Attachment A ‐ FR224 SCHEDULE OF ITEMS
B‐ 1 ‐ SCHEDULE OF ITEMS
ITEM
NO.
DESCRIPTION PAY
UNIT
EST.
QTY.
UNIT
PRICE
TOTAL
PRICE
15101 Mobilization Lump Sum 1 $________ $________
15706 Soil Erosion Control, Check Dam Each 2 $________ $________
15713 Soil Erosion & Pollution Control Lump Sum 1 $________ $________
20101 Clearing & Grubbing, Disposal Method F Lump Sum 1 $________ $________
20301 Removal of Pipe Culvert Each 3 $________ $________
20415 Waste Excavation Cubic Yard 150 $________ $________
20801 Structure Excavation Cubic Yard 150 $________ $________
20803 Structural Backfill Cubic Yard 125 $________ $________
25101 Placed Riprap, Method A Cubic Yard 70 $________ $________
25116 Geotextile, Type IV, Class I Square Yard 210 $________ $________
30115 Aggregate Surface Course, Grading G, Compaction Method B
Ton 2925 $________ $________
30120 Pit Run, Max Size 4 Inch, Compaction Method B Ton 725 $________ $________
30301 Ditch Reconditioning Foot 1500 $________ $________
30302 Roadway Reconditioning Foot 4020 $________ $________
60201‐1 18‐Inch Pipe Culvert, Polymer Coated Foot 82 $________ $________
60201‐2 24‐Inch Pipe Culvert, Polymer Coated Foot 90 $________ $________
60201‐3 36‐Inch Pipe Culvert, Polymer Coated Foot 82 $________ $________
60201‐4 60‐Inch Pipe Culvert, Polymer Coated Foot 44 $________ $________
60412 Lead‐Off Ditch Each 14 $________ $________
60520 Granular Backfill Cubic Yard 200 $________ $________
62528 Seeding and Mulching, Dry Method Lump Sum 1 $________ $________
63501 Temporary Traffic Control Lump Sum 1 $________ $________
Total $________
B‐2 ‐ NOTE: Payment for bond premiums in accordance with Clause 52.232‐5, Payments under Fixed‐Price Construction
Contracts, shall not be in addition to the contract price. Include bond payments under 151.01 Mobilization.
Payment will be made on actual work performed as described in FP‐14 109.01 unless otherwise noted.
1. The Standard Specifications for Construction of Roads and Bridges on Federal Highway Project FP‐14 edition has been used for this contract. Copies of this book are available at the USFS engineering office.
2. All clearing, grubbing, bedding, borrow, backfill, detours, diversions, signing, and other miscellaneous items not listed above with unique bid items shall be considered incidental to the contract. See 109.05
3. Quantities for aggregate are compacted in place volumes.
Contractor Duns #