This document outlines requirements for a federal construction contract solicitation. The United States Department of Agriculture Agricultural Research Service Plains Area Office is seeking to build several shade structures at its Clay Center, Nebraska facility. The contractor will be responsible for providing all labor, equipment, materials and transportation to install shade structures in Areas 42E, 42W and 25, with optional additions for Area 42W and a new hoop barn. Work inside existing pens is restricted from July 1st to September 1st. The contractor must restore all sites to original conditions. The contract has a period of performance of 450 days and a value between $1,000,000 to $5,000,000. Optional additions include additional shade coverage and portable structures.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USDA Clay Center NE Construct Sunshades Bid Schedule

CLIN 0001 BASE BID:

· Preconstruction submittals and documents.

· Installation of poles, columns, and cables for Areas 42E, 42W (southern section) and 25.

· Work inside the pens in Areas 42E and 42W is limited to 1 July to 1 Sept.

· Work inside the pens in Area 25 is limited to 1 July to 20 Sept.

· Architectural, civil and electrical work to provide a complete project.

· Restore site to original conditions.

Period of Performance: 450 days Price / Cost: ___$______________________

CLIN 0002 ALTERNATE 1: Add fabric shade over 42W north and middle sections

· Installation of poles, columns, and cables for Area 42W middle and north sections.

· Work inside the pens in Area 42W is limited to 1 July to 1 Sept.

· Architectural and civil work to provide a complete project.

· Restore site to original conditions.

Additional Period of Performance: 0 days Price / Cost: ______$__________

CLIN 0003 ALTERNATE 2: Provide and construct a 60’ x 80’ hoop barn and associated work

· Installation of foundations, structure, covering and fencing for a new hoop barn at location 18.

· There are no restrictions to when this work can be performed.

· Architectural and civil work to provide a complete project.

· Restore site to original conditions.

Additional Period of Performance: 0 days Price / Cost: ______$__________

CLIN 0004 ALTERNATE 3: Provide 4 portable shade structures

· Provide 4 portable shades structures to location identified on the USDA Clay Center Complex.

· No restrictions on when work can be performed.

Additional Period of Performance: 0 days Price / Cost: ______$_______________