Questions.docx
DOCX document 12 KB Posted
- Attached to
- Radio Shelters Federal contract opportunity
- Solicitation number
- 12760419Q0028
About this file
Questions and answers
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| R6_Drake_Peak_NEPA_Memo_WR20193029.pdf | ||
| R9_Ino_Shelter_Request_WR20192953.pdf | ||
| BOM.xlsx | XLSX spreadsheet | |
| R9_Ino_NEPA_LTF_WR20192953.docm | DOCM document | |
| Shelter_PWS_April_8_2019.docx | DOCX document | |
| GPATLMRFY19LifeCycle.docx | DOCX document | |
| R6_Drake_Peak_Shelter_Request_WR20193029.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions: Solicitation 12760419Q0028
Can you please confirm that the Drake Peak site shelter roof pitch can be 4/12? It states 7”?
Roof needs to be concrete, normally thicker at one end to allow water runoff.
Is the solar supplied by others?
2 runs of unistrut installed on roof is required, all other solar equipment is supplied and installed by USFS The Drake Peak shelter states a 12vdc system, no HVAC, this will be a moist interior affecting the interior coating and possible water damage. Will the HVAC by supplied by others?
No HVAC, Bill of materials states Passive fixed louver.
The Ino shelter does not specify vents or an HVAC system. Will this be supplied by others?
The Bill of materials specifies HVAC needed What is the Ino existing shelter made out of?
Fiberglass with 2 steel I beam floor foundation