AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE PAGE OF PAGES
1 1
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
0001 7/26/2019
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
USDA Forest Service Lake States Acquisition Team 500 Hanson Lake Road Rhinelander, WI 54501
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
12569R19B0007
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE 7/16/19
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 01 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
(X) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN
THE CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.
The purpose of this solicitation amendment 01 is to make the following changes:
- NCT-1, sheet 2, note 20. Camber requirement has been removed. No camber shall be fabricated into bridge stringers;
- FR227. New schedule of items and sheet 2 (quantity chart) to include the 21” x 15” x 32’ CMPA that was in the plans but missing from the quantities; and
- Identify that all CMP’s and CMPA’s on this project shall be polymer-coated steel.
FR 227 General Notes, FR227 Schedule of Items, and NCT Bridge Sheet 2 are attached. All other terms & conditions remain unchanged.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
Shawn M. Lacina, Contracting Officer
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
7-26-19
(Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
30-105 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
PART I - SCHEDULE OF ITEMS
SECTION B – SERVICES AND PRICES
WI ERFO 2018 Flood Recovery (2)
FR227
Washburn Ranger District
Chequamegon-Nicolet National Forest
Bayfield County, Wisconsin
B- 1 - SCHEDULE OF ITEMS
ITEM
NO.
DESCRIPTION
PAY
UNIT
EST.
QTY.
UNIT
PRICE
TOTAL
PRICE
15101
Mobilization
Lump Sum
15713
Soil Erosion & Pollution Control
20101
Clearing & Grubbing
20301
Removal of Pipe Culvert
Each
20401 Roadway Excavation Cubic Yard 600 $________ $________
20403 Borrow Cubic Yard 420 $________ $________
25101 Riprap, Class IV Cubic Yard 325 $________ $________
25116 Geotextile, Type IV, Class I Square Yard 1225 $________ $________
30115 Aggregate Surface Course, Grading G, Compaction Method B
Ton 2740 $________ $________
30120
Pit Run, Max Size 4 Inch, Compaction Method B
Ton
30301
Ditch Reconditioning
Foot
30302 Roadway Reconditioning Foot 6310 $________ $________
60201A
24-Inch Pipe Culvert
60201B
21-Inch x 15-Inch Elliptical Pipe Culvert
61506
Armoflex Mattress, Ford Crossing
Square Yard
62528 Seeding and Mulching, Dry Method Lump Sum 1 $________ $________
63304 Signs, Aluminum Panels, Type 3 Sheeting Square Foot 20.25 $________ $________
63501 Temporary Traffic Control Lump Sum 1 $________ $________
Total:
Total Without Options:
B-2 - NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction
Contracts, shall not be in addition to the contract price. Include bond payments under 151.01 Mobilization.
Payment will be made on actual work performed as described in FP-14 109.01 unless otherwise noted.
1. The Standard Specifications for Construction of Roads and Bridges on Federal Highway Project FP-14 edition has been used for this contract. Copies of this book are available at the USFS engineering office.
2. Optional bid items will only be awarded based on available funds. Zero or all items or a combination of items may be awarded. Contractor shall provide pricing for all optional items.
3. All clearing, grubbing, bedding, borrow, backfill, detours, diversions, signing, and other miscellaneous items not listed above with unique bid items shall be considered incidental to the contract. See 109.05
4. Quantities for aggregate are compacted in place volumes.
ITEM NO. DESCRIPTION UNITS QUANTITY
15101 MOBILIZATION LPSM 1
15201
CONSTRUCTION SURVEY AND STAKING, METHOD 1,
TOLERANCE CLASS B MILE 0.01
15713 SOIL EROSION AND POLLUTION CONTROL LPSM 1
20305 REMOVAL OF TIMBER SILLS AND EX TIMBER BRIDGE EACH 1
20801 STRUCTURE EXCAVATION CUYD 5
25101 RIPRAP, CLASS IV CUYD 5
25116 GEOTEXTILE, TYPE IV, CLASS I SQYD 19
30110 AGGREGATE SURFACE COURSE, COMPACTION METHOD A TON 5
55703 TREATED STRUCTURAL TIMBER AND LUMBER MFBM 1.976
56401 BEARING DEVICE EACH 6
62528 SEEDING AND MULCHING, DRY METHOD LPSM 1
SUMMARY OF PROJECT QUANTITIES
| Amendment 1 |
| FR 227 - C-01 general notes & quantities |
| FR 227 - Schedule of Items |
| NCT Bridge - Sheet 2 |
| 2019-07-26T10:16:31-0500 | |
| SHAWN LACINA |