This is a Statement of Work (SOW) for perimeter security enhancement at Parking Lot 9 of the Jamie L. Whitten Building in Washington, DC, dated June 20, 2022.
The project objective is to provide greater perimeter security for public events at the farmers market site, which operates weekly from early May through late October. The scope of work includes: (1) relocating two of three existing gate arm systems at both lot entries, reusing the two best systems and salvaging the third, with new concrete pads and underground sensor loops for exit operations; (2) providing active bollard systems at both entries with dual modes—mechanical operation only and combined manual-electrical operation with hydraulic pressure units painted dark green; (3) watering new and existing landscaping plants and trees throughout construction until the first frost with water bags for new trees; (4) installing five streetlights along 12th Street (replacing three existing lights) with identical fixtures and electrical modifications; (5) replacing four building signs at each corner of the Whitten Building, with addresses required only at the southwest and southeast corners; and (6) relocating the Smithsonian sign at the southeast corner if necessary. The construction period shall not exceed 16 months. The contractor must comply with federal, state, and local safety and fire prevention regulations, obtain Hot Work Permits for welding and cutting, provide construction barriers and signs, conduct weekly meetings with distributed minutes, submit daily work reports to the Contracting Officer Representative by 8:00 AM, and provide as-built drawings in hard copy (18"x24") and digital formats (PDF and AutoCAD). Work hours are 6:00 AM to 6:00 PM, with noise-generating activities scheduled after business hours as approved by USDA, other federal agencies, and DC government. The contract is a firm fixed price with all incidental costs included, and the government will only provide water from the People's Garden site; the contractor must provide all other materials and equipment and reimburse USDA for water usage. Payment to workers must meet Department of Labor requirements, whichever is more stringent. The contracting officer and contracting officer representative are the primary USDA contacts, and permits must be obtained from all relevant authorities.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Perimeter Security Enhancement at Parking Lot 9
Jamie L. Whitten Building 1400 Independence Avenue, SW
Washington, DC 20250 06-20-2022
I. BACKGROUND
The Jamie L. Whitten Building (called Whitten for short) is located along the National Mall near the Smithsonian Metrorail stations on Independence Avenue.
Lot 9 is a parking lot that is bound by a landscaped area known as the People’s Garden to the north, the 12th Street to the east, the Whitten Building to the west, and the Independence Avenue to the south. The site hosts a weekly farmers market during the summer and fall, attracting large groups of people. The farmers market opens in early May and ends in later October each year. Lot 9 will be closed for construction in 2023.
II. OBJECTIVES
To provide greater perimeter security for the public events at the farmers market site.
III. SCOPE OF WORK
A. PROJECT DELIVERY
1. Delivery: The contractor shall provide and deliver a firm fixed price which includes all incidental costs to complete the project which meets the requirements of the documents below and the ensuing sections of this Section III. The ensuing sections can be the additional requirements to those which have been included in the documents or completely new items which have not been mentioned in the documents. In case there are conflicts or mismatching of information or of requirements of any kinds among these documents and/or between these documents and the requirements stated in this scope of work, the most stringent information and/or requirements must be used.
1. USDA Whitten Lot 9 100% submission
2. USDA Whitten 100% Spec Submission R2
3. USDA Whitten Building Supplemental Information (for reference only)
4. 20210329 NCPC (for reference only)
5. 8129 Jamie L Whitten Federal Building Public Gathering Area Security Plan Modification (for reference only)
2. This project is a USDA Project: Wherever the terms “GSA” or “government” is mentioned in the bid documents and referenced materials, it is equivalent to mean “USDA.” Therefore, the point of contacts for the project will be USDA’s contracting officer (CO) and USDA’s contracting officer representative (COR). All contract documents and correspondences shall be coordinated and submitted through the USDA CO and COR.
3. Relocate two of the three existing Gate Arm Systems and associated components: Reuse the two best of the three. Salvage and return the last system to USDA. Replace the corner safety bollards with new. Relocate the proximity pass poles and signage. Clean and repaint the poles with two coats. Provide new concrete pads that are large enough to house the gate arm equipment and the corner safety bollards. Coordinate with the trade which performs the demo work to save all control wiring for reuse. Reuse existing control and power wiring for the gate arm to the extent possible. Provide new control and power wiring as required. Provide the new underground sensor loop, like existing loop, on the exit sides of the gate arms. Sequence of Operation: Vehicle that has the government provided proximity pass can enter the parking lot. The control unit at the top of the pole (see photo below) reads the proximity pass and raise the gate arm for the vehicle to pass. On the way out, the underground sensor loop will lift the gate arm for the vehicle to exit. The above work is required at each of the two entries to Lot 9.
One of the three existing gate arm systems. Photo was taken from inside the parking lot looking toward 12 Street.
4. Active Bollard Systems: Provide the most reliable means for the operations of the active bollards. To achieve this goal, provide both modes below for the active bollard equipment at both entries to Lot 9:
Mode 1 – Mechanical Operation Only: operator shall be able to raise or lower the bollards manually at the site without relying on electrical power source.
Mode 2 – Combined Manual and Electrical Operation: provide switches at the site for raising and lowering of the bollards. Operator can activate a switch manually to raise the bollards and another switch to lower them.
Provide a set of switches and associated equipment at each of the gates.
Locate the central hydraulic pressure unit (HPU) at a least visible location.
Coordinate with USDA to determine the spot for the HPU. Paint it dark green, 2 coats. Provide concrete pad.
5. Watering Service for Landscaping Plants and Trees: water the new plants and trees regularly throughout the construction period until the first frost. Water existing plants and trees within the construction zone also. Provide water bags as shown below for new trees.
6. Provide Five (5) Street Lights in lieu of Three (3): provide five (5) streetlights along the 12 Street between Independence Avenue and Jefferson Drive, on USDA side as shown below. Modify the electrical work as required to accomplish this task.
Fix affected plants and trees due to this work. All five lights shall be identical.
7. Replace Building Signs: Provide four building signs, one at each of the corners of the Whitten Building. The signs at the SW and SE corners shall have building address as shown in the above-mentioned documents. Building address is not required for the signs at the NW and NE corners. Protect existing landscaping plants to the extent possible during demo and new work. Provide foundation to support the new signs. Below are the images of the existing building signs for reference.
8. Relocate the Smithsonian Sign at the SE corner as needed if it is in the way of new work (See photo of SE corner above)
B. PERIOD OF PERFORMANCE
The construction period shall not exceed 16 months or as specified in the contract document.
C. SAFETY AND FIRE PREVENTION
The contractor shall comply with all safety and fire prevention rules from Federal, State, and local construction regulations regarding work zone. The contractor shall obtain a “Hot Work Permit” or “burn permit” from USDA prior to performing welding, soldering, or cutting which generates heat and/or flammable debris. The Hot Work Permit shall be kept at the site where work is being performed. Besides fire extinguisher and fire blanket, the Hot Work Permit requires a separate person who must be present at the welding and hot cutting spot to perform the fire watch duty throughout the entire welding and/or hot cutting process.
D. SUBMITTALS
Besides USDA, the contractor shall also submit documents to other oversight authorities such as GSA, DC government, and NCPC if required.
E. AS-BUILT DRAWINGS
The contractor shall provide two (2) hard copies of completed as-built documents where the drawing size shall be 18”x24” and two (2) thumb drives where the drawings shall be in both pdf and AutoCAD formats.
F. SPECIAL CONSIDERATIONS
1. Work can be performed during daytime, between 6:00am to 6:00pm. However, activities which generate excessive noise; vibration; dust; odor, power outages, or any disruption of the normal business of the adjacent USDA buildings; other government buildings; or events at the National Mall; or DC government’s business shall be scheduled after normal business hours at the dates and times which are acceptable to USDA, other Federal Agencies, and DC government.
2. Work which may cause extra cost to the contract must be pre-approved by the contracting officer.
3. Parking is not available at USDA parking lots.
4. No materials will be furnished by the government except water source from the
People Garden site at the north end of Lot 9. Contractor shall provide materials and/or equipment for using this water. Provide water meter to track the usage and reimburse USDA for the cost of water.
5. Conduct weekly meeting, prepare meeting agenda, and distribute meeting minutes to all interested parties.
6. Obtain permits as required from authorities having jurisdiction over the project and the construction site.
7. Provide construction barriers and signs for the safety of the government employees and public throughout the construction period.
8. Attend the pre-bid walkthrough to factor in the existing conditions in bid.
9. Payment to workers shall meet the requirements stated in the contract and the requirements from the Department of Labor, whichever is more stringent. Payment shall be made commensurate with the category of the work that is performed.
10. Submit daily work report (e-mail COR before 8:00AM next day) describing the work being performed, number of workers onsite, time in, time out, problems/issues required attentions, and incidents. Inform COR as soon as possible of issues which impact the workflow.
VI. ATTACHMENT
1. USDA Whitten Lot 9 100% submission
2. USDA Whitten 100% Spec Submission R2
3. USDA Whitten Building Supplemental Information (for reference only)
4. 20210329 NCPC (for reference only)
5. 8129 Jamie L Whitten Federal Building Public Gathering Area Security Plan Modification (for reference only)