127EAX21Q0041 - Amendment III - 127EAX21Q0041 - Coconino NF Access Heritage Sites GAOA.pdf
PDF 753 KB Posted
- Attached to
- Coconino NF Heritage Site Access Improvements
- Solicitation number
- 127EAX21Q0041
About this file
This is a solicitation amendment for construction services related to improving access and sites on the Coconino National Forest in Arizona. The amendment extends the response deadline to August 31, 2021, provides additional responses to questions from interested offerors, and clarifies specifications. The work includes preparing sites and constructing walkways, viewing platforms, and sidewalks at V Bar V Ranch and Elden Pueblo locations following all applicable accessibility codes. Optional items include site preparation, paving, and striping of the Elden Pueblo parking lot. The solicitation is set aside for small businesses with average annual receipts less than $39.5 million. Offerors must be registered in SAM and submit responses to the contracting officer by the amended deadline. The Department of Agriculture Forest Service R3-Southwestern Region will award a firm fixed-price contract to the best value offer using a lowest-price technically acceptable process.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
127EAX21Q0041
x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
SPRINGERVILLE AZ 85938
30 S CHIRICAHUA DR
PO BOX 640
APACHE SITGREAVES NATIONAL FOREST
USDA FOREST SERVICE
ALBUQUERQUE NM 87102
333 BROADWAY SE
SOUTHWESTERN REGION
GAOA103844308/10/2021
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
08/10/2021
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Amendment III: This solicitation is being amended to:
1. Provide additional responses to RFI & Q&A's received - see pages 3-5
2. DEADLINE EXTENTION: THE DEADLINE FOR RECEIPT OF RESPONSES TO THE RFQ SHALL BE
August 31, 2021 @ 4:00 pm PDT
All Other Terms and Conditions of this Solicitation and Amendment I, II Remain the Same
Continued ...
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
127EAX21Q0041
Contact:
Michelle Bahr Contract Specialist
(928) 333-6278 michelle.l.bahr@usda.gov
In order to be eligible for award of a Federal Contract, potential vendors need to already be registered in the System for Award Management
(SAM) www.sam.gov
Offer Submissions: Offerors shall submit the Return Packet with the required information from Section M of the solicitation. Offers or responses to the solicitation (include the solicitation number in the name of the document) may be sent to the Contracting officer by email:
michelle.l.bahr@usda.gov before the deadline.
The Deadline for receipt of responses to the RFQ shall be 8/31/2021 @ 4:00 pm PDT
Delivery Location Code: 8167
USDA FOREST SERVICE
COCONINO NATIONAL FOREST SO
1824 S THOMPSON ST
FLAGSTAFF AZ 86004 US
FOB: Destination
GAOA Coconino NF Access Heritage Sites
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Amendment III
1. Sheet 2 of the plans indicates that an archeological monitor shall be onsite during excavation activities. Who pays for and schedules the monitor?
No response has been given for this question. A subsequent addendum will be posted prior to closing with the answer.
2. Section 105.02 material sources provides a pit location for borrow materials. Please provide location (site map or GPS coordinates) for the Red Tank Draw and Girdner Pits.
No material is available from Red Tank Draw or Girder Pit, all materials shall be from a commercial source.
Section 105.02, page 119, Revised as follows:
3. No asphalt specifications were found on the asphaltic concrete for Elden Pueblo. Please provide the required asphalt mix to be used on the project (ie ADOT 409, MAG, etc.) including nominal mix size.
All FP-14 are included by reference per the specifications for the project. If a specific section is not in the supplemental specification then the bidders should refer to the main specifications.
The actual mix is called out in the Schedule of Items.
4. The special provisions indicate utilizing the gradations in table 703-2 for the 9” of aggregate base under the paving at Elden Pueblo. There are 5 gradations classifications in this table. Please provide the required gradation designation. Due to the small quantity of aggregate base it is unlikely that any commercial source will setup to produce any of the FP-14 gradations. Will USFS accept a locally available alternative such as MAG ABC or ADOT Class 2 base?
The Schedule of Items for this line items should be updated to include “Grading D” and “compaction D”. There are local sources that do meet this specification which is similar to a MAG ABC. Supplemental specification 301 is included for clarity as well. See page 6
5. The special provisions indicate utilizing the gradations in table 703-3 for the surface course aggregate for the path at V Bar V. There are 6 gradations classifications in this table. Please provide the required gradation designation. Due to the small quantity of surface course aggregate it is unlikely that any commercial source will setup to produce any of the FP-14 gradations. Will USFS accept a locally available alternative? Does USFS have a surface course aggregate supplier that they have used on past projects that could be suggested? Can contact information be provided?
The Schedule of Items for this line item is per the CSI specifications and not FP-14 for surface course.
6. Note 1 on sheet 2 of the plans indicates that USFS has had issues with local material sources in the past and gives the Government the ability to reject materials based upon a visual inspection. Please provide suppliers and contact information for materials that USFS has approved previously.
The contractor shall provide samples of local materials for approval before ordering and delivering to the site.
7. The project plans indicate to “place boulders to carry grade” in the fill areas. The project special provisions has specific sizing requirements for boulders in the fills areas. Will the contractor be required to size boulders/rock excavation to meet all the sizing requirements specified in the special provisions?
Rock boulders used to carry the grade are not subject to FP-14 Rip Rap specifications. It is found under the Schedule of Items for the following line item. The rocks shall be of adequate size and weight to carry any fill required behind them similar to the retaining walls.
301 - Untreated Aggregate Courses 301.03_National_7_17_2017
Add the following to Subsection 301.03:
301.03 General.
Written approval of the roadbed is required before placing aggregate.
For pit run or grid-rolled material, furnish material smaller than the maximum size, no gradation will be required otherwise. After processing on the road, remove all oversize material from the road and dispose as directed by the CO.
Provide additives or binder, if required, at the proportions specified.
Develop and use Government furnished sources according to Section 105.
If the aggregate is produced and stockpiled before placement, handle and stockpile according to Section 314.
301.05_National_7_17_2017
Delete Subsection 301.05 and replace with the following:
301.05 Compacting.
Compact each layer full width. Roll from the sides to the center, parallel to the centerline of the road.
Along curbs, headers, walls, and all places not accessible to the roller, compact the material with approved tampers or compactors.
Compact the aggregate using one of the following methods as specified:
(a) Compaction A. Operating spreading and hauling equipment over the full width of the travelway.
(b) Compaction B. Operate rollers and compact as specified in Subsection 204.11(a)(1).
(c) Compaction C. Moisten or dry the aggregate to a uniform moisture content between 5 and 7 percent based on total dry weight of the mixture. Operate rollers and compact as specified in Subsection 204.11(a)(1).
(d) Compaction D. Compact to a density of at least 95 percent of the maximum density, as determined by AASHTO T 99, method C or D.
(e) Compaction E. Compact to a density of at least 95 per-cent of the maximum density, as determined by AASHTO T 180, method C or D.
For all compaction methods, blade the surface of each layer during the compaction operations to remove irregularities and produce a smooth, even surface. When a density requirement is specified, determine the in place density and moisture content according to AASHTO T 310 or other approved test procedures.