Solicitation #12805B20R0007 Upgrade Electrical Distribution and Lighting
Panels in Buildings 1 & 2
Questions and Answers
1. Q - Are transformers to be set on a concrete pad?
A - All transformers are to be mounted as per manufacturers requirements and per current electrical code.
2. Q - Could you please provide existing panel schedules that were not included in the documents?
A – Bldg 2: Panel L3A: no panel schedule was included because that panel is not to be replaced. It was included in the block diagram for informational purposes only.
3. Q - Attachment 8 has multiple tabs for multiple panels, but Attachment 7 only has 1 tab for 1 panel. Can you please provide all of the panel schedules for Building 1?
A - I will upload an updated Attachment 7 that will contain the missing attachments.