REVISED - Attachment 1. Statement of Work.pdf
PDF 233 KB Posted
- Attached to
- 127EAW24R0017 - Crestline Group CG Renovation
- Solicitation number
- 127EAW24R0017
- Issued by
-
Department of Agriculture Forest Service
About this file
This document is a Statement of Work (SOW) for the Crestline Group Campground Renovation project. The scope of work includes demolition of existing infrastructure and construction of new accessible concrete walkways, pads, and campsite amenities such as picnic tables, benches, grills, and signage. The project also includes installation of new gates, fencing, and a concrete dumpster pad. The work must be performed in a manner to minimize ground disturbance, and a Forest Service archeological or Tribal monitor may be onsite during excavation. The total work time is 60 calendar days.
The related federal contract opportunity is Solicitation Number 127EAW24R0017 for the Crestline Group CG Renovation project on the Cleveland National Forest. It is a Total Small Business Set Aside valued between $250,000 and $500,000. Key dates include a pre-proposal site visit on May 20, 2024 and a request for information deadline of May 21, 2024. The contract will be awarded by the USDA Forest Service.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CRESTLINE GROUP CAMPGROUND RENOVATION
STATEMENT OF WORK SECTION C - 1
REVISED
STATEMENT OF WORK
C.1 SCOPE OF WORK
This project will include, but is not limited to the following:
Crestline Group Campground Renovation Base Bid:
Demolition of existing asphalt walkways, concrete pads, picnic tables, grill, fire ring, benches, campground signage, existing bollards and chain link fencing, and clearing and grubbing.
Construction improvements include, but are not limited to the following; accessible concrete walkways, concrete pads, stabilized decomposed granite walkways and table pads, accessible campsite, tent pads, and installation of new picnic tables, benches, grill, fire pit, bulletin boards, site signage, trash and recycle containers, installation of wood bollards around roadway edge and replacement of chain link fencing on campground boundary, and installation of 6‐inch thick concrete dumpster pad with concrete block retaining wall.
Construction elements include, but are not limited to: site work, surveying, demolition, clearing and grubbing, excavation and placement, compaction, best management practices (BMP’s), aggregate base, portland cement concrete, concrete reinforcement and sampling and testing.
All site improvements shall meet the minimum requirements of Americans With Disabilities Act and Architectural Barriers Act guidelines (ADAABA) and the Forest Service Outdoor Recreation Accessibility Guidelines (FSORAG).
All work shall be performed in a manner to minimize ground disturbance.
Option Item:
New gates related items include construction staking, clearing and grubbing, excavation, compaction, finish grading, concrete foundations, and furnishing and installation of two double swing gates.
All work shall be performed in a manner to minimize ground disturbance.
A Forest Service archeological and/or Tribal monitor may be onsite during ground disturbance and vegetation clearance. The contractor shall work closely with the Contracting Officer Representative to schedule required archeological oversight.
Total work time is 60 calendar days from the issuance of the Notice to Proceed.
C.2 PROJECT LOCATION
Crestline Group Campground– San Diego County, Palomar Ranger District
STATEMENT OF WORK SECTION C - 2
Travel north on I-15, take exit 46 towards CA-76 E. Continue on CA-76 for 20.5 miles. Take slight left onto S6 (South Grade Rd)/Palomar Mountain R. Continue for 6.7 miles, turn right onto S7 (East Grade Rd). Crestline Group Campground will be on the left.
C.3 FOREST CONTACT
For information regarding site conditions, contact Grace Bassett at (619) 984-0804 between the hours of 8:00 am and 4:00 pm, Monday through Friday, except legal holidays.
C.4 PROJECT MANAGEMENT
The contractor shall appoint a Project Manager and/or Engineer to coordinate all Contractor’s activities during construction and to liaise with the Contracting Officer Representative (COR) and/or Contracting Officer (CO), and Project Engineer for the USDA Forest Service. Engineer/Architect and Surveyor shall be licensed in the State of California. Contractor shall designate in writing an on-site superintendent to be on-site at all times that any construction activities take place and to coordinate all site work and activities.
C.5 GENERAL INFORMATION
C.5 - 1 Parking and Storage
The Contractor shall coordinate parking of their vehicles and temporary storage of equipment and materials with the Contracting Officer. Contractor shall have all heavy equipment washed prior to entering the project area to remove soil, seeds and plant material from noxious weeds to prevent the introduction and spread of weeds not already present on Palomar Ranger District or the Cleveland National Forest. Inspections shall be coordinated and scheduled with the Contracting Officer’s Representative.
C.6 SPECIFICATIONS
The Construction Specification Institute (CSI) specifications applicable to this contract are listed below:
00 01 10 TABLE OF CONTENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 31 00 PROJECT MANAGEMENT AND COORDINATION
01 32 23 SURVEY AND LAYOUT DATA
01 33 23 SHOP DRAWINGS, PRODUCT DATA, AND SUBMITTALS
01 40 00 QUALITY REQUIREMENTS
01 41 00 REGULATORY REQUIREMENTS
01 57 24 STORMWATER POLLUTION CONTROL
01 71 13 MOBILIZATION
01 74 00 CLEANING AND WASTE MANAGEMENT
STATEMENT OF WORK SECTION C - 3
01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
02 41 00 DEMOLITION
03 11 00 CONRETE FORMING
03 20 00 CONCRETE REINFORCEMENT
03 30 00 CAST-IN-PLACE CONCRETE
31 10 00 SITE CLEARING
31 20 00 EARTH MOVING
32 30 00 SITE IMPROVEMENTS
32 31 13 CHAIN LINK FENCES AND GATES
33 11 00 WATER UTILITY DISTRIBUTION PIPING
33 12 00 WATER UTILITY DISTRIBUTION EQUIPMENT
33 13 00 DISINFECTING OF WATER UTILITY DISTRIBUTION
C.7 DELIVERABLES
C.7-1 Fire Plan
See the Fire Plan for fire restrictions and requirements, emergency contact information, and fire project activity levels.
C.7-2 Work Plan
The Contractor(s) shall provide the Government with two (2) copies of the Work Plan for the project prior to mobilization. This Work Plan shall include, but is not limited to, the following:
Contractor’s Design Proposal A description of how the work will be performed.
Specific exclusions/ assumptions regarding the specific work to be performed.
A listing of personnel, including subcontractor(s), working on the project.
A list of equipment proposed for use on the project.
A Project Work Schedule.
Detailed cost estimate/ cost breakdown of work to be performed per Specification Section that can be used for partial payments as work is completed and accepted.
Description of what material(s) or method of concrete washout will be used on the project.
C.7-3 Storm Water Management Plan
Contractor shall develop an Erosion Control/Storm Water Control Plan. Contractor shall identify all types and specific locations of erosion control measures.
C.7-4 Construction Waste Management Plan
Contractor shall develop a proposal on how to collect, segregate, and dispose of all construction wastes and debris produced by the work of this contract, including hazardous materials.
STATEMENT OF WORK SECTION C - 4
C.7-5 Spill Prevention Control and Countermeasures (SPCC), spill response plan and an emergency response plan for refueling and servicing vehicles.
Identify and use suitable measures around vehicle service, storage and refueling areas, and waste dumps to fully contain spills and avoid or minimize soil contamination and seepage to groundwater. Use suitable measures to avoid spilling fuels, lubricants, cleaners, and other chemicals during handling and transporting. Report spills to the Contracting Officer’s Representative and initiate suitable cleanup action in accordance with applicable State and Federal laws, rules, and regulations.
C.7-6 Sampling, Testing, and Abatement Work Plan
Contractor shall develop a Sampling, Testing and Abatement Work Plan for lead based paint, asbestos abatement, and contaminated soil from leaking vaults abatement.
END OF STATEMENT OF WORK