 - Vibration And Seismic Controls For Hvac Section 230553 - Identification For Hvac Piping And Equipment Section 230593 - Testing, Adjusting, And Balancing For Hvac Section 230713 - Duct Insulation Section 230719 - Hvac Piping Insulation Section 230800 - Commissioning Of HVAC Section 232113 - Hydronic Piping Section 232113.33 - Ground-Loop Heat Exchanger Section 232113.34 - Ground-Loop Heat Exchanger Earthwork Section 232116 - Hydronic Piping Specialties Section 232123 - Hydronic Pumps Section 232500 - Hvac Water Treatment Section 233113 - Metal Ducts Section 233300 - Air Duct Accessories Section 233346 - Flexible Ducts Section 233713 - Diffusers, Registers, And Grilles Section 237213 - Heat Wheel Air-To-Air Energy Recovery Units Section 238126 - Split-System Air-Conditioners Section 238129 - Variable-Refrigerant-Flow Hvac Systems Section 260500 - Common Work Results For Electrical Section 260519 - Low-Voltage Electrical Power Conductors And Cables Section 260523 - Control-Voltage Electrical Power Cables Section 260526 - Grounding And Bonding For Electrical Systems Section 260533 - Raceways And Boxes For Electrical Systems Section 260553 - Identification For Electrical Systems Section 260923 - Lighting Control Devices Section 262713 - Electricity Metering Section 262726 - Wiring Devices Section 262816 - Enclosed Switches

Section 263323 - Central Battery Equipment Section 264313 - Surge Protection For Low-Voltage Electrical Power Circuits Section 265100 - Interior Lighting Section 270500 - Common Work Results For Communications Section 270526 - Grounding And Bonding For Communications Systems Section 270528 - Pathways For Communications Systems Section 270536 - Cable Trays For Communications Systems Section 271100 - Communications Equipment Room Fittings Section 271200 - Communications Copper Network Cabling Section 275116 - Public Address Systems Section 281300 - Access Control System Section 282300 - Video Surveillance Section 284621.13 - Conventional Fire-Alarm Systems Section 311000 - Clearing And Grubbing Section 312000 - Earthwork Section 312010 - Select Borrow Section 312100 - Project Site Preparation And Grading Section 312225 - Excavation & Embankment Section 321200 - Hot-Mix Asphalt Paving Section 321204 - Crushed Aggregate Base Or Surface Course Section 322640 - Pavement Marking Section 322705 - Pavement Sawing Section 323113 - Chain-Link Fences And Gates Section 328000 - Irrigation System Section 329220 - Drainage Structure Section 329310 - Exterior Plants, Landscape Boulders And Topsoil Section 329400 - Landscape Stone, Weed Barrier & Landscape Edging

1.14 OTHER APPLICABLE DOCUMENTS:

A. Green Globes Strategy B. Geotechnical Report for Site, GSH Engineers, October 2018 C. Commissioning Plan, Systematics, April 2019 D. Pre-Demolition Asbestos Inspection and Universal Waste and Hazardous Materials Assesement, prepared by Terracon, December 5, 2018

1. Demolition Work is shown in plans and noted in specifications and includes the following:
2. The BLM has maintenance operations and other facilities at the east of the Forest Service site that shall remain in place and operational during construction. Access to these areas must be maintained during construction.
3. New construction work is shown in the plans and noted in the specifications and includes the following:
1. The contractor shall have full use of the premises for construction operations, including the use of the Project site during the construction period. The Contractor’s use of the premises is limited only by the Government’s right to perform work or...
2. Except as noted herein, the construction site for the new building will be closed to the public during construction. The Contractor will be responsible for fencing, signing and limiting public access. Access shall be maintained to the facilities ...
3. The Contractor shall not disrupt existing utility service (water, power, telecom, sewer, etc.) to and within the compound without coordination and approval in writing from the Contracting Officer’s Representative. Provide 48 hours’ notice prior to ...
4. Water is available at the site for construction purposes. The contractor is responsible for any temporary connection hardware.
5. Electricity is available at the site for construction purposes. The Contractor will be responsible for coordinating the installation of temporary power for the site and the cost for the service.
6. Telephone service is not available, and shall be the contractor’s responsibility.
7. Sewer lines are available to the contractor, if desired.
8. The Contractor shall provide temporary toilet facilities (porta-potties) at the site during all construction work. Toilet facilities shall be provided at a rate of one stool for every 10 workers assigned or working on site with a minimum of one re...
9. All construction equipment shall be pressure washed before entering the Site. The removal of mud and debris from treads, tracks and undercarriage, with emphasis on axles, frame, cross-members, motor mounts, and underneath steps, running boards, an...
10. The contractor shall inform and enforce an “Anti-Idling” policy for vehicles on the site that requires vehicles will not idle for more than 2 minutes on the site. The contractor shall inform subcontractors and deliveries of this policy.
11. Work hours allowed shall be Monday-Friday 7AM-7PM. The contractor may work weekends if needed, 8AM-7PM.
1. The elevation of the site is approximately 6300 feet above sea level. The construction site experiences very cold temperatures with snow on the ground from October to April. Summer temperatures are moderate and rarely exceed 90 degrees.
2. In depth soil surveys have been performed and are available as an attachment to the specifications. See Geotechnical Report, prepared by GSH Engineering, SLC, UT, October 2018.
3. The contractor shall review the water table information included in the geotechnical study.
1. G1: Cover Sheet
2. G2: Drawing Index
3. D101: Site Demolition Plan, Sign Shop Building/ Oil and Gas Building Demolition
4. D102: Maintenance Building Demolition
5. C-01: Existing Site Conditions & Demolition Plan
6. C-02: Site construction and Utility Plan
7. C-03 Site Grading Plan
8. CD-01: Detail Sheet 1
9. CD-02: Detail Sheet 2
10. CD-03: Detail Sheet 3
11. CD-04: Detail Sheet 4
12. CD-05: Detail Sheet 5
13. CD-06: Detail Sheet 6
14. L-01: Landscape Plan
15. L-02: Landscape Berm Layout Plan
16. IR-01: Irrigation Plan
17. IR-02: Irrigation Details
18. D-01: Site ID Sign, Dry Stack Retaining Wall, Berm Construction Details
19. D-02: Bulletin Board, Flag Pole, Bike Rack Details
20. D-03: Picnic Table, Edging, Planting Details
21. G101: Code Analysis
22. GA101: Accessibility Standards
23. A101A: Footing and Foundation Plan A
24. A101B: Footing and Foundation Plan B
25. A102A: Office Floor Plan A
26. A102B: Office Floor Plan B
27. A103A: Framing Floor Plan A
28. A103B: Framing Floor Plan B
29. A104A: Finish Floor Plan A
30. A104B: Finish Floor Plan B
31. A105A: Reflected Ceiling Plan A
32. A105B: Reflected Ceiling Plan B
33. A106A: Roof Plan A
34. A106B: Roof Plan B
35. A201: Office Elevations
36. A202: Office Elevations
37. A301: Building Sections
38. A302: Building Sections
39. A303: Building Sections
40. A304: Building Sections
41. A305: Building Sections
42. A306: Building Sections
43. A401: Enlarged Floor Plans
44. A402: Enlarged Floor Plans
45. A403: Interior Elevations
46. A404: Interior Elevations
47. A405: Interior Elevations
48. A501: Architectural Details
49. A502: Architectural Details
50. A503: Roof Details
51. A504: Roof Details
52. A505: Floor and Ceiling Details
53. A506: Door and Window Details
54. A507: Millwork and Cabinet
55. A508: Millwork and Signage Details
56. A701: Wall Types
57. A801: Door/ Frame Schedules and Types
58. A802: Hardware Schedule
59. A803: Window Elevations
60. A901: Finish Schedule and Legend
61. A902: Accessory Schedule and Signage
62. S001: Structural Notes
63. S002: Structural Notes (Cont)
64. S003: Schedules
65. S004: Schedules
66. S005: Schedules
67. S006: Schedules
68. S101: Footing and Foundation Plan, Grid M to E
69. S102: Footing and Foundation Plan, Grid E to A
70. S103: Roof Framing Plan Grid M to E
71. S104: Roof Framing Plan Grid E to A
72. S105: Entrance Framing Plan
73. S201: Typical Details
74. S202: Typical Details
75. S203: Details
76. S204: Details
77. S205: Details
78. S206: Details
79. S207: Details
80. MS-01: Geothermal Site Plan
81. MS-02: Geothermal Details
82. MS-03 Geothermal Details
83. MS-04: Geothermal Drilling Log
84. P001: Plumbing Legend, Schedules and Notes
85. P101: Plumbing Plan
86. P102: Waste and Vent Plan
87. P401: Enlarged Plumbing Plan
88. P402: Enlarged Waste and Vent Plan
89. P501: Plumbing Details
90. M001: Mechanical Legend, Schedules and Notes
91. M002: Mechanical Legend, Schedules and Notes
92. M101: Mechanical Plan
93. M102: Mechanical Refrigerant Piping Plan
94. M401: Enlarged Mechanical Plans
95. M501: Mechanical Details
96. E001: Electrical Legend, Notes, and Panel Schedules
97. E002: Service Block Diagram and Lighting Controls
98. E003: Lighting Controls, Continued and Main Conference Room AV Details
99. E101: Receptacle Floor Plan
100. E201: Telecommunications Floor Plan
101. E301 : Lighting Floor Plan
102. E401: Mechanical Power
103. E501: Security and Intercom Systems
104. ES001 Electrical Exterior Demolition
105. ES101 Electrical Exterior Site Plan